Pre-Arbitration Readiness Checklist
A pre arbitration dispute checklist keeps a claim alive before the Request is filed. This guide covers the contract record, evidence preservation, notices and conditions precedent, limitation, parties and urgent relief, so that an ICC arbitration starts on time, under the right clause and with the evidence intact.

Key takeaways
- Under Article 5(2) of the 2026 ICC Rules, the arbitration commences when the Secretariat receives the Request.
- Issue a written preservation instruction as soon as a dispute is reasonably anticipated, before any formal notice.
- Log every contractual pre-arbitral step, its trigger, its duration and the evidence of compliance.
- Calculate limitation under every candidate governing law and check for shorter contractual time bars.
- Decide on respondents, joinder, urgent relief and funding disclosure before filing, not after.
The Pre Arbitration Dispute Checklist in Brief
A pre arbitration dispute checklist is the disciplined review a party carries out between the moment a commercial disagreement hardens and the day a Request for Arbitration reaches the ICC Secretariat. Its purpose is simple: to make sure that the claim is filed in time, under the right clause, against the right parties, after any contractual steps have been completed, and with the evidence still intact. Most procedural disasters in ICC arbitration, from limitation defences to jurisdictional objections, can be traced back to something that was missed in this window.

The 2026 ICC Rules, in force from 1 June 2026, do not regulate what happens before the arbitration starts. Article 5(2) simply provides that the date on which the Secretariat receives the Request is, for all purposes, the date of commencement. Everything that matters before that date is governed by the contract, the law of the seat and the law applicable to the merits. That is why a written checklist, owned by a named person and updated as facts emerge, is worth more than any number of informal discussions.
This note sets out the checklist we recommend to general counsel and in-house teams. It is deliberately practical. It assumes that a dispute exists or is likely, that the contract contains an ICC arbitration clause, and that the business wants to keep its options open while settlement remains possible. For the filing itself, see our core guide to filing a Request for Arbitration.
Step One: Secure the Contract Record and the Arbitration Agreement
Start with the documents that define the relationship. Collect the signed contract, every amendment, side letter, change order, novation or assignment, and any guarantees or parent company undertakings. Confirm which version is operative and whether any later agreement contains a different dispute resolution clause. Projects with several contracts, such as an engineering, procurement and construction contract alongside an operation and maintenance agreement, frequently have clauses that differ on seat, rules or number of arbitrators.
Then read the arbitration agreement itself with care. The review should answer at least the following questions:
- Institution and rules. Does the clause refer to ICC arbitration clearly, or is it pathological? Our guide to multi-tier and escalation clauses explains the common drafting traps.
- Seat, language and governing law. The seat determines the supervising courts and, in many systems, the law that governs the arbitration agreement if the parties have not chosen one.
- Date of the agreement. Under the 2026 Rules the date the arbitration agreement was concluded affects, among other things, whether the expedited procedure applies automatically and at what threshold.
- Pre-arbitral steps. Notices, negotiation periods, mediation, dispute board decisions or expert determination that must come first.
- Contractual time bars. Clauses that require claims to be notified, or arbitration to be commenced, within a fixed period.
Where the clause is ambiguous, record the competing readings and the evidence that supports each. If the counterparty later objects to jurisdiction, the Secretary General may refer the question to the ICC Court under Article 7, and the Court will let the arbitration proceed if it is prima facie satisfied that an arbitration agreement under the Rules may exist. Knowing the weak points early allows the claimant to address them in the Request rather than in a rushed reply.
Evidence Preservation Before Filing
Evidence is lost quietly. Email accounts are deleted when employees leave, project servers are decommissioned, site records are archived by subcontractors and messaging apps auto-delete. A pre arbitration dispute checklist should therefore trigger a written preservation instruction, often called a legal hold, as soon as a dispute is reasonably anticipated.
The instruction should identify the custodians, the systems and the date range, and it should expressly suspend routine deletion. It should cover personal devices and messaging platforms where business was conducted on them, which is now common in construction, commodities and technology disputes. Keep a record of when the instruction was sent, to whom, and what each custodian confirmed. If document production is ordered later, tribunals will expect each party to explain how relevant documents were preserved and searched.
Preservation is different from collection. At this stage the aim is to stop destruction, not to review everything. Targeted collection usually follows: the contract file, key correspondence, meeting minutes, payment records, technical reports and the documents that show when the claimant first knew of the facts giving rise to the claim. That last category matters for limitation. Under the case management techniques set out in the 2026 Note to Parties, tribunals may ask parties to produce with their submissions the documents on which they rely, including documents relating to a prior pre-arbitral step, so organising them early saves time later.
Send the preservation instruction before the first formal notice to the other side. Once a notice of dispute is served, the counterparty will start its own internal review, and your own employees may begin to write emails about the dispute that later have to be disclosed or withheld as privileged. A short instruction on how to communicate about the dispute, and who to copy, reduces that risk.
Witnesses are evidence too. Identify the individuals who negotiated the contract, ran the project or took the key decisions, and check whether they are still employed, whether they are likely to leave and whether any of them has a personal interest in the outcome. Early, privileged interview notes prepared with counsel are often the most reliable record of what happened.
Notices, Conditions Precedent and Time Bars
Many ICC clauses do not allow a party to file immediately. They require a notice of dispute, a period of negotiation between senior executives, a mediation under the ICC Mediation Rules or a decision by a dispute board. Construction contracts based on FIDIC forms add notice requirements for claims that operate as time bars in their own right. Skipping these steps can lead to a stay, a costs sanction or, depending on the clause and the seat, a challenge to the award.
Courts in several leading seats now treat non-compliance with pre-arbitral steps as a question of admissibility for the tribunal rather than a question of jurisdiction for the court. The English Commercial Court took that view in Republic of Sierra Leone v SL Mining Ltd [2021] EWHC 286 (Comm), which arose from an ICC arbitration, and the Hong Kong Court of Final Appeal reached a similar result in C v D (2023). That trend reduces the risk of losing an award, but it does not make the steps optional.
A tribunal can still stay the proceedings or reflect the breach in costs. Our insight on drafting a notice of dispute explains how to satisfy these conditions without losing time.
The pre arbitration dispute checklist should therefore list every contractual step, its trigger, its duration and the evidence that it has been complied with. Where a limitation deadline is close and the contractual process cannot be completed in time, the usual solution is to seek a standstill agreement or to file the Request and invite the tribunal to suspend the proceedings while the steps are completed. Both options should be weighed before the deadline, not on it.
Limitation Checks on the Pre Arbitration Dispute Checklist
Limitation is the item on any pre arbitration dispute checklist that is most often misjudged, because it depends on more than one legal system. The ICC Rules contain no limitation period. The tribunal will apply whatever law governs the question, which may be the law of the contract, the law of the seat or a combination of the two, depending on whether limitation is treated as substantive or procedural.
In England, for example, section 13 of the Arbitration Act 1996 applies the Limitation Acts to arbitral proceedings as they apply to court proceedings. Within the European Union and in the United Kingdom, Article 12(1)(d) of the Rome I Regulation (in the UK, as assimilated into domestic law) treats prescription and limitation of actions as matters for the law applicable to the contract. Other systems characterise limitation differently, and contractual time bars may be shorter still. Our separate note on limitation periods in international arbitration analyses the characterisation question seat by seat.
For the checklist, four practical steps cover most cases:
- Identify every candidate governing law for limitation and calculate the earliest possible expiry date under each.
- Identify the accrual date for each claim, and any rules on knowledge, concealment or acknowledgement that might postpone or restart time.
- Check whether any contractual time bar is shorter than the statutory period and whether the seat's law permits a court to extend it.
- Confirm what act stops time running. Under the ICC Rules, the arbitration commences when the Secretariat receives the Request, but the relevant limitation law may define commencement differently, and a Request for Joinder starts time only for the additional party from its own date of receipt (Article 8(1)).
Remember also that the filing fee must accompany the Request. If it is not paid within the time limit the Secretariat fixes, the file is closed, without prejudice to the claimant's right to file again. A closed file is not the kind of risk to run in the last week of a limitation period.
Parties, Assets, Urgency and Funding
The next block of the checklist concerns who should be in the arbitration and what the claimant needs before the tribunal is constituted.
- Parties. Decide whom to name as respondent and whether any affiliate, guarantor or assignee should be joined. Joinder after the confirmation or appointment of any arbitrator requires the consent of the additional party to the constitution of the tribunal, so it is easier to include parties at the start.
- Assets and enforcement. Identify where the respondent has assets and whether those countries are parties to the New York Convention. An award is only as valuable as the enforcement route behind it.
- Urgency. If assets may be dissipated or evidence destroyed, consider an application to the emergency arbitrator under Appendix IV or to a competent court. Article 29(2) confirms that applying to a court for interim measures before the file reaches the tribunal is not a waiver of the arbitration agreement. Our guide to court-ordered interim relief covers the options by seat.
- Funding and disclosure. If the claim will be funded by a third party, Article 12(6) requires prompt disclosure of the funder's existence and identity. Each party must also file, with its Request or Answer, the list of persons and entities required by Article 12(5) to assist arbitrators with their disclosure.
Budget belongs on the pre arbitration dispute checklist too. The 2026 Schedule of Fees has been restructured, and the amount in dispute drives both the administrative expenses and the arbitrators' fees. A realistic budget, prepared before filing, helps the board decide whether to proceed, settle or seek funding.
Using the Pre Arbitration Dispute Checklist: A Summary Table
The table below condenses the pre arbitration dispute checklist into a single page that can be adapted for internal approval processes.
| Item | Key question | Typical output |
|---|---|---|
| Contract record | Which documents and which arbitration agreement govern each claim? | Indexed contract bundle; clause analysis memo |
| Evidence preservation | Have routine deletion and device turnover been suspended? | Legal hold notice; custodian confirmations |
| Pre-arbitral steps | What notices, negotiation or mediation must come first? | Compliance log with dates and evidence |
| Limitation | What is the earliest possible expiry date under every candidate law? | Limitation memo; diary entries; standstill if needed |
| Parties | Who should be respondent and who may need to be joined? | Party map, including affiliates and guarantors |
| Urgency | Is emergency or court interim relief needed? | Draft application and evidence pack |
| Funding and costs | How will the case be paid for, and what must be disclosed? | Budget; funding term sheet; Article 12 disclosures |
A checklist is only useful if somebody owns it. Assign each line to a named person, set review dates and keep the document privileged by preparing it for the purpose of obtaining legal advice. Revisit it whenever settlement discussions start or stop, because each change in posture can affect limitation, notices and evidence.
Illustration: a hypothetical supplier discovers in month eleven of a twelve-month contractual claims window that its buyer has rejected a final invoice. Its clause requires thirty days of executive negotiation before arbitration. A checklist would flag at once that the negotiation period overlaps the end of the window, prompting the supplier to serve its notice immediately and to seek a written standstill, rather than discovering the clash after the window has closed.
How TRW & Co Helps
We help clients work through the pre-arbitration phase before positions harden and deadlines close. Our teams in Dhaka, London, Dubai, New York, Singapore and Delhi review arbitration agreements and multi-tier clauses, prepare limitation analyses across the candidate governing laws, draft preservation instructions and notices of dispute, and map parties, assets and enforcement routes. Where urgent relief is needed, we prepare emergency arbitrator applications and coordinate court applications at the seat or where assets are located. We act for claimants and respondents, and we keep the checklist under review as settlement discussions develop. To discuss a dispute that may be heading to ICC arbitration, please contact us.
Frequently asked questions
When should a company start a pre-arbitration checklist?
As soon as a dispute is reasonably anticipated, which is often well before any formal notice is served. Early action matters most for evidence preservation and limitation, because documents can be deleted in the ordinary course of business and time may already be running. Starting early also gives the business time to complete any negotiation or mediation steps required by the contract without pressure from an imminent deadline.
Do the ICC Rules contain a limitation period?
No. The 2026 ICC Rules do not set a limitation period for claims. They fix the date of commencement, which is the date the Secretariat receives the Request, but whether a claim is time-barred depends on the applicable law and on any contractual time bar. The tribunal decides which law governs limitation, and different seats characterise the issue differently.
Can a party file an ICC Request before completing negotiation or mediation steps?
It can, but it takes a risk. Depending on the wording of the clause and the seat, the tribunal may stay the arbitration until the steps are completed, order costs against the party that skipped them or, in rarer cases, decline to hear the claim. Where limitation is about to expire, filing protectively and asking the tribunal to suspend the proceedings is often the safer course, ideally after seeking a standstill agreement.
What should a legal hold notice cover?
It should identify the dispute in general terms, the custodians, the systems and devices, and the date range, and it should expressly suspend routine deletion. It should cover messaging applications and personal devices used for business, and it should explain how to communicate about the dispute. Keep records of who received the notice and when, because tribunals may later ask how documents were preserved.
Is urgent relief available before the ICC tribunal is constituted?
Yes. A party may apply to an ICC emergency arbitrator under Appendix IV, subject to its exclusions, or to a competent court. Article 29(2) of the 2026 Rules confirms that a court application for interim measures before the file is transmitted to the tribunal does not infringe or waive the arbitration agreement. Any such application must be notified to the Secretariat without delay.
Sources
General information only, not legal advice. References to the ICC, the ICC Court and the ICC Rules describe their published rules and practice; TRW & Co is independent of the ICC.