This clause builder turns the ICC standard wording into a clause that works for your contract. It takes you step by step through arbitrators, seat, governing law, language, mediation tiers and the expedited, highly expedited and emergency options available under the 2026 ICC Rules, with model wording for each choice.

10 min read Updated
ENFR

Key takeaways

  • Start from the ICC standard clause and keep its broad 'arising out of or in connection with' wording.
  • Name the number of arbitrators, the seat as a city and country, the language and the governing law.
  • State the law of the arbitration agreement expressly; in England it otherwise follows the seat under section 6A.
  • The Expedited Procedure applies automatically up to US$4 million for agreements concluded on or after 1 June 2026.
  • Highly Expedited Arbitration needs all parties' agreement and targets an award within three months of the initial CMC.
  • Tiered clauses need objective time limits and a carve-out for urgent or protective filings.

How to Use This ICC Clause Builder

This clause builder walks you through the decisions that turn the ICC standard wording into a clause that fits your contract: the number of arbitrators, the seat, the governing law, the language, any negotiation or mediation tiers, and the choice between the Expedited Procedure, Highly Expedited Arbitration and the ordinary 2026 ICC Rules. Work through the steps in order, record your choice at each one, and then assemble the building blocks using the template at the end of this page.

ICC arbitration clause drafted with a clause builder checklist covering seat, law, language and expedited options
Each building block of an ICC clause answers one question: who decides, where, under which law, in which language and how fast.

The starting point is always the ICC's own recommended text, published on the ICC arbitration clause page: "All disputes arising out of or in connection with the present contract shall be finally settled under the Rules of Arbitration of the International Chamber of Commerce by one or more arbitrators appointed in accordance with the said Rules." That sentence works on its own. The ICC nevertheless encourages parties to add the number of arbitrators, the place and language of the arbitration and the law governing the contract, and to check for mandatory requirements at the seat and in likely places of enforcement.

The clause builder below is a structured checklist, not a substitute for advice on a particular transaction. Where national law imposes form or content requirements, those requirements prevail over any model wording.

Step 1: Core Wording and the Rules Version

Keep the ICC's operative words intact. "Arising out of or in connection with" is deliberately broad and is read by most leading courts as covering contractual, tortious and statutory claims connected with the contract. Narrower formulations, such as "disputes under this contract", invite arguments about scope that cost time and money before the merits are reached.

Under Article 1(2) of the 2026 ICC Rules, the Rules apply to any arbitration commenced on or after 1 June 2026, unless the parties have agreed to submit to the Rules in effect on an earlier date. A clause that simply refers to "the Rules of Arbitration of the International Chamber of Commerce" therefore picks up whichever version is in force when the Request is filed. Freezing an older version is possible but rarely wise, because it locks the parties out of later improvements such as early determination under Article 30 and electronic communications by default.

The date on which the arbitration agreement was concluded still matters for two features. It sets the Expedited Procedure threshold (Step 5), and the Emergency Arbitrator Provisions do not apply to agreements concluded before 1 January 2012.

Steps 2 and 3: Arbitrators, Seat, Law and Language

Sole arbitrator or three?

If the clause is silent, Article 13(2) provides that the Court appoints a sole arbitrator unless it determines that the dispute warrants three. Parties who want three arbitrators in every case should say so. A sensible compromise for contracts with very different possible claim sizes is a value-based formula, for example a sole arbitrator below an agreed amount and three above it, provided the formula is easy to apply on the day the Request is filed. Remember that, under Article 2(1) of Appendix V, the Court may appoint a sole arbitrator in an expedited case notwithstanding any contrary provision of the arbitration agreement.

Choosing the seat

The seat (the "place of the arbitration") determines the procedural law of the arbitration, the courts that supervise it and the only courts that can set the award aside. If the parties do not agree, Article 19(1) lets the Court fix it. Name a city and a country, for example "London, England" or "Singapore". Hearings may still take place elsewhere or remotely under Article 19(2). Our guide to ICC seats and the page on seat, law and language compare the leading options.

For ICC arbitration seated in Mainland China, the ICC recommends replacing "finally settled under the Rules" with an express submission to "the International Court of Arbitration of the International Chamber of Commerce", so that the institution is clearly identified.

Governing law and language

Add a separate choice of law for the contract. Under Article 22(1), the parties are free to agree on the rules of law applied to the merits; failing agreement, the tribunal applies the rules of law it determines to be appropriate. Article 22(3) allows the tribunal to act as amiable compositeur or decide ex aequo et bono only if the parties have expressly given it those powers.

The law governing the arbitration agreement itself deserves its own sentence. In England, section 6A of the Arbitration Act 1996, inserted by the Arbitration Act 2025, now provides that the arbitration agreement is governed by the law of the seat unless the parties expressly agree otherwise, and a choice of law for the main contract does not by itself count as such an agreement. Other legal systems apply different tests. Stating the law of the arbitration agreement expressly removes a frequent source of satellite litigation; see our explainer on Enka v Chubb for the background.

Finally, fix the language. If the parties have not agreed, Article 21 leaves it to the tribunal, which considers all relevant circumstances, including the language of the contract. Where documents will be in two languages, consider agreeing one language for the proceedings while permitting documents in the other without translation.

Step 4: Negotiation and Mediation Tiers

Escalation clauses can save relationships, but badly drafted tiers create jurisdiction and admissibility fights. If you include them, make every step objective: who must meet, within what period, and what happens when the period expires.

The ICC publishes model mediation clauses. Its sequential clause requires the parties to refer the dispute first to the ICC Mediation Rules and provides that, if the dispute has not been settled within 45 days of the filing of the Request for Mediation (or another agreed period), it is finally settled by ICC arbitration. A separate model allows arbitration to be commenced in parallel with mediation, which protects against limitation and urgency problems. Where the contract uses dispute boards or expert determination, arbitration can serve as the final tier; see multi-tier clauses.

Practical point

A time-limited tier should always say whether a party may start arbitration without completing it when urgent relief is needed or a limitation period is about to expire. One sentence permitting a protective Request for Arbitration, with the proceedings then suspended until the tier ends, avoids most of the disputes that tiered clauses generate.

Step 5: Expedited, Highly Expedited and Emergency Options

Under Article 32, by agreeing to ICC arbitration the parties accept that the Expedited Procedure Provisions in Appendix V take precedence over contrary terms of their clause. Under Article 1(3) of Appendix V, the procedure applies automatically where the amount in dispute does not exceed US$4 million for arbitration agreements concluded on or after 1 June 2026, US$3 million for agreements concluded between 1 January 2021 and 1 June 2026, and US$2 million for agreements concluded between 1 March 2017 and 1 January 2021. The award is due within six months of the initial case management conference. The ICC's model wording lets parties tailor this:

  • Opt out: "The Expedited Procedure Provisions shall not apply."
  • Opt in regardless of value: "The parties agree that the Expedited Procedure Provisions shall apply irrespective of the amount in dispute."
  • Higher ceiling: "The parties agree that the Expedited Procedure Provisions shall apply, provided the amount in dispute does not exceed US$ [amount]."

Highly Expedited Arbitration under Appendix VI is new in 2026 and applies only if all parties agree. It provides for a sole arbitrator, an initial CMC within seven days of the file reaching the tribunal and a final award within three months of that conference. Joinder and consolidation are not permitted, and the parties may agree that the award need not state reasons. The ICC's model clause adds: "The parties agree that the Highly Expedited Arbitration Provisions shall apply", followed by the place and language of arbitration.

The Emergency Arbitrator Provisions in Appendix IV apply by default. To exclude them, the ICC wording is "The Emergency Arbitrator Provisions shall not apply." Excluding them is rarely advisable in commercial contracts, because court relief at the seat or where assets are located may be slower or less predictable.

Step 6: Multi-Contract Projects, Confidentiality and Publication

For a suite of related agreements, use the same ICC clause, seat, language and number of arbitrators in each document. Article 10 allows claims under several contracts in one arbitration, and Article 11 allows consolidation where arbitration agreements are compatible; mismatched clauses are the most common reason those mechanisms fail. Cross-referencing clauses and express consent to joinder and consolidation help further.

The ICC Rules make arbitrators keep matters relating to the arbitration confidential (Article 12(8)) and let the tribunal make confidentiality orders at a party's request (Article 23(3)), but they do not impose a general duty of confidentiality on the parties. If confidentiality matters commercially, add an express undertaking. Separately, under the Note to Parties and Arbitral Tribunals, ICC may publish awards and orders in anonymised form no less than two years after notification unless a party objects. The ICC's model clause wording "No award or procedural order made in the arbitration shall be published" records that objection from the outset.

Assembling the Clause Builder Output

Once every step has been answered, the clause builder output can be assembled in a fixed order. In practice, most negotiated clauses use the clause builder blocks below; the table lists each one, the model wording and the Rules provision it relies on.

Building blockSuggested wordingRules reference
Core submission"All disputes arising out of or in connection with the present contract shall be finally settled under the Rules of Arbitration of the International Chamber of Commerce by one or more arbitrators appointed in accordance with the said Rules."Art. 1
Number of arbitrators"The arbitral tribunal shall consist of [one / three] arbitrator(s)."Art. 13
Seat"The place of arbitration shall be [city, country]."Art. 19
Language"The language of the arbitration shall be [language]."Art. 21
Law of the contract"This contract shall be governed by the laws of [jurisdiction]."Art. 22
Law of the arbitration agreement"This arbitration agreement shall be governed by the laws of [jurisdiction]."Seat law (e.g. s.6A AA 1996)
Expedited choiceOpt-out, opt-in or higher-ceiling wording from Step 5Art. 32, App. V
Highly Expedited"The parties agree that the Highly Expedited Arbitration Provisions shall apply."Art. 33, App. VI
Emergency arbitratorDefault applies; opt-out only if deliberateArt. 31, App. IV
Publication"No award or procedural order made in the arbitration shall be published."Note to Parties

Illustration (hypothetical): a supply agreement between a Bangladeshi manufacturer and a German buyer might combine the core submission, three arbitrators, a Singapore seat, English as the language, German law for the contract, Singapore law for the arbitration agreement, a 45-day ICC mediation tier with a carve-out for urgent relief, and the default Expedited Procedure threshold. Each choice should then be checked against the enforcement law in Bangladesh and Germany before signature.

Before signing, test the clause against the classic defects described in our guide to pathological clauses: a misnamed institution, a seat that conflicts with the rules chosen, an option for either party to litigate, or a tier with no end date. The ICC also publishes a consolidated 2026 clauses document that can be checked alongside this clause builder.

Clause builder checklist before signature

Run this final clause builder checklist on the signing draft, not an earlier version. Late changes to the commercial terms often move the governing law or add a new party without anyone revisiting the dispute resolution clause.

  • Parties: every entity that may need to claim or be claimed against signs the contract containing the clause, or a separate submission agreement. Guarantors and parent companies are frequent gaps.
  • Consistency: no competing jurisdiction clause elsewhere in the contract, its schedules or the general terms incorporated by reference. If court jurisdiction is preserved for specific matters, such as injunctions or debt recovery, say exactly which.
  • State parties: where a state or state-owned entity is involved, confirm authority and any approval needed to arbitrate, and consider an express waiver of immunity from enforcement and execution. Our page on state entities covers the main issues.
  • Enforcement map: list the countries where the counterparty holds assets and confirm that each is a party to the New York Convention and has no local rule that would undermine the clause.
  • Notices: the notices clause gives current email addresses, because the 2026 Rules make electronic communication the default for filings with the Secretariat.

Used this way, the clause builder produces wording that is short, consistent with the rest of the contract and tested against the places where a dispute would actually be fought. A clause builder cannot answer the commercial questions for you, such as how much speed is worth compared with the right to three arbitrators, but it makes sure each of those questions has been asked and answered before signature.

How TRW & Co Helps

We draft and review ICC arbitration clauses for commercial, construction, energy, finance and state contracts. Our teams in Dhaka, London, Dubai, New York, Singapore and Delhi look at each clause from the angle of where a dispute is likely to arise and where an award would need to be enforced. We test seat and governing-law choices against current legislation, align clauses across contract suites, design workable escalation tiers and advise on expedited, highly expedited and emergency options. When a dispute has already arisen, we assess how an existing clause will operate under the 2026 Rules. To discuss a clause or a contract suite, contact our team.

Frequently asked questions

Is the ICC standard clause enough on its own?

It is valid and workable, but it leaves the number of arbitrators, the seat, the language and the governing law to be decided later by the ICC Court or the tribunal. The ICC itself recommends adding those elements. Agreeing them in advance avoids early procedural disputes, reduces cost and gives both parties more certainty about which courts will supervise the arbitration and how the award will be enforced.

Does a clause signed before 1 June 2026 use the 2026 ICC Rules?

Generally yes. Article 1(2) applies the 2026 Rules to arbitrations commenced on or after 1 June 2026 unless the parties agreed to an earlier version. However, the date of the agreement still affects the Expedited Procedure threshold, which is US$3 million for agreements concluded between 1 January 2021 and 1 June 2026, and the Emergency Arbitrator Provisions do not apply to agreements concluded before 1 January 2012.

Should we opt out of the Expedited Procedure?

Only for a clear reason. The procedure keeps lower-value disputes proportionate, with a target award six months after the initial case management conference, and the Court can disapply it where it is inappropriate. Parties sometimes opt out where they always want three arbitrators or expect technically complex claims. The alternative is to raise or lower the ceiling using the ICC's model wording rather than excluding it entirely.

How do we choose between Highly Expedited Arbitration and the Expedited Procedure?

Highly Expedited Arbitration requires express agreement, a sole arbitrator and an award within three months of the initial CMC, with short fixed time limits, no joinder and no consolidation. It suits documents-based disputes needing very fast answers. The Expedited Procedure applies automatically below the threshold, allows a six-month timetable and retains more flexibility for multi-party cases and evidence.

Do ICC Rules make the arbitration confidential?

Not fully. Arbitrators must keep matters relating to the arbitration confidential under Article 12(8), and the tribunal can make confidentiality orders at a party's request under Article 23(3). There is no general confidentiality duty on the parties in the Rules, so add an express undertaking where it matters. The ICC's no-publication wording records an objection to anonymised publication of awards and orders.

Sources

  1. ICC: Arbitration clause (standard and suggested clauses)
  2. ICC 2026 Arbitration Clauses (PDF)
  3. ICC 2026 Arbitration Rules
  4. ICC Mediation clauses
  5. ICC Note to Parties and Arbitral Tribunals on the Conduct of the Arbitration (1 June 2026)
  6. Arbitration Act 2025 (legislation.gov.uk)

General information only, not legal advice. References to the ICC, the ICC Court and the ICC Rules describe their published rules and practice; TRW & Co is independent of the ICC.