ICC Dispute Boards: DRB, DAB and CDB Models

Dispute boards help parties to long-term contracts avoid and resolve disagreements while the work continues. This guide explains the ICC Dispute Board Rules, the differences between review, adjudication and combined boards, the referral timetable, how conclusions become binding, the Centre's services and fees, and the link with FIDIC and ICC arbitration.

10 min read Updated
ENFR

Key takeaways

  • The ICC Dispute Board Rules took effect on 1 October 2015, with appendices in force from 1 October 2018.
  • DABs issue decisions binding on receipt; DRBs issue recommendations that bind only if no one objects within 30 days.
  • Boards must issue conclusions within 90 days of the referral, with limited extensions.
  • Non-compliance can go straight to arbitration, and merits arguments are no defence to a failure to comply.
  • ICC decides challenges to FIDIC 2017 DAAB members under Appendix III to the Rules.

What ICC dispute boards are

Dispute boards are standing panels of one, three or more independent members, usually set up at the start of a long-term contract, that help the parties avoid and resolve disagreements as the project proceeds. The ICC Dispute Board Rules, in force since 1 October 2015 with appendices in force since 1 October 2018, provide a complete framework for dispute boards in construction, infrastructure, energy, shipbuilding, technology and other long-term contracts. They replaced the original 2004 ICC rules.

Members of ICC dispute boards on a site visit reviewing progress with contractor and owner representatives
Dispute boards follow a project from the start, using site visits and regular meetings to head off disagreements.

Under Article 1(2) of the Rules, a dispute board is not an arbitral tribunal and its conclusions are not enforceable like arbitral awards. Instead, the parties agree in their contract to be bound by the board's conclusions under the conditions the Rules set out. The board's authority is contractual, and its effectiveness depends on that contractual commitment being well drafted and backed by an arbitration clause that allows non-compliance to be dealt with quickly.

The Rules can be used without any involvement of ICC. However, the ICC International Centre for ADR (the Centre) offers administrative services that make them more robust: appointing board members when the parties cannot agree, deciding challenges, fixing members' fees where requested, and reviewing draft decisions. The full text is available in the ICC Dispute Board Rules booklet.

Dispute boards add most value on projects that run for several years, involve many interfaces and variations, and depend on continued cash flow. They are common on large infrastructure, power and transport projects, including those financed by development banks, where stopping work to arbitrate each disagreement would be ruinous. On short, low-value contracts, the standing cost of a board may outweigh its benefits, and an ad hoc adjudication or expert procedure may be more proportionate.

DRB, DAB and CDB: three models of ICC dispute boards

The Rules require the parties to choose, normally when they sign the contract, between three types of board (Article 3). They differ in the type of conclusion the board issues on a formal referral.

ModelConclusion issuedEffect on receiptIf no notice of dissatisfaction within 30 days
Dispute Review Board (DRB), Article 4RecommendationParties may comply voluntarily but need notBecomes final and binding; parties must comply without delay
Dispute Adjudication Board (DAB), Article 5DecisionBinding on receipt; must be complied with without delay, even if a party is dissatisfiedRemains binding and becomes final
Combined Dispute Board (CDB), Article 6Recommendation by default; Decision if requested and not opposed, or if the board so decidesAs for a DRB or DAB, depending on the conclusion issuedAs for a DRB or DAB

For a CDB, if one party requests a decision and the other objects, the board decides which type of conclusion to issue. Article 6(3) lists the factors it must consider, including whether a decision would facilitate performance of the contract or prevent substantial loss or harm, whether it would prevent disruption of the contract, and whether it is necessary to preserve evidence.

The choice of model is a commercial one. DABs give the most immediate certainty and are familiar from FIDIC contracts. DRBs suit relationships where the parties prefer persuasion to compulsion, and where a public owner may be reluctant to accept a binding interim decision. CDBs give flexibility at the price of an additional argument about which type of conclusion should be issued.

Choosing members matters as much as choosing the model. A three-member board often combines an engineer or quantity surveyor with project experience, a lawyer familiar with the contract form, and a chair trusted by both sides for judgement and process management. Availability is critical, because members must attend regular meetings and site visits throughout the project. Parties should also consider language, familiarity with the local legal and regulatory environment, and the absence of any relationship with the owner, contractor, engineer or lenders.

How ICC dispute boards work in practice

The 2015 Rules spell out three functions of equal value. Under Article 16, when the board perceives a potential disagreement, it may raise it and encourage the parties to resolve it themselves. Under Article 17, with the agreement of all parties, it may give informal assistance: a conversation, informal views or a written note. Under Article 18, any party may formally refer a disagreement for a conclusion, at which point it becomes a "Dispute" and informal contacts must stop.

Informal assistance is protected. Under Article 17(3), if the board later has to issue a conclusion on the same matter, it is not bound by any views it expressed informally and may not take into account information that was not available to all parties. The system depends on information flowing to the board: Article 11 requires the parties to cooperate fully, keep the board informed through progress reports, meetings and site visits, and provide working facilities during visits. A board that receives regular, candid reporting can spot problems before positions harden.

Establishment and meetings

Unless agreed otherwise, a board has three members (Article 7(2)). The parties jointly appoint the sole member, or the first two members, within 30 days after signing the contract or after performance begins, whichever is earlier, failing which the Centre appoints on request. The first two members propose the third, who chairs the board unless otherwise agreed. Each member signs a statement of acceptance, availability, impartiality and independence (Article 8). Where site visits are relevant, there must be at least three per year unless the parties and the board agree otherwise (Article 12), and urgent meetings should be accommodated, using best efforts, within 30 days.

Formal referral

The referring party submits a concise Statement of Case (Article 19); the date of its receipt by the sole member or president is the Date of Commencement. The other party responds within 30 days (Article 20), and a hearing is normally held within 15 days of the Response (Article 21). The board must issue its conclusion within 90 days of the Date of Commencement (Article 22), extendable by agreement or, without agreement, by no more than 20 days in total. Conclusions must state findings and reasons (Article 24), and can be corrected or interpreted within 30-day windows (Article 26).

Two further features stand out. Under Article 15 the board may decide on provisional relief, including interim or conservatory measures. And under Article 9(3), unless all parties agree otherwise in writing, a board member may not act as judge, arbitrator, expert or party representative in later proceedings relating to the contract, which protects the candour of informal exchanges.

Binding effect and enforcement of dispute board conclusions

The 2015 Rules strengthened compliance in two ways. They use the express language of "final" and "binding", and they prevent a party from defending a failure to comply by attacking the merits. Under Articles 4(4) and 5(4), a party that fails to comply with a binding recommendation or decision "shall not raise any issue as to the merits" as a defence to its failure to comply.

Equally important, the failure itself may be referred directly to arbitration (or to court, if there is no arbitration agreement) without first going back to the board. That allows a claim for compliance to proceed separately from any substantive challenge to the decision. In ICC arbitration under the 2026 Rules, such a claim may be suited to interim relief under Article 29, a partial award, or an application for early determination under Article 30 where the only defence offered is a manifestly unmeritorious attack on the decision's merits. Whether those routes are available depends on the tribunal's assessment and the law of the seat.

Where a party gives a timely notice of dissatisfaction with a DAB decision, the dispute is finally settled by arbitration, but under Article 5(6) the parties remain bound to comply with the decision until the arbitration or court decides otherwise. A dissatisfied party must therefore pay now and argue later.

For the receiving party, practical preparation pays off. Keep a clear record of receipt of the decision, any notice of dissatisfaction and any demand for payment. Quantify what is due under the decision precisely, including any interest provided for in the contract. When filing the Request for Arbitration, consider framing the compliance claim separately from any merits dispute, so that the tribunal can deal with it first. Where the paying party is a public entity, check whether budget or approval procedures explain the delay, as that may point to a negotiated payment timetable rather than contested proceedings.

Article 27 also provides that, unless otherwise agreed, conclusions and any separate dissenting statements are admissible in later judicial or arbitral proceedings between the same parties.

Practical point

Calendar the 30-day dissatisfaction period from receipt of every conclusion. Missing it makes a recommendation or decision final and binding, with an agreement not to contest it. If you are dissatisfied, serve a written notice on the other party and the board within the period, and give brief reasons, since the board may ask for them if none are given.

Enforcement questions for FIDIC DAAB decisions, including how arbitral tribunals and national courts have dealt with non-payment, are considered in our insight on enforcing DAAB decisions through arbitration.

Centre services, decision review and costs

The Centre's services are optional and are charged separately. A distinctive one is review of decisions. Where the parties have agreed that DAB or CDB decisions will be reviewed by ICC, the board submits its draft decision to the Centre before signature (Article 23). The Centre may require changes only to the form of the decision, and no decision can be signed or communicated until approved. The Centre must normally complete its review within 30 days (Article 22(2)), and the time limit for the decision is extended accordingly.

Fees under Appendix II to the Rules, as published, are as follows; check with ICC before relying on them.

  • Appointment of a member: filing fee of US$5,000 per member, non-refundable.
  • Challenge of a member: filing fee of US$5,000, credited to administrative expenses of up to US$10,000.
  • Review of a decision: filing fee of US$5,000, credited to administrative expenses of up to US$10,000.
  • Fixing members' fees: filing fee of US$5,000.

Board members themselves are paid by the parties under the board member agreement. Unless that agreement says otherwise, each member receives a monthly management fee for staying conversant with the project, equal by default to three times the daily fee (Article 29), plus a daily fee for meetings, site visits, travel and work on referrals (Article 30). Those standing costs are the main objection to dispute boards on smaller projects, and need to be weighed against the cost of disputes that the board helps avoid.

FIDIC contracts and ICC dispute boards

Many users meet ICC dispute boards through FIDIC contracts rather than the ICC Rules themselves. The 2017 FIDIC suite uses a Dispute Avoidance/Adjudication Board (DAAB), and Rule 11 of the 2017 FIDIC DAAB Procedural Rules provides for challenges to DAAB members to be decided by ICC. Appendix III to the ICC Dispute Board Rules sets out that procedure: a challenge must be submitted to the Centre within 21 days of learning of the relevant facts, the Centre invites comments, and its decision is final and conclusive. The filing fee is US$5,000, credited to administrative expenses of up to US$15,000.

FIDIC contracts commonly also name ICC arbitration as the final tier after the DAAB. Our pages on construction and FIDIC disputes and FIDIC Clause 21 from DAAB to ICC explain the sequence, including the notice requirements that must be satisfied before arbitration can begin.

Illustration (hypothetical): on a ten-year port concession, the owner and operator establish a three-member CDB under the ICC Rules, with ICC review of decisions. During construction the contractor seeks a decision on a disputed variation affecting cash flow. The owner objects, preferring a recommendation. The CDB weighs the urgency and the risk of disruption, issues a decision, and the owner, though dissatisfied, pays while referring the merits to ICC arbitration within the contractual period.

Drafting dispute board clauses

ICC publishes standard dispute board clauses for each of the three models, each providing for ICC arbitration as the final step. When adapting them, parties should address:

  • the model (DRB, DAB or CDB) and the number of members;
  • the timetable for appointing members and the Centre's role in default;
  • whether the Centre will review decisions;
  • which disputes may be referred, and whether some categories go directly to arbitration;
  • how the 30-day dissatisfaction period interacts with any contractual time bars and with the arbitration clause;
  • whether the board continues after completion, or is disbanded, and what happens to disputes arising later (Article 14(4) sends them to arbitration).

Consistency is essential. A dispute board clause that conflicts with the contract's notice provisions or its arbitration clause can generate jurisdictional arguments that defeat the purpose of having a board. Our guidance on multi-tier clauses explains how to make each tier enforceable.

Public owners need particular care. Procurement rules or financing conditions may prescribe the dispute board model, the appointing authority or the final forum, and an owner's internal approvals may be needed before it can pay a binding decision. Building those realities into the clause, for example by specifying payment mechanics and the consequence of non-payment, makes the board's decisions more credible on both sides.

How TRW & Co helps

We advise owners, contractors, lenders and operators on dispute boards throughout the project life cycle. We help clients choose between DRB, DAB and CDB models, draft dispute board and arbitration clauses that work together, and select board members. During projects we prepare Statements of Case and Responses, represent clients at hearings, advise on notices of dissatisfaction and time bars, and pursue or defend claims for non-compliance in ICC arbitration. Our teams in Dhaka, London, Dubai, New York, Singapore and Delhi work on infrastructure and energy projects across South Asia, the Middle East and beyond. To discuss a project or referral, please contact us.

Frequently asked questions

Are dispute board decisions enforceable like arbitral awards?

No. Article 1(2) of the ICC Dispute Board Rules states that dispute boards are not arbitral tribunals and their conclusions are not enforceable like awards. The parties agree contractually to be bound. If a party fails to comply, the other may refer that failure directly to arbitration, and an arbitral award ordering compliance can then be enforced in the usual way.

What is the difference between a DAB and a DRB?

A DAB issues decisions that are binding on receipt and must be complied with immediately, even if a party serves a notice of dissatisfaction. A DRB issues recommendations that the parties may follow voluntarily; a recommendation becomes final and binding only if no party serves a notice of dissatisfaction within 30 days. A CDB normally issues recommendations but can issue decisions in defined circumstances.

How long does a dispute board referral take?

Under the ICC Rules, the response is due within 30 days of the Statement of Case, a hearing is normally held within 15 days of the response, and the conclusion must be issued within 90 days of the Date of Commencement. The board may extend that time by agreement or, without agreement, by up to 20 days in total. ICC review of a decision adds up to around 30 days.

Does ICC have to be involved if we use its Dispute Board Rules?

No. The Rules can be applied without any ICC involvement. The ICC International Centre for ADR offers optional services: appointing members if the parties fail to do so, deciding challenges, fixing members' fees on request, and reviewing draft decisions where the contract provides for it. Each service carries a filing fee under Appendix II.

What role does ICC play in FIDIC DAAB challenges?

Rule 11 of the 2017 FIDIC DAAB Procedural Rules provides for challenges to DAAB members to be decided by ICC. Appendix III to the ICC Dispute Board Rules governs the procedure: the challenge must be filed within 21 days of learning of the facts, the Centre invites comments, and its decision is final and conclusive. A US$5,000 filing fee applies.

Sources

  1. ICC Dispute Board Rules (2015, with 2018 Appendices)
  2. ICC Dispute Board Rules overview (iccwbo.org)
  3. ICC standard dispute board clauses
  4. ICC 2026 Arbitration Rules, Articles 29 and 30

General information only, not legal advice. References to the ICC, the ICC Court and the ICC Rules describe their published rules and practice; TRW & Co is independent of the ICC.