Construction and FIDIC Disputes in ICC Arbitration

FIDIC construction disputes pass through notices, Engineer's determinations and the DAAB before reaching ICC arbitration as the final tier. This guide explains Clauses 20 and 21 of the 2017 forms, the 2022 amendments, enforcement of DAAB decisions and how the 2026 ICC Rules shape the arbitration.

10 min read Updated
ENFR

Key takeaways

  • FIDIC 2017 Clause 21 sends disputes through the DAAB and amicable settlement to ICC arbitration.
  • Notices of Claim are due within 28 days of awareness; late notice can extinguish entitlement.
  • DAAB decisions are due within 84 days, bind the parties at once and become final without a 28-day NOD.
  • Failure to comply with a DAAB decision can be referred directly to arbitration under Sub-Clause 21.7.
  • Construction and engineering accounted for 28% of new ICC cases filed in 2025.
  • The 2026 ICC Rules add early determination and a US$4m expedited threshold for new agreements.

How FIDIC construction disputes reach ICC arbitration

FIDIC construction disputes follow a tiered path written into the contract. Under the 2017 Second Editions of the Red, Yellow and Silver Books, a claim is first notified and decided through the Engineer's (or Employer's) agreement or determination procedure; a dispute is then referred to the Dispute Avoidance/Adjudication Board (DAAB), which decides within 84 days; a party dissatisfied with the decision gives a Notice of Dissatisfaction within 28 days; the parties have a short window for amicable settlement; and the dispute is finally resolved by arbitration under the ICC Rules under Sub-Clause 21.6. The 1999 First Editions follow a similar structure under Clause 20.

Infrastructure construction site with engineers reviewing documents in a FIDIC construction dispute
FIDIC construction disputes move from claim notice to Engineer's determination, DAAB decision and, finally, ICC arbitration.

The ICC is therefore the default final tier for a large share of international construction work. Construction and engineering is consistently the largest sector in the ICC caseload: the ICC's 2025 statistics attribute 28% of new cases filed that year to the sector, ahead of energy at 15%. Many of those cases arise from FIDIC-based contracts, often amended by particular conditions, used on projects financed by development banks and governments.

Understanding the contractual machinery matters because tribunals take it seriously. Missed notices, unreferred disputes and ignored DAAB decisions shape what an ICC tribunal can decide and when. This page explains the main steps, how they interact with the 2026 ICC Rules and the practical points for employers and contractors. Our overview of sector guidance places construction alongside the other industries we cover.

Claims, notices and time bars

Clause 20 of the 2017 forms sets out a single claims procedure for both parties. A party that considers itself entitled to additional time or money must give a Notice of Claim as soon as practicable and no later than 28 days after it became aware, or should have become aware, of the relevant event or circumstance. If it does not, it loses its entitlement, subject to the procedures in Clause 20 under which the Engineer must respond to a notice it considers late and the lateness may in some circumstances be reviewed. A fully detailed claim must then generally follow within 84 days, unless a different period is agreed.

Sub-Clause 20.2.3 adds an obligation to keep contemporary records needed to substantiate the claim, and the Engineer may monitor them. In practice, those records become the core of the evidence in any later arbitration, so they should be organised from the first notice rather than assembled after a dispute crystallises.

The Engineer then proceeds under Sub-Clause 3.7 to seek agreement and, failing agreement, to make a fair determination within the contractual time limit. A party dissatisfied with the determination must give a Notice of Dissatisfaction within 28 days; otherwise the determination becomes final and binding. The 2022 amendments published by FIDIC, which took effect on 1 January 2023, revised the definition of "Dispute" and parts of Sub-Clauses 3.7 and 20.1 to clarify how claims become disputes.

Time bars are a frequent battleground in FIDIC construction disputes. Their effect depends on the governing law as well as the contract: some legal systems enforce such clauses strictly, others treat them through doctrines such as good faith, waiver, prevention or abuse of rights. A tribunal will usually decide those questions with the benefit of expert evidence on the governing law. Our insight on construction time-bar notices discusses the main approaches.

The DAAB in FIDIC construction disputes: decisions and compliance

Clause 21 of the 2017 forms provides for a standing DAAB appointed at the start of the project, with a role in avoiding disputes as well as deciding them. Sub-Clause 21.3 allows the parties jointly to ask the DAAB for informal assistance. Under Sub-Clause 21.4, a dispute is referred to the DAAB, which must give its reasoned decision within 84 days unless the parties agree otherwise. The decision is binding on the parties, who must promptly comply with it whether or not a Notice of Dissatisfaction is given, and it becomes final and binding if no such notice is given within 28 days.

Step1999 forms (Clause 20)2017 forms (Clauses 20 and 21)
Notice of claimSub-Clause 20.1: 28 days from awarenessSub-Clause 20.2.1: 28 days from awareness, for both parties
BoardDispute Adjudication Board (DAB); standing for the Red Book, ad hoc for the Yellow and Silver BooksDispute Avoidance/Adjudication Board (DAAB), standing in all three Books
Board decisionWithin 84 days of referral (Sub-Clause 20.4)Within 84 days of referral (Sub-Clause 21.4)
Notice of DissatisfactionWithin 28 days of the decisionWithin 28 days of the decision
Amicable settlementArbitration may start on or after the 56th day after the notice (Sub-Clause 20.5)Arbitration may start on or after the 28th day after the notice (Sub-Clause 21.5)
Final tierICC arbitration, three arbitrators unless otherwise agreed (Sub-Clause 20.6)ICC arbitration, three arbitrators unless otherwise agreed (Sub-Clause 21.6)
Non-compliance with decisionSub-Clause 20.7 (final and binding decisions)Sub-Clause 21.7 covers binding and final decisions; tribunal may use summary or other expedited procedures

The 2022 amendments changed Sub-Clause 21.2 so that, if a party fails to appoint a DAAB member or agree the DAAB terms, either party may apply to the President of FIDIC, or a person appointed by the President, to make the appointment. They also added situations, such as certain payment and termination disputes, in which a dispute is deemed to have arisen without a Notice of Dissatisfaction.

Enforcing a binding but non-final decision

The leading appellate decision on the 1999 forms is PT Perusahaan Gas Negara (Persero) TBK v CRW Joint Operation [2015] SGCA 30. The Singapore Court of Appeal, by a majority, held that the obligation to comply promptly with a binding DAB decision is distinct from the underlying dispute, that a failure to comply may be referred directly to arbitration, and that an ICC tribunal may make an interim or partial award finally disposing of the compliance issue while the merits continue.

The case was the second round of the dispute: in 2011 the same court had upheld the setting aside of an earlier final award that ordered payment of the DAB sum without the tribunal also addressing the merits, which is why the structure of the second award mattered. The 2017 forms codify the approach approved in 2015 in Sub-Clause 21.7. Our insight on enforcing DAAB decisions explains the strategy.

For a party holding a favourable DAAB decision, the practical lesson is to frame the request carefully: ask for an award on the obligation to comply, expressly without prejudice to the other side's right to have the merits finally determined, and ask the tribunal to say so in the dispositive part. That structure helps the award withstand a later challenge at the seat or resistance at the enforcement stage.

Amicable settlement and starting the arbitration

After a Notice of Dissatisfaction, Sub-Clause 21.5 requires the parties to attempt amicable settlement, but arbitration may be commenced on or after the 28th day after the notice even if no attempt has been made. The window is short, so settlement efforts are often more productive if they begin while the DAAB referral is still pending. Mediation under the ICC Mediation Rules, or a without-prejudice meeting of senior executives, can be run in parallel with preparation of the Request for Arbitration. Our insight on moving from the DAAB to ICC arbitration sets out the sequence.

The ICC also offers its own dispute board rules for projects that do not use the FIDIC DAAB, with models that make recommendations, decisions, or a combination of both; see our page on ICC dispute boards. On FIDIC projects the contractual DAAB procedure in Clause 21 and the DAAB Procedural Rules annexed to the contract take precedence.

FIDIC construction disputes under the 2026 ICC Rules

Sub-Clause 21.6 refers disputes to arbitration under the ICC Rules. Under Article 1(2) of the 2026 Rules, an arbitration commenced on or after 1 June 2026 is conducted under the 2026 Rules unless the parties agreed to the Rules in effect on an earlier date. Several features matter in FIDIC construction disputes.

  • Expedited procedure. Under Appendix V, the expedited procedure applies automatically where the amount in dispute does not exceed US$4 million for agreements concluded on or after 1 June 2026 (US$3 million for 2021 to 2026 agreements, US$2 million for 2017 to 2020 agreements), unless the parties opt out. Article 2(1) of Appendix V allows the Court to appoint a sole arbitrator notwithstanding a contractual provision for three. See our page on the expedited procedure.
  • Multi-party and multi-contract cases. Article 8 (joinder), Article 10 (multiple contracts) and Article 11 (consolidation) help where subcontracts, joint venture agreements and guarantees are involved.
  • Early determination. Article 30 allows applications for early determination of claims or defences that are manifestly without merit, which may be used to test clearly hopeless claims, though contested time-bar defences will often require evidence.
  • Experts. Article 26(3) allows the tribunal to appoint its own experts after consulting the parties, in addition to party-appointed delay and quantum experts.
  • Interim measures. Article 29 allows the tribunal to order conservatory and interim measures, for example in relation to performance bonds, and Article 31 with Appendix IV provides for an emergency arbitrator before the tribunal is constituted.

Procedure after constitution of the tribunal is also relevant. Under Article 24(1) of the 2026 Rules, the tribunal must hold a first case management conference within 30 days of receiving the file, and Terms of Reference are now optional rather than mandatory. In construction cases, the first conference is the natural moment to agree the sequence of pleadings, the scope of document production, the timetable for delay and quantum expert reports, and whether a site visit or a virtual inspection is useful.

Parties drafting particular conditions can tailor these defaults, for example by opting out of the expedited procedure for a major project or by opting into the new Highly Expedited Arbitration track in Appendix VI for disputes suited to a very short timetable.

Recurring issues in FIDIC construction disputes

Beyond delay and disruption, certain issues recur across FIDIC construction disputes, whatever the project.

  • Performance and advance payment securities. Demand guarantees supporting the contract, often subject to the ICC Uniform Rules for Demand Guarantees, can be called independently of the underlying dispute. Applications to restrain an allegedly abusive call are usually made to national courts, though tribunals may also consider interim measures between the contract parties.
  • Delay damages. Disputes over the Employer's entitlement to delay damages under Sub-Clause 8.8 of the 2017 forms, and whether extensions of time should have been granted, are frequently intertwined.
  • Exceptional Events. The 2017 forms replaced the 1999 force majeure clause with Clause 18 on Exceptional Events, which governs notice, relief and termination when qualifying events prevent performance.
  • Termination. Termination by the Employer under Clause 15 or by the Contractor under Clause 16 is often contested, and the 2022 amendments treat certain disputed termination notices as deemed disputes.
  • Variations and the Engineer's role. Claims that instructions amounted to variations under Clause 13, and complaints about the Engineer's neutrality in determinations, feature in many cases.

On projects financed by multilateral development banks, the contract may be based on a FIDIC edition harmonised with the banks' requirements, with specific dispute board and arbitration provisions. Those terms should be read as carefully as the general conditions, because they may change the institution, the seat or the steps before arbitration.

Delay, disruption and quantum evidence

Most FIDIC construction disputes are ultimately about time and money: extensions of time, prolongation costs, acceleration, disruption, variations, defects and liquidated damages. Those claims are won or lost on records and expert analysis. Tribunals expect contemporaneous programmes, progress reports, site diaries, correspondence and cost records, and they scrutinise the delay methodology used to link events to completion dates.

Delay experts commonly apply recognised methods such as as-planned versus as-built analysis, time impact analysis or windows analysis, and many refer to the Society of Construction Law Delay and Disruption Protocol as a reference point. Concurrent delay, float ownership and the treatment of disruption are frequent areas of disagreement, and the governing law can affect the answer. Our insight on delay and disruption claims covers the main methods.

Quantum evidence must be equally disciplined. Global claims are difficult to sustain where causation can be broken down, and tribunals often ask experts to meet, produce joint statements and identify the issues that genuinely divide them. Witness conferencing of experts can be efficient when issues are narrowed in advance.

Practical strategy for employers and contractors

The parties' conduct during the project usually decides FIDIC construction disputes long before any hearing. The following steps reflect how we advise clients on both sides.

  1. Diarise every contractual time limit. Notices of claim, fully detailed claims, Notices of Dissatisfaction and referrals should be tracked centrally, with legal review of significant notices.
  2. Constitute the DAAB early. A standing DAAB that knows the project is more useful, and the 2022 appointment mechanism reduces scope for delay.
  3. Comply with binding decisions. Non-compliance invites a Sub-Clause 21.7 referral and may weaken a party's position before the tribunal.
  4. Preserve records. Programmes, native files and correspondence should be preserved in a form that experts can use.
  5. Review the particular conditions. Amendments to Clauses 20 and 21, the seat, governing law and language often differ from the general conditions.
  6. Plan for enforcement. On projects with state employers, check capacity, approvals and immunity waivers at signature.
Practical point

Before commencing ICC arbitration, confirm that every dispute in the Request has passed through the contractual tiers, or falls within an exception such as Sub-Clause 21.7 or the deemed disputes added in 2022. A Request that bundles referred and unreferred disputes invites jurisdictional or admissibility objections and can delay the case for months.

Illustration: a contractor on a 2017 Yellow Book project receives a DAAB decision awarding it an extension of time and costs. The employer gives a Notice of Dissatisfaction but does not pay. The contractor refers the failure to comply to ICC arbitration under Sub-Clause 21.7 and asks the tribunal for a partial award on compliance, while the employer's challenge to the merits proceeds in the same arbitration. The example is hypothetical.

How TRW & Co helps with FIDIC construction disputes

We act for employers, contractors and subcontractors in FIDIC construction disputes on energy, transport, water and building projects, working from our offices in Dhaka, London, Dubai, Singapore, New York and Delhi. We advise during the project on notices, claims and Engineer's determinations; prepare and respond to DAAB referrals; enforce or resist DAAB decisions; and conduct ICC arbitrations through to award and enforcement. We work with independent delay, quantum and technical experts and coordinate local counsel where state employers or local courts are involved. Our approach starts with an early assessment of entitlement, records and likely cost. To discuss a project or dispute, please contact us.

Frequently asked questions

Do FIDIC contracts provide for ICC arbitration?

Yes. The general conditions of the 1999 and 2017 Red, Yellow and Silver Books provide that disputes not settled amicably, and in respect of which a DAB or DAAB decision has not become final and binding, are finally settled by international arbitration under the ICC Rules, by three arbitrators unless otherwise agreed. Particular conditions frequently amend the seat, language or institution, so the project contract must always be checked.

What happens if a party ignores a DAAB decision?

A DAAB decision is binding and must be complied with promptly even if a Notice of Dissatisfaction is given. Under Sub-Clause 21.7 of the 2017 forms, the failure to comply can be referred directly to arbitration, and the tribunal may use summary or expedited procedures, interim measures or an award to enforce the decision, as the Singapore Court of Appeal recognised for the 1999 forms in Persero (2015).

Is the FIDIC 28-day notice of claim really a time bar?

The 2017 forms state that a party which fails to give a Notice of Claim within 28 days of awareness is not entitled to additional time or payment, subject to procedures under which late notice can be challenged and in some circumstances reviewed. Whether a tribunal enforces the bar strictly also depends on the governing law, including doctrines such as good faith, waiver and prevention.

Which version of the ICC Rules applies to a FIDIC arbitration started in 2026?

Under Article 1(2) of the 2026 ICC Rules, an arbitration commenced on or after 1 June 2026 is governed by the 2026 Rules unless the parties agreed to submit to Rules in effect on an earlier date. A general reference to the ICC Rules in a FIDIC contract signed earlier will therefore usually lead to the 2026 Rules, though the expedited threshold depends on the agreement date.

Can a FIDIC dispute be decided by a sole arbitrator under the expedited procedure?

Yes, if the expedited procedure applies. Article 2(1) of Appendix V allows the ICC Court to appoint a sole arbitrator notwithstanding any contrary provision of the arbitration agreement, which includes the FIDIC default of three arbitrators. Parties that want three arbitrators for all disputes should opt out of the expedited procedure expressly in the particular conditions.

Sources

  1. FIDIC, Conditions of Contract for Construction (Second Edition 2017): amendments (November 2022)
  2. PT Perusahaan Gas Negara (Persero) TBK v CRW Joint Operation [2015] SGCA 30
  3. ICC Dispute Resolution Statistics (2025)
  4. ICC 2026 Arbitration Rules