Infrastructure and PPP Disputes
Infrastructure PPP disputes decide who pays when a long-term concession fails. This guide explains how termination compensation is calculated and contested, how lender step-in rights and direct agreements work, what changes when the counterparty is a public authority, and how the 2026 ICC Rules help parties manage complex project disputes.

Key takeaways
- Termination compensation usually depends on why the contract ended, so characterisation of default drives quantum.
- Authority default and adverse government action typically attract fuller compensation than private partner default.
- Direct agreements give lenders notice, cure, step-in and substitution rights that limit termination.
- Aligned ICC clauses across the contract chain make joinder and consolidation workable.
- Article 14(4) lets the ICC Court appoint arbitrators directly where a state entity is a party.
Infrastructure PPP Disputes in Short
Infrastructure PPP disputes arise under the long-term contracts through which a public authority engages a private project company to design, build, finance, operate and maintain an asset such as a toll road, port, airport, hospital, water plant or power station. The contract often runs for several decades, the project is financed mostly with limited-recourse debt, and the private partner is paid through user tariffs, availability payments or both.

When a dispute reaches the point of termination, the central questions are almost always the same: who caused the termination, how much compensation is payable, and what the lenders may do to protect their loans. ICC arbitration is often chosen for these questions, and new ICC cases now run under the 2026 ICC Rules of Arbitration unless the parties agree otherwise.
This guide focuses on the two issues that drive most high-value PPP cases: termination compensation and lender step-in. It also covers the earlier disputes that lead to termination, the special features of arbitrating with a public authority, and the tools in the 2026 ICC Rules that suit long-term project contracts.
How PPP Structures Shape Disputes
A PPP is a web of contracts. The project agreement or concession sits at the centre, between the contracting authority and the special purpose project company. Around it are the financing documents, a direct agreement between the authority and the lenders, an EPC contract for construction, an operation and maintenance contract and, often, a shareholders' agreement among the sponsors. Each contract may have its own dispute clause, and risk is passed down the chain so that the project company is left with as little residual exposure as possible.
The World Bank's Guidance on PPP Contractual Provisions (2019 edition) addresses the provisions that cause the most difficulty in practice: force majeure, material adverse government action, change in law, step-in rights for the authority and the lenders, refinancing, termination events, termination payments, handback, confidentiality and dispute resolution. At the legislative level, the UNCITRAL Model Legislative Provisions on Public-Private Partnerships (2019) cover the duration, extension and termination of PPP contracts and the settlement of disputes. Both are useful reference points for tribunals asked what a balanced allocation of risk looks like.
| Stage | Typical infrastructure PPP disputes | Main parties |
|---|---|---|
| Procurement and financial close | Award challenges, conditions precedent, land acquisition delays | Bidders, authority, sponsors |
| Construction | Delay, design changes, ground conditions, relief and compensation events | Project company, EPC contractor, authority |
| Operation | Availability deductions, tariff indexation, traffic or demand risk, change in law | Project company, authority, O&M contractor |
| Distress and termination | Default notices, cure periods, termination compensation, step-in | Authority, project company, lenders |
| Handback | Condition of the asset, retention funds, transfer of staff and data | Authority, project company |
Termination Compensation in Infrastructure PPP Disputes
Termination compensation is the largest single issue in infrastructure PPP disputes. Because the asset usually reverts to the authority on termination, almost every PPP contract contains a formula for what the authority must pay. The formula typically depends on the reason for termination, and the parties' dispute is often less about the arithmetic than about which category applies.
| Termination ground | Typical compensation approach | Common battleground |
|---|---|---|
| Authority default, material adverse government action or voluntary termination | Outstanding senior debt, equity invested and a measure of expected equity return | Whether conduct amounts to authority default; valuing lost equity return |
| Force majeure | Commonly senior debt and equity paid in, often without equity return | Whether the event is force majeure or a political risk the authority bears |
| Private partner default | Often linked to senior debt or to the market value of the remaining contract, less authority costs | Validity of default notices; cure periods; deductions and set-off |
| Change in law or corruption-related termination | Depends heavily on the contract and governing law | Characterisation of the measure; illegality defences |
Three issues recur. First, characterisation: a project company may argue that a government measure is material adverse government action entitling it to full compensation, while the authority says the project company defaulted first. Second, valuation: equity compensation may be fixed by a base-case financial model, by an agreed internal rate of return or by a market valuation, and experts often disagree about the inputs. Third, set-off and timing: authorities sometimes deduct their own claims and the cost of re-procurement, and payment may be due in instalments. Each point can shift the outcome by a large proportion of the project's value.
Illustration: a toll road concession provides for full compensation on authority default and debt-only compensation on concessionaire default. Traffic falls short of forecasts after the state builds a competing free road. The authority terminates for missed debt service; the concessionaire says the competing road breached a non-competition covenant and was material adverse government action. The infrastructure PPP dispute turns on causation and on the order in which the defaults occurred, and quantum follows from that answer.
Lender Step-In and Direct Agreements
Lenders finance most PPP projects on a limited-recourse basis, so their security is the contract itself. To protect it, they usually sign a direct agreement with the authority. That agreement typically requires the authority to notify lenders before terminating, gives the lenders a period to cure the default, allows them to step in through a nominated entity to run the project for a time, and lets them transfer the contract to a suitable substitute. The World Bank guidance treats lenders' step-in rights as a core bankability provision.
Step-in creates its own disputes. Lenders and authorities argue about whether notice was properly given, whether the cure period ran, whether the proposed substitute meets the agreed criteria and what liabilities the step-in entity assumes. A termination made without respecting the direct agreement may be invalid or may expose the authority to damages. For arbitration, the key practical questions are whether the direct agreement contains an arbitration clause compatible with the project agreement and whether lenders can be joined to, or participate in, a dispute between the authority and the project company.
Align the dispute clauses in the project agreement, direct agreement, EPC and O&M contracts. Under Articles 8, 10 and 11 of the 2026 ICC Rules, joinder, multi-contract claims and consolidation work best when the clauses provide for ICC arbitration with the same seat and language and expressly contemplate related claims being heard together. Without that drafting, parallel proceedings and inconsistent findings on the same termination are a real risk.
Disputes Before Termination
Most PPP contracts never reach termination, yet the disputes that arise during construction and operation shape what happens if they do. During construction, the project company and its EPC contractor commonly argue about delay caused by late land handover, permits or design approvals. A well-drafted PPP contract treats such events as relief events, which protect the project company from default, or as compensation events, which also entitle it to money. Classifying an event correctly matters, because a project company that has relief but not compensation may avoid termination yet still run out of cash.
During operation, availability-based contracts generate disputes about performance deductions, the measurement of service standards and whether failures were caused by the authority. Demand-risk concessions generate disputes about tariff increases that the authority refuses to approve and about competing infrastructure. Change in law clauses are also frequently tested: the parties may disagree on whether a new tax, environmental standard or safety requirement is a general change in law that the project company bears, or a discriminatory or specific change for which the authority must compensate. These earlier disputes often provide the factual record on which a later termination claim is built, so how they are handled matters.
Arbitrating with Public Authorities
Infrastructure PPP disputes almost always involve a public body, which brings additional questions. Did the authority have capacity and the necessary approvals to agree to arbitration? Is the subject matter arbitrable under the law of the host state, or are some disputes reserved to administrative courts? Has the state waived immunity from execution, and are there assets that can be reached? Our guide to contracting with state entities covers these points in detail.
The 2026 ICC Rules contain specific provisions for these cases. Article 14(4) allows the ICC Court to appoint an arbitrator directly where a party is a state or may be considered a state entity. Where the arbitration agreement arises from a treaty or an investment protection law, the emergency arbitrator provisions do not apply (Appendix IV, Article 1(3)(c)) and Article 14(6) bars arbitrators sharing a party's nationality unless the parties agree otherwise. Foreign sponsors may also have treaty protection alongside the contract; the interaction between contract and treaty claims is discussed in our page on state contracts and our insight on stabilisation clauses.
Procedure for Infrastructure PPP Disputes
Long-term contracts call for a dispute process that resolves smaller disagreements quickly while the project continues. Many PPP contracts use a tiered approach: negotiation between senior representatives, then expert determination for technical or financial issues such as indexation or availability deductions, or a standing dispute board during construction, and finally arbitration. Our guidance on multi-tier clauses explains how to make each step enforceable and how to avoid preconditions that become a jurisdictional trap.
Once in ICC arbitration, several tools are relevant. Article 29 allows the tribunal to order interim measures, for example to restrain termination or the drawing of a bond while the dispute is decided, and Article 29(2) preserves recourse to the courts.
Article 30 permits early determination of claims or defences that are manifestly without merit or manifestly outside jurisdiction. Under the revised rules, the first case management conference remains mandatory within 30 days, while Terms of Reference are optional. For the large, document-heavy cases typical of infrastructure PPP disputes, an early procedural plan covering the financial model, expert issues and bifurcation of liability and quantum is usually worth the time.
- Preserve the financial model. The base-case model is often the starting point for compensation; secure the native files and audit history early.
- Record government conduct. Keep a contemporaneous log of decisions, permits and policy changes that may amount to material adverse government action.
- Involve lenders early. Their consent or participation may be required for settlement, and their rights under the direct agreement can affect remedies.
- Plan enforcement from the outset. Identify commercial assets of the authority and any payment mechanisms or guarantees supporting termination payments.
How TRW & Co Helps
TRW & Co advises project companies, sponsors, lenders, contractors and public authorities on infrastructure PPP disputes under the ICC Rules and other arbitration rules. Our teams in Dhaka, London, Dubai, New York, Singapore and Delhi work on termination and compensation claims, material adverse government action and change in law disputes, step-in and substitution issues, and the construction and operating disputes that precede them. We help clients assess the contract chain, preserve financial and technical evidence, work with independent valuation and delay experts, seek interim protection and plan enforcement against public bodies. We also review PPP dispute clauses and direct agreements before signing. To discuss a matter, please contact us.
Frequently asked questions
How is termination compensation calculated in a PPP contract?
It depends on the contract. Most PPP contracts set different formulas for authority default, force majeure and private partner default. Authority default usually attracts the most generous formula, often covering senior debt, equity and some expected return, while private partner default often yields less. Disputes typically concern which ground applies, the valuation inputs and the deductions the authority may make.
What are lender step-in rights?
They are rights, usually set out in a direct agreement between the authority and the lenders, allowing lenders to be notified of a threatened termination, cure the default, temporarily take over the project through a nominee and transfer the contract to an approved substitute. They protect the lenders' security and make the project bankable. Disputes arise over notice, cure periods and the acceptability of a substitute.
Can lenders take part in an ICC arbitration between the authority and the project company?
Only if there is a basis in the arbitration agreements. Under the 2026 ICC Rules, joinder under Article 8 and claims under several contracts under Article 10 depend on the parties being bound by compatible arbitration agreements. Drafting the direct agreement and project agreement with aligned ICC clauses, the same seat and express consent to related claims makes participation far more straightforward.
Is the ICC emergency arbitrator available in PPP disputes?
It is available where the arbitration agreement is in the PPP contract and the parties have not opted out. It is not available where the arbitration agreement arises from a treaty or an investment protection law. In treaty-based cases, urgent relief must come from courts or from the tribunal once constituted under Article 29.
Are PPP disputes always arbitrable?
Not always. Some legal systems reserve certain disputes involving public contracts or regulatory powers to administrative courts, or require specific approval before a public body agrees to arbitration. The position depends on the law of the host state, the law of the seat and the law where enforcement is sought, so it should be checked before the contract is signed.
Sources
General information only, not legal advice. References to the ICC, the ICC Court and the ICC Rules describe their published rules and practice; TRW & Co is independent of the ICC.