Construction Disputes in Bangladesh Under FIDIC

Bangladesh construction disputes FIDIC contracts govern turn on notices, dispute boards and the seat of arbitration. This insight compares the FIDIC 2017 DAAB route with the national e-PW3 public works conditions and explains how Bangladeshi courts and the 2026 ICC Rules affect performance security calls and claims.

Bridge construction site illustrating Bangladesh construction disputes FIDIC contracts and dispute boards

Key takeaways

  • Claims under both FIDIC 2017 and e-PW3 require notice within 28 days of awareness, or the claim can be lost.
  • e-PW3 public works disputes go to an Adjudicator within 14 days, then arbitration under the Arbitration Act 2001.
  • A DAAB decision binds immediately; without a notice of dissatisfaction within 28 days it becomes final.
  • The High Court Division restrained a performance guarantee call under section 7A in a December 2025 judgment.
  • With a foreign seat, section 7A relief is largely unavailable before enforcement, so plan for emergency arbitrator relief.

Bangladesh construction disputes FIDIC: the short answer

Most Bangladesh construction disputes FIDIC-based contracts govern are won or lost on procedure rather than merit. Projects financed by development partners usually run on FIDIC conditions with a Dispute Avoidance/Adjudication Board (DAAB) and international arbitration, often under the ICC Rules. Domestically funded public works use the national standard tender documents, an Adjudicator and arbitration under the Arbitration Act 2001. In both systems a missed 28-day notice can extinguish an otherwise sound claim.

Bridge construction site illustrating Bangladesh construction disputes FIDIC contracts and dispute boards
Bangladesh construction disputes FIDIC contracts govern usually pass through notices, a DAAB and then arbitration.

The practical questions therefore come in sequence. Which form governs the works? Has the DAAB actually been appointed, and is it still functioning? Has a notice of dissatisfaction been served in time? Where is the seat of arbitration, and which court can grant interim relief while the dispute runs? This insight works through those questions for contractors, employers, engineers and lenders on Bangladeshi transport, energy, port and industrial projects.

It is general information, not legal advice. Particular Conditions frequently change the default position, so every answer below must be checked against the contract actually signed.

Which contract forms govern Bangladeshi projects

Public works procured by government agencies fall under the Public Procurement Act 2006 and its rules. According to the Bangladesh Public Procurement Authority (BPPA), the Public Procurement Rules 2025 took effect on 28 September 2025, and Parliament passed the Public Procurement (Amendment) Bill 2026 in April 2026. For open-tender works above BDT 5 crore, procuring entities use the BPPA's e-PW3 standard tender document (October 2025). Its General Conditions deal with claims in clause 94 and disputes in clause 95.

Development-partner projects are different. Training material published through the Asian Development Bank records that the World Bank adopted the FIDIC 2017 suite in its Standard Procurement Documents in July 2019, making constitution of the DAAB a condition precedent to the Commencement Date, and that JICA promotes dispute boards and finances the employer's share of their cost (ADB-hosted FIDIC 2017 DAAB presentation, July 2025). Bangladesh's large externally financed projects therefore tend to generate FIDIC-style disputes, while ministries and local authorities generate e-PW3 disputes. Our insight on JICA-funded projects in Bangladesh covers the lender overlay.

Private developers, power producers and industrial investors usually start from FIDIC Yellow or Silver Book terms and amend them heavily. The dispute clause in those contracts is negotiated, so the seat, the rules and any dispute board must be read from the contract rather than assumed.

Stagee-PW3 public works (BPPA, October 2025)FIDIC 2017 Red Book (default terms)
Notice of claimWithin 28 days of awareness (GCC 94.1); late notice discharges the employer (GCC 94.2)Within 28 days of awareness (Sub-Clause 20.2)
Fully detailed claimWithin 42 days of awareness (GCC 94.3)Within 84 days of awareness (Sub-Clause 20.2)
First-tier decisionProject ManagerEngineer's agreement or determination
Referral to dispute bodyTo the Adjudicator within 14 days of the Project Manager's decision (GCC 95.2(a))To the DAAB within 42 days of a notice of dissatisfaction with the Engineer's determination (Sub-Clause 21.4)
Decision period28 days (GCC 95.2(c))84 days unless otherwise agreed (Sub-Clause 21.4)
Route to arbitrationNotice if no settlement within 28 days of the Adjudicator's decision (GCC 95.3(a))Notice of dissatisfaction within 28 days of the DAAB decision, then amicable settlement (Sub-Clauses 21.4 and 21.5)
ArbitrationArbitration Act 2001, at the place stated in the Particular Conditions (GCC 95.3(b))ICC Rules by default (Sub-Clause 21.6)

Two points follow from the table. First, the e-PW3 timetable is tighter: a contractor has 14 days, not 42, to escalate. Second, under e-PW3 the default appointing authority for the Adjudicator, where the parties disagree, is the President of the Institution of Engineers, Bangladesh. FIDIC instead relies on the appointing entity named in the Contract Data.

Extensions of time on public works

Extensions of time under e-PW3 follow an approval ladder that has no FIDIC equivalent. The Project Manager may recommend, and the procuring entity grant, an extension of up to thirty per cent of the original contract time (GCC 44.4). Between thirty and one hundred per cent, the Head of the Procuring Entity or an authorised officer must approve (GCC 44.5); beyond one hundred per cent, the Secretary of the ministry or division must approve (GCC 44.6). A failure to give early warning of a delay is excluded when the extension is assessed (GCC 44.3).

This ladder explains many long-running disputes on public works. Contractors keep working while a large extension sits awaiting approval, liquidated damages accrue under GCC 71, and the employer later relies on the absence of approval. Starting the approval chain early, and recording each step, is cheaper than arguing about it in arbitration years later.

How the DAAB works in Bangladesh construction disputes FIDIC projects

The 2017 FIDIC forms favour a standing DAAB, appointed by default within 28 days of the Letter of Acceptance and kept informed through site visits. Its first job is avoidance: the parties can jointly ask it for informal assistance before a disagreement hardens. When a dispute is referred, the DAAB decision binds the parties immediately and must be complied with, even if one of them later challenges it in arbitration.

In practice, Bangladesh construction disputes FIDIC drafters expected to go to a standing board often reach an empty room. Boards are not appointed on time, members resign and are not replaced, or the employer's share of fees is not budgeted. A contractor facing that situation should press for appointment in writing and use the appointing-entity mechanism in the Contract Data rather than wait. The 2017 forms also let a party go to arbitration where no DAAB is in place, so delay in appointment should not freeze a claim indefinitely.

Timing remains critical. If no notice of dissatisfaction is given within 28 days of a DAAB decision, the decision becomes final and binding. If a party fails to comply with a binding decision, the other party may refer that failure directly to arbitration. Calendar control is therefore part of the merits.

Practical point

Diarise every contractual period from the day of the event, not the day the claims team hears about it. On Bangladesh construction disputes FIDIC tribunals regularly test whether notices were given within 28 days of when the contractor "became aware or should have become aware". Contemporaneous site diaries, e-GP correspondence and programme updates are the evidence that wins that argument.

ICC arbitration of Bangladesh construction disputes FIDIC-style

FIDIC's default arbitration clause refers to the ICC Rules. The 2026 ICC Rules of Arbitration came into force on 1 June 2026 and apply to arbitrations commenced on or after that date unless the parties agreed otherwise. Several features matter for construction claims.

Early determination under Article 30 allows a party to ask the tribunal to dispose of claims or defences that are manifestly without merit or manifestly outside its jurisdiction. That can shorten disputes about plainly time-barred heads of claim. The Expedited Procedure under Article 32 and Appendix V applies automatically up to US$4 million for arbitration agreements concluded on or after 1 June 2026, and up to US$3 million for agreements concluded between 1 January 2021 and 1 June 2026, which suits smaller variation and payment disputes.

Emergency relief is available under Article 31 and Appendix IV where measures cannot await the constitution of the tribunal, for example to restrain an abusive call on a performance security. Multi-party projects can use joinder and claims under multiple contracts (Articles 8 to 10) to bring subcontractors or guarantors into one proceeding, provided the arbitration agreements are compatible. For the wider sector picture see our page on construction and FIDIC disputes, and for standing boards administered by ICC see ICC Dispute Boards.

A binding but non-final DAAB decision can itself be the subject of an ICC arbitration. A party seeking prompt payment may ask the tribunal to order compliance by interim or partial award while the underlying merits continue. Tribunals approach such requests with care, and the seat's law on partial awards should be checked before relying on that route.

Bangladeshi courts, performance securities and interim relief

Section 7A of the Arbitration Act 2001, inserted in 2004, lets a party seek interim measures before or during an arbitration, or until the award is enforced. In an international commercial arbitration the application goes to the High Court Division; in other cases it goes to the District Judge. Available measures include injunctions against transferring property, interim injunctions and the appointment of a receiver.

Calls on performance guarantees are the most common flashpoint. In Civil Revision No. 1042 of 2025 (High Court Division, judgment of 9 December 2025) the District Judge in Dhaka had summarily rejected a section 7A application to restrain encashment of a performance guarantee, treating the guarantee as autonomous. The Division Bench held that the Act is a special law prevailing over the Code of Civil Procedure, preferred an earlier Division Bench view over contrary single-bench decisions, and restrained encashment until the pending application to set aside the award was decided. The law is not uniform, so outcomes on guarantee calls remain uncertain.

A foreign seat changes the analysis. In First Appeal No. 209 of 2016 (judgment of 12 December 2021) a larger bench of the High Court Division held that, apart from sections 45 to 47, the Act does not apply where the seat is abroad, and that section 7A relief becomes available only once an application to enforce the foreign award is filed. A contractor with a Singapore or London seat should plan for emergency arbitrator or seat-court relief instead; our insight on interim relief for foreign-seated arbitrations explains the options.

Practical checklist for contractors and employers

The following steps reduce the risk that Bangladesh construction disputes FIDIC procedures turn against the party with the better case on the merits:

  • Identify the governing form on day one: e-PW3, FIDIC 1999, FIDIC 2017 or a bespoke EPC, and map every notice period into the project calendar.
  • Confirm that the DAAB or Adjudicator has been appointed, that fees are budgeted, and that replacement mechanisms work if a member resigns.
  • Serve notices of dissatisfaction on time and in the form the contract requires, even while settlement talks continue.
  • Check whether the seat is Dhaka or abroad, because that decides whether Bangladeshi courts can grant section 7A relief during the arbitration.
  • Review performance security wording and prepare evidence early if an abusive call is likely.
  • Consider the 2026 ICC tools: early determination for weak heads of claim, the Expedited Procedure for smaller disputes and the emergency arbitrator for urgent protection.
  • Where the seat is Dhaka, read our guide to Dhaka as an ICC seat on court supervision and set-aside risk.

Employers should apply the same discipline. A determination that ignores the contract procedure, or a security call made without contractual basis, invites an injunction and weakens the employer's position in any later arbitration.

How TRW & Co helps

We advise contractors, employers, lenders and engineers on Bangladesh construction disputes FIDIC and e-PW3 contracts create, from the first notice through DAAB referral and ICC or Bangladesh-seated arbitration. Our teams in Dhaka, London, Dubai and Singapore work together on claim strategy, notice reviews, delay and quantum evidence, performance security disputes and section 7A applications, and we coordinate with technical experts where programme or valuation analysis is needed. We act for claimants and respondents and focus on preserving rights early, because most construction claims are decided by what happens in the first weeks. To discuss a live project, contact our team.

Frequently asked questions

Do Bangladeshi public works contracts use FIDIC?

Domestically funded public works normally use the Bangladesh Public Procurement Authority's standard tender documents, such as e-PW3 for open-tender works above BDT 5 crore. Those conditions borrow from international models but have their own claims clause, an Adjudicator and arbitration under the Arbitration Act 2001. Projects financed by the World Bank, ADB or JICA more often use FIDIC-based conditions with a dispute board.

What happens if a DAAB was never appointed?

The FIDIC 2017 forms provide an appointing mechanism where the parties fail to agree on members, and they allow a party to refer a dispute to arbitration where no DAAB is in place. A contractor should still request appointment in writing and keep a record of the employer's response, because tribunals will look at whether each party tried to operate the agreed procedure.

Can a Bangladeshi court stop a call on a performance guarantee?

Possibly. In Civil Revision No. 1042 of 2025 the High Court Division restrained encashment under section 7A of the Arbitration Act 2001 pending a challenge to the award, while noting contrary single-bench decisions. Relief depends on the facts, the guarantee wording and whether the seat is in Bangladesh, so applicants should move quickly and prepare full evidence.

Which ICC Rules apply to a FIDIC arbitration started in 2026?

The 2026 ICC Rules apply to arbitrations commenced on or after 1 June 2026 unless the parties agreed otherwise. They add early determination, a Highly Expedited option and a higher automatic Expedited Procedure threshold of US$4 million for arbitration agreements concluded on or after 1 June 2026. Older agreements keep lower thresholds.

Is Dhaka a sensible seat for a FIDIC dispute?

It can be where the employer, assets and works are in Bangladesh and both sides accept local court supervision. The trade-offs are wider set-aside grounds under section 43 of the Arbitration Act 2001 and court timetables. A neutral seat abroad limits Bangladeshi court support before an award, so the choice should reflect where interim relief and enforcement will be needed.

Sources

  1. Arbitration Act 2001 (Act No. 1 of 2001), Laws of Bangladesh
  2. BPPA Standard Tender Document e-PW3 (October 2025)
  3. ICC 2026 Arbitration Rules
  4. Supreme Court of Bangladesh, HCD: Civil Revision No. 1042 of 2025
  5. Supreme Court of Bangladesh, HCD: First Appeal No. 209 of 2016
  6. ADB-hosted presentation: FIDIC 2017 Red Book and the DAAB (July 2025)

General information only, not legal advice. References to the ICC, the ICC Court and the ICC Rules describe their published rules and practice; TRW & Co is independent of the ICC.