Dispute Resolution in Bangladesh Economic Zones
Bangladesh economic zones dispute resolution is layered: zone authority decisions, developer leases, commercial contracts, labour issues and treaty claims each follow a different route. We explain what the BEZA and BEPZA statutes provide, where ICC arbitration fits, and how foreign investors can align dispute clauses across a zone project.

Key takeaways
- The Economic Zones Act 2010 overrides other laws and allows the Government to specify courts for zone civil cases.
- Appeals from the specified courts go to the High Court Division within 60 days.
- ICC arbitration suits developer, lease, supply and construction contracts in zone projects.
- The FPI Act 1980 promises fair treatment, compensation for expropriation and free transfer of returns.
- Treaty protection may sit behind commercial clauses where the investor's home state has a treaty.
Bangladesh economic zones dispute resolution: the overview
Bangladesh economic zones dispute resolution depends on who is in dispute with whom. A foreign manufacturer in an economic zone or export processing zone may face disputes with the zone authority over land and permits, with a private zone developer over leases and utilities, with suppliers and buyers over commercial contracts, and, in rare cases, with the State over measures affecting its investment. Each layer has a different legal basis and a different natural forum. ICC arbitration fits some layers well; others are channelled to specified courts, labour bodies or treaty mechanisms.

Two statutory regimes matter. The Bangladesh Economic Zones Authority (BEZA) operates under the Bangladesh Economic Zones Act 2010 (Act No. 42 of 2010), amended in 2015 and 2023. The Bangladesh Export Processing Zones Authority (BEPZA) operates under the Bangladesh Export Processing Zones Authority Act 1980. Both sit on top of the general investor protections in the Foreign Private Investment (Promotion and Protection) Act 1980 and Bangladesh's bilateral investment treaties.
This insight maps those layers, explains what the statutes say about courts and investor protection, and sets out how to draft dispute clauses for zone projects. It reflects the published English and Bengali texts and should be checked against current notifications before any decision is taken.
What the zone statutes provide
The 2010 Act gives BEZA a wide remit. Section 3 provides that the Act prevails notwithstanding anything in any other law. Section 4 recognises several types of zone: zones developed through public-private partnership, private economic zones established by local, non-resident Bangladeshi or foreign investors, government economic zones, and special economic zones for particular industries. Section 8 allows the Authority to appoint zone developers, and section 28 allows it to suspend or cancel a developer's permit for specified failures.
Investor-facing functions are concentrated in section 12, which requires the Authority to provide a one-stop service for permits, including permissions for the repatriation of capital and dividends. Sections 10 and 11 provide for customs arrangements and financial incentives broadly matching those available under the export processing zone legislation. Section 13 allows the Government to exempt a zone, or an organisation in it, from listed laws, including the Foreign Exchange Regulation Act 1947, or to modify their application. The authoritative Bengali text is on the Laws of Bangladesh portal.
The export processing zones follow an older model. BEPZA's information for investors describes three categories of enterprise: Type A (wholly foreign-owned, including investment by Bangladeshis ordinarily resident abroad), Type B (joint ventures between foreign and resident Bangladeshi investors) and Type C (wholly owned by resident Bangladeshis). Employment in export processing zones is governed by a dedicated labour statute, the EPZ Labour Act 2019, rather than the general labour code.
Specified courts under section 36 of the 2010 Act
Section 36 of the 2010 Act allows the Government to specify one or more courts for the trial of civil cases arising from economic zones. Cases under the Act are tried only in those courts, and an aggrieved party may appeal to the High Court Division within 60 days. Section 37 gives the Authority strong recovery powers, including pursuing unpaid dues against owners or directors and, in defined circumstances, seizing assets of an enterprise that fails to pay.
How section 36 interacts with an arbitration agreement is not spelled out in the Act. Section 7 of the Arbitration Act 2001 bars courts from hearing matters the parties have agreed to arbitrate, except as that Act provides. Our view is that a clear arbitration agreement between a zone enterprise and a private counterparty should still be given effect, with section 36 directing civil cases that are not arbitrated to the specified courts.
Claims under the 2010 Act itself, such as challenges to the Authority's statutory decisions, are a different matter and may well belong in court. Where the point is material, it should be addressed expressly in the contract, because uncertainty about the forum is one of the main sources of delay in Bangladesh economic zones dispute resolution. A clause that states which matters are arbitrable and which are reserved to the specified courts reduces the scope for parallel proceedings and jurisdictional objections.
Bangladesh economic zones dispute resolution by type of dispute
The table below summarises the natural forum for the main categories of dispute that arise in zone projects. It is a starting point for planning, not a substitute for reading the specific contract, licence or allotment document.
| Dispute | Typical legal basis | Likely forum |
|---|---|---|
| Investor v zone authority (allotment, lease, permits) | Allotment or lease terms; 2010 Act or 1980 BEPZA Act | Contractual dispute clause if any; otherwise specified or ordinary courts and judicial review |
| Zone developer v BEZA | Developer appointment, development or PPP agreement | Negotiated clause; international arbitration is often sought by foreign developers |
| Unit investor v private zone developer | Lease and service agreements | Freely negotiated; ICC arbitration is well suited |
| Enterprise v suppliers, buyers, contractors | Commercial contracts | ICC or other institutional arbitration with a neutral seat |
| Employer v workers in export processing zones | EPZ Labour Act 2019 | Statutory labour bodies, not commercial arbitration |
| Foreign investor v State (expropriation, unfair treatment) | Bilateral investment treaty; FPI Act 1980 | Treaty arbitration where a treaty applies; domestic courts otherwise |
For commercial and developer contracts, ICC arbitration offers neutrality, enforceability in New York Convention states and an institution with experience of South Asian disputes. Bangladesh economic zones dispute resolution clauses with state bodies require more negotiation, because public authorities often prefer domestic arbitration or courts. Our page on sovereigns and state-owned entities covers the approval and immunity points that arise.
Investor protections behind Bangladesh economic zones dispute resolution
The Foreign Private Investment (Promotion and Protection) Act 1980 applies inside and outside the zones. Section 4 promises fair and equitable treatment and full protection and security. Section 5 provides that the terms of a sanction for foreign investment shall not be unilaterally changed so as to adversely alter its conditions, and guarantees treatment no less favourable than similar investment by Bangladeshi citizens.
Section 7 permits expropriation only for a public purpose against adequate compensation, defined as market value immediately before the measure, paid expeditiously and freely transferable. Section 8 guarantees transfer of capital and returns, subject to limits in exceptional financial and economic difficulty.
The 1980 Act contains no dispute resolution clause of its own. Its protections are enforced through domestic courts, unless a bilateral investment treaty gives the investor access to international arbitration. Bangladesh has concluded a series of investment treaties, and our insights on Bangladesh's bilateral investment treaties and on treaty protection explain how to check whether an investor's home state is covered and how to structure investment to obtain coverage.
History shows why this layer matters. In the ICSID case brought by Saipem against Bangladesh, the investor relied on a treaty after domestic court intervention in an ICC arbitration concerning a gas pipeline project. The case is a reminder that treaty protection can sit behind a commercial ICC clause, and that court conduct can itself become the subject of a claim.
Interim relief and enforcement for zone enterprises
Urgent relief is often the first practical question in a zone dispute. Where the arbitration is seated in Bangladesh, section 7A of the Arbitration Act 2001 allows a party to seek interim measures from the court, and in an international commercial arbitration the application goes to the High Court Division. Where the seat is abroad, section 3(2) of the 2001 Act applies only the provisions on foreign award enforcement, so the availability of Bangladeshi court support for a foreign-seated case is less certain. Our insight on interim relief for foreign-seated arbitrations discusses that gap.
Within the ICC framework, a party may apply to an emergency arbitrator under Article 31 and Appendix IV of the 2026 Rules before the tribunal is constituted, and the tribunal may order interim or conservatory measures under Article 29(1) once it has the file. Those orders bind the parties contractually. Whether a Bangladeshi court will give them direct effect is a separate question, and zone enterprises should plan accordingly, for example by securing bank guarantees that can be called outside Bangladesh.
Enforcement against a zone counterparty follows the general rules. A foreign award is enforced through the District Judge's court in Dhaka under section 45 of the 2001 Act, and payment abroad then requires foreign exchange clearance. Effective Bangladesh economic zones dispute resolution therefore needs to look beyond the award to the assets of the counterparty and the route by which money can leave the country. The authority's own recovery powers under section 37 of the 2010 Act also mean that an enterprise in a payment dispute with BEZA should keep paying undisputed dues while the dispute proceeds.
Illustration: a foreign-owned garment accessories maker leases a factory from a private zone developer. A dispute arises over unreliable power supply and service charges. The lease contains an ICC clause with a Singapore seat, while the utility agreement refers disputes to the courts in Bangladesh. The investor faces two forums for one factual dispute. Had the documents used compatible clauses with consent to consolidation, a single ICC tribunal could have decided both claims.
Drafting dispute clauses for zone projects
Good Bangladesh economic zones dispute resolution begins with the documents signed at the outset. Zone investors usually sign several instruments at once: an allotment or lease with the authority or developer, utility and service agreements, construction contracts and supply contracts. Clauses drafted separately by different teams often conflict. A coordinated approach avoids parallel proceedings in different forums over one project.
- Use compatible clauses. Where the commercial contracts provide for ICC arbitration, use the same rules and seat across the project and include consent to consolidation and joinder.
- Choose the seat deliberately. A neutral seat such as Singapore or London keeps set-aside proceedings outside Bangladesh; a Dhaka seat may be acceptable for purely domestic counterparties.
- Address statutory decisions. Distinguish contractual disputes, which can be arbitrated, from challenges to statutory decisions of the authority, which may have to be brought in court.
- Escalation. A short negotiation or mediation step before arbitration suits long-term relationships with zone authorities and developers; see our page on multi-tier clauses.
- Payment. Link the clause to foreign exchange arrangements, as explained in our insight on foreign exchange rules for award payment.
Before signing an allotment or lease in a zone, ask the authority or developer for its standard dispute resolution clause and any amendments it has accepted in the past. State bodies sometimes agree to institutional arbitration for foreign investors if the request is made at the negotiation stage, but rarely after a dispute has arisen.
How TRW & Co helps
We advise foreign investors, zone developers and Bangladeshi enterprises on Bangladesh economic zones dispute resolution, from project structuring through to proceedings and payment. Our Dhaka team works with colleagues in London, Singapore and Dubai to review allotment, lease, development and supply documents, align dispute clauses across a project, and assess treaty coverage for the investor's structure. When disputes arise, we act in ICC and other institutional arbitrations, advise on interim relief and court applications in Bangladesh, and coordinate enforcement and payment planning. To discuss a zone project or dispute, please contact us.
Frequently asked questions
Can a foreign investor in a Bangladeshi economic zone agree to ICC arbitration?
Yes, for contractual disputes with private counterparties, such as developers, suppliers, buyers and contractors, ICC arbitration with a neutral seat is commonly used. Disputes with the zone authority depend on the authority's documents and willingness to agree. Challenges to statutory decisions taken under the 2010 Act may still need to be brought in court even where a contract contains an arbitration clause.
What does section 36 of the Economic Zones Act 2010 do?
It allows the Government to specify one or more courts to try civil cases arising from the economic zones, provides that cases under the Act are tried only in those courts, and gives a right of appeal to the High Court Division within 60 days. The Act does not expressly address arbitration, so the relationship with arbitration agreements should be dealt with in the contract.
Are export processing zones governed by the same law as economic zones?
No. Export processing zones are administered by BEPZA under the Bangladesh Export Processing Zones Authority Act 1980, while economic zones are administered by BEZA under the 2010 Act. Incentives are broadly aligned, but the statutes, authorities and some procedures differ, and export processing zone employment is governed by the EPZ Labour Act 2019.
What protections do foreign investors have if the State changes the rules?
The Foreign Private Investment (Promotion and Protection) Act 1980 promises fair and equitable treatment, protection against unilateral adverse changes to sanction terms, compensation at market value for expropriation and free transfer of returns. It has no arbitration clause of its own, so international arbitration against the State usually depends on an applicable bilateral investment treaty.
Should a zone project use a Dhaka seat or a foreign seat?
Both can work. A foreign seat such as Singapore or London keeps set-aside proceedings outside Bangladesh and is often preferred by foreign investors and lenders. A Dhaka seat may suit disputes between Bangladeshi parties or where the State counterparty insists. The decision should consider where assets are, enforcement routes and the identity of the counterparty.
Sources
General information only, not legal advice. References to the ICC, the ICC Court and the ICC Rules describe their published rules and practice; TRW & Co is independent of the ICC.