A FIDIC DAAB decision binds the parties at once, but it is not an award and cannot be taken straight to court. This guide to enforcing DAAB decisions arbitration explains Sub-Clause 21.7, the Persero cases in Singapore, the tools available under the 2026 ICC Rules and the defences paying parties can realistically raise.

Key takeaways
- DAAB decisions bind both parties immediately, even if a Notice of Dissatisfaction is given.
- Sub-Clause 21.7 of FIDIC 2017 lets non-compliance go straight to arbitration, bypassing the DAAB and settlement steps.
- Persero II confirms a tribunal may enforce a non-final decision by an interim or partial award.
- A reasoned partial award is usually safer than a procedural order for cross-border enforcement.
- Merits arguments are deferred; credible defences focus on the validity of the DAAB decision.
Enforcing DAAB Decisions Arbitration: The Short Answer
A decision of a FIDIC Dispute Avoidance/Adjudication Board (DAAB) is binding as soon as it is given, and both parties must promptly comply with it even if one of them gives a Notice of Dissatisfaction. But a DAAB decision is not an arbitral award. It cannot be registered in court under the New York Convention, and a losing party that simply refuses to pay forces the winner to start proceedings. In practice, enforcing DAAB decisions arbitration means asking an ICC tribunal to turn the board's decision into an order or award that the courts will recognise, quickly and without reopening the merits.

The 2017 FIDIC suite deals with the problem expressly in Sub-Clause 21.7, and the Singapore Court of Appeal has confirmed that a tribunal may enforce a binding but non-final decision by an interim or partial award. This insight explains the legal basis, the procedural options under the 2026 ICC Rules, the defences a paying party may raise, and the steps that make an enforcement application succeed.
Binding but not final: why enforcement is needed
Under Sub-Clause 21.4.3 of the 2017 Red Book, a DAAB decision is binding on both parties, who must promptly comply with it whether or not a Notice of Dissatisfaction (NOD) is given. Where the decision requires one party to pay money, the DAAB may require the payee to provide appropriate security. The decision stays binding unless and until it is revised by amicable settlement or an arbitral award. If no NOD is given within 28 days, it also becomes final and binding.
The policy is "pay now, argue later": cash keeps flowing during the project, and the merits are decided in arbitration afterwards. The weakness is that the contractual obligation to comply is only as good as the means of enforcing it. A paying party in financial difficulty, or a state employer facing budget constraints, may prefer to wait for the final award. That is why enforcing DAAB decisions arbitration has become a recognised category of ICC case, often run in parallel with, or ahead of, the arbitration on the underlying dispute.
Board decisions are also not judgments. National courts may treat an unpaid DAAB decision as a contractual debt, but an arbitration clause will usually require that debt to be pursued in arbitration rather than litigation. Our overview of ICC dispute boards explains how the standing-board model is meant to work in practice.
The 1999 Gap and the Sub-Clause 21.7 Solution
Under the 1999 FIDIC books, Sub-Clause 20.7 allowed a party to refer a failure to comply with a DAB decision directly to arbitration, but its wording referred only to decisions that had become final and binding. That left a so-called gap for decisions that were binding but subject to an NOD. Tribunals and commentators disagreed over whether the winning party had to go back through the DAB and amicable settlement steps simply to enforce a decision it had already won, and FIDIC issued a Guidance Memorandum in 2013 suggesting amended wording for users of the 1999 books.
The 2017 books close the gap. Sub-Clause 21.7 provides, in substance, that if a party fails to comply with any DAAB decision, whether binding or final and binding, the other party may refer the failure itself directly to arbitration under Sub-Clause 21.6, and Sub-Clauses 21.4 and 21.5 do not apply to that referral.
The arbitral tribunal has power, by summary or other expedited procedure, to order the enforcement of the decision, whether by an interim or provisional measure or an award, as may be appropriate. FIDIC's 2022 amendments did not change this mechanism, so it applies to both the original 2017 text and the reprinted version.
For users of the 1999 books who did not adopt the 2013 wording, the gap still matters. The safest course is to bring the compliance claim together with the merits, as the claimant eventually did in Singapore, so that the tribunal has jurisdiction over both and can make a partial award on the first. Tribunals in an enforcing DAAB decisions arbitration under the 1999 forms have increasingly been asked to follow that approach.
Two points follow. First, the referral concerns the failure to comply, not the merits of the underlying dispute. Second, any order or award enforcing the decision is subject to the parties' rights to have the merits decided later; it gives effect to the binding decision, without finally determining whether the DAAB was right.
The Persero Cases in Singapore
The leading authority on enforcing DAAB decisions arbitration comes from a pipeline project in Indonesia under a contract based on the 1999 Red Book.
A DAB had ordered the employer, PT Perusahaan Gas Negara (Persero), to pay its contractor US$17,298,834.57. The employer gave an NOD and did not pay, and the contractor commenced ICC arbitration seated in Singapore.
In the first round, the tribunal's majority issued a final award ordering payment without examining the merits. The Singapore High Court set that award aside, and the Court of Appeal dismissed the contractor's appeal in CRW Joint Operation v PT Perusahaan Gas Negara (Persero) TBK [2011] SGCA 33, holding that a tribunal could not make a final award giving effect to a non-final decision without also hearing the dispute on the merits.
The contractor tried again. A new tribunal, seized of both the obligation to comply and the merits, issued an interim award ordering prompt payment.
In PT Perusahaan Gas Negara (Persero) TBK v CRW Joint Operation [2015] SGCA 30, the Court of Appeal upheld it by majority (Sundaresh Menon CJ and Quentin Loh J; Chan Sek Keong SJ dissenting). The majority held that the obligation to promptly comply is a distinct obligation, that its breach can be referred to arbitration on its own, and that where the tribunal has both issues before it, it may make an interim or partial award that finally disposes of the compliance issue while the merits continue.
Procedural Options Under the 2026 ICC Rules
The 2026 ICC Rules offer several routes. Which one fits depends on the seat, the place where enforcement will be sought, and whether the merits are already in the arbitration.
| Tool | Basis | Form | Main advantage | Main risk |
|---|---|---|---|---|
| Partial or interim award on the duty to comply | Sub-Clause 21.7; Article 2 definition of "award" | Award scrutinised by the ICC Court under Article 37 | Enforceable under the New York Convention in most jurisdictions | Must be framed as final on the compliance issue to resist set-aside |
| Interim measure | Article 29(1) | Order or award, as the tribunal decides | Speed and flexibility, including security conditions | An order may not be enforceable abroad as an award |
| Early determination | Article 30 | Order or award | Disposes quickly of manifestly unmeritorious defences to payment | Tribunal has discretion whether to allow the application to proceed |
| Emergency arbitrator | Article 31 and Appendix IV | Order | Available before the tribunal is constituted | Rarely suited to money orders; not an award |
| Expedited procedure | Article 32 and Appendix V | Final award | Fast final award on a stand-alone Sub-Clause 21.7 claim | Threshold depends on the date of the arbitration agreement |
For most claimants, a reasoned partial award is the safest instrument. Article 29(1) allows interim measures to take the form of an order or an award, and our guide to Article 29 interim measures explains the difference. An award must be scrutinised by the ICC Court, which adds a little time, but it will normally be recognised under the New York Convention, whereas many courts will not enforce procedural orders.
Where the amount in dispute is modest, a stand-alone Sub-Clause 21.7 arbitration under the expedited procedure can produce a final award on the obligation to comply within months.
Draft the prayer for relief so that the tribunal is asked to decide finally that the respondent is obliged to pay the DAAB sum now, while expressly reserving the merits for later. That framing, endorsed by the majority in Persero II, makes the award harder to attack as provisional and easier to enforce in the respondent's home courts.
Defences in Enforcing DAAB Decisions Arbitration
Because the merits are deferred, the paying party's options are narrow. Tribunals generally will not entertain arguments that the DAAB was simply wrong on the facts or the law; that is what the later merits phase is for. The more credible defences in enforcing DAAB decisions arbitration concern the validity of the decision itself:
- Jurisdiction of the DAAB. The board decided a matter that was never referred to it, or a dispute that had not crystallised under the contract.
- Serious procedural unfairness. A party was denied a fair opportunity to present its case, in breach of the DAAB Procedural Rules.
- Payment or set-off. The sum has already been paid, or the contract permits a set-off that the DAAB decision does not exclude.
- Security. Where the payee's solvency is doubtful, the payer may ask the tribunal to condition enforcement on security or a bank guarantee, mirroring the DAAB's own power under Sub-Clause 21.4.3.
Respondents should also check whether the claimant has fully complied with its own obligations under the decision. Tribunals may be reluctant to grant an enforcement order to a party that is itself in breach of the same decision. The ICC Commission's Report on Construction Industry Arbitrations notes that a tribunal may order compliance with, or relief from, a dispute board decision as an interim measure.
Seat, Set-Aside and Cross-Border Enforcement
The choice of seat shapes every enforcing DAAB decisions arbitration. The supervisory courts decide whether an interim or partial award is a true "award" capable of challenge and enforcement. Singapore's courts, after Persero II, treat a properly framed interim award on the duty to comply as final on that issue. Other jurisdictions have their own approach, and some courts have been reluctant to treat provisional relief as an award. Before filing, check how the seat's arbitration law treats partial awards and whether the time limit for challenging one runs from its notification.
Enforcement abroad raises a second set of questions. The respondent's home courts will apply Article V of the New York Convention, and a paying party may argue that an award ordering payment "pending" the merits is not binding within Article V(1)(e). An award that decides finally the separate obligation to comply, while reserving the merits, answers that argument. It also helps to ask for interest and costs on the compliance phase, so that the award is complete in itself. Our guide to the New York Convention explains the grounds on which recognition may be refused.
State employers bring additional issues, including immunity from execution and the need for budget approvals before payment. Those risks do not prevent enforcement, but they affect timing and the choice of assets to target. Where the employer is a state or state-owned entity, identify early which assets are used for commercial purposes, check whether the contract contains a waiver of immunity, and consider whether the seat's courts will grant interim relief in support of the arbitration while the partial award is pending.
Practical Steps for Claimants and Respondents
For the payee, success in an enforcing DAAB decisions arbitration starts during the DAAB phase. Ask the DAAB to state the sum payable clearly, with any interest and the date by which it must be paid. If the payer does not comply, give a written notice of non-compliance, then file a Request for Arbitration identifying Sub-Clause 21.7 as the basis and seeking a partial award at the earliest possible stage of the timetable. Where the merits arbitration is already running, ask the tribunal to deal with compliance as a preliminary issue at the first case management conference.
For the payer, the priorities are to give a timely and precise NOD, assess whether any genuine jurisdictional or procedural objection exists, and decide whether to offer security in exchange for a stay of payment. It is also worth modelling enforcement risk: an award obtained in a seat such as Singapore, London or Paris will be enforceable in most Convention states, so delay may only add interest and costs. Our guide to the full FIDIC Clause 21 dispute route and the construction and FIDIC disputes overview explain how the enforcement claim fits into the wider case.
How TRW & Co Helps
We act for contractors, employers and state entities on enforcing DAAB decisions arbitration from both sides. Our teams in Dhaka, London, Dubai, New York, Singapore and Delhi advise during the DAAB phase on how decisions should be framed, prepare notices of non-compliance, and file Sub-Clause 21.7 Requests designed to obtain an early partial award. For paying parties, we assess jurisdictional and procedural objections, negotiate security arrangements and plan for the merits phase.
Once an award is issued, we coordinate recognition and enforcement in the jurisdictions where assets are located, working with local counsel where required. We give candid advice on prospects and cost. To discuss a DAAB decision that has not been honoured, or one you are being asked to pay, contact our team.
Frequently asked questions
Can a DAAB decision be enforced directly in court?
Usually not in the way an award can. A DAAB decision is a contractual determination, not an arbitral award, so it falls outside the New York Convention. Where the contract contains an ICC arbitration clause, a party seeking payment will normally need to obtain an order or award from an arbitral tribunal, which can then be recognised and enforced by national courts.
What did the Singapore Court of Appeal decide in Persero II?
In PT Perusahaan Gas Negara (Persero) TBK v CRW Joint Operation [2015] SGCA 30, the majority held that the obligation to promptly comply with a binding DAB decision is distinct from the underlying dispute. Where both are before the tribunal, it may issue an interim or partial award that finally disposes of the compliance issue while the merits proceed.
Is an interim measure order enough to enforce a DAAB decision abroad?
It may not be. Many courts only enforce awards under the New York Convention and decline to recognise procedural orders. Article 29(1) of the 2026 ICC Rules allows the tribunal to issue interim measures as an award, and Article 2 includes interim and partial awards in the definition of award. A reasoned award, scrutinised by the ICC Court, is generally the more robust choice.
Can the paying party argue that the DAAB got the merits wrong?
Generally not at the enforcement stage. The purpose of a binding decision is that it is complied with now and reviewed later. Tribunals usually confine the enforcement phase to whether a valid decision exists, whether it has been complied with, and whether security or another condition is appropriate. Arguments about the merits are reserved for the main arbitration.
How quickly can a DAAB decision be enforced through ICC arbitration?
It depends on the tribunal and the procedure chosen. A stand-alone Sub-Clause 21.7 claim may qualify for the expedited procedure, and a tribunal can address compliance as a preliminary issue. Time is also needed for the ICC Court to scrutinise any award under Article 37 before it is notified to the parties.
Sources
- PT Perusahaan Gas Negara (Persero) TBK v CRW Joint Operation [2015] SGCA 30
- CRW Joint Operation v PT Perusahaan Gas Negara (Persero) TBK [2011] SGCA 33
- ICC 2026 Arbitration Rules (official page and text)
- ICC Arbitration and ADR Commission Report on Construction Industry Arbitrations (2019)
- FIDIC, Conditions of Contract for Construction (Second Edition 2017): amendments list