Force Majeure and Hardship in International Contracts
Force majeure and hardship claims decide who bears the cost of sanctions, epidemics, price shocks and changes in law in long-term contracts. We explain the ICC Force Majeure and Hardship Clauses 2020, how governing laws differ, what RTI v MUR Shipping means for reasonable endeavours, and how to run these claims in ICC arbitration.

Key takeaways
- Force majeure excuses performance during an impediment; hardship triggers renegotiation, adaptation or termination.
- The ICC 2020 clause presumes two of three conditions for listed events such as sanctions and epidemics.
- The ICC hardship clause offers three fallback options if renegotiation fails.
- English law has no general hardship doctrine; French law allows judicial revision under Article 1195.
- RTI v MUR Shipping: reasonable endeavours do not require accepting non-contractual performance.
- Defective or late notices defeat many otherwise strong claims.
Force Majeure and Hardship Claims: The Short Answer
Force majeure and hardship claims arise when an event outside a party's control disrupts a long-term contract. Force majeure deals with events that prevent or impede performance and, if established, suspends or excuses the affected party's obligations and its liability for non-performance. Hardship deals with events that leave performance possible but so much more onerous that the contractual balance is fundamentally upset, and its usual consequence is renegotiation, adaptation or termination rather than excuse.

Whether either remedy is available depends first on the contract. If the contract is silent, the governing law fills the gap, and legal systems differ sharply: some recognise a statutory right to revision for unforeseen circumstances, while others, notably English law, rely on the narrow doctrine of frustration and leave hardship to express drafting. In international arbitration, the tribunal applies the contract and the law chosen by the parties, taking account of trade usages under Article 22 of the 2026 ICC Rules.
This note explains the ICC model clauses published in 2020, the position under major governing laws, and how such claims are presented and defended in ICC arbitration.
The ICC Force Majeure and Hardship Clauses 2020
In March 2020 the ICC published updated Force Majeure and Hardship Clauses, which parties may incorporate by reference or adapt. The force majeure clause comes in a long form and a short form. Under the long form, the affected party must prove three conditions: the impediment is beyond its reasonable control; it could not reasonably have been foreseen when the contract was concluded; and its effects could not reasonably have been avoided or overcome. The ICC notes that this threshold is lower than impossibility.
The clause then lists presumed events, including war and hostilities, civil unrest and terrorism, sanctions and trade restrictions, acts of authority, epidemics and natural disasters, explosions and prolonged breakdowns of utilities, and general labour disturbances. For those events, the first two conditions are presumed, so the affected party need only prove that the effects could not reasonably have been avoided or overcome. Non-performance by a subcontractor qualifies only if the conditions are met for the subcontractor as well.
The affected party must give notice without delay. If it does, relief runs from the time the impediment causes the failure; if notice is late, relief runs only from receipt. Relief lasts while the impediment lasts, the affected party must take reasonable measures to limit its effects, and either party may terminate if the impediment substantially deprives the parties of what they reasonably expected, with a default trigger once it exceeds 120 days.
The hardship clause starts from the principle that a party is bound to perform even if performance has become more onerous. The exception applies where continued performance has become excessively onerous because of an event beyond reasonable control that could not reasonably have been taken into account, and whose consequences could not reasonably have been avoided or overcome. The parties must then negotiate alternative terms within a reasonable time. If negotiations fail, the clause offers three options: termination by the invoking party, adaptation or termination by a judge or arbitrator, or termination only by a judge or arbitrator.
| Feature | ICC force majeure clause | ICC hardship clause |
|---|---|---|
| Trigger | Impediment that prevents or impedes performance | Performance excessively onerous, but still possible |
| Foreseeability | Not reasonably foreseeable at conclusion | Could not reasonably have been taken into account |
| Presumed events | Yes, listed events presume the first two conditions | No list |
| Primary consequence | Relief from performance and liability while the impediment lasts | Duty to negotiate alternative terms |
| If it continues or talks fail | Termination right, default 120 days | Option of termination, or adaptation or termination by tribunal |
What the Governing Law Adds
Model clauses operate against a governing law, and the default rules vary considerably. The United Nations Convention on Contracts for the International Sale of Goods exempts a party from liability in damages under Article 79 where its failure was due to an impediment beyond its control that it could not reasonably have taken into account or overcome. The exemption covers damages only; it does not prevent the other party from exercising other remedies such as avoidance.
The UNIDROIT Principles of International Commercial Contracts, often chosen as rules of law in ICC arbitration or applied as evidence of trade usage, contain both a force majeure provision and a hardship regime. Under the hardship regime, the disadvantaged party may request renegotiation and, if that fails, a court or tribunal may terminate or adapt the contract with a view to restoring its equilibrium.
French law, since the 2016 reform of the law of obligations, allows a party to request renegotiation when an unforeseeable change of circumstances makes performance excessively onerous for a party that had not accepted that risk, and ultimately allows the judge to revise or terminate the contract (Article 1195 of the Civil Code). The provision is widely treated as default law that parties may exclude, and many commercial contracts do so.
English law has no general doctrine of hardship. Absent express wording, a party must show frustration, which requires a supervening event that makes performance impossible, illegal or radically different from what was undertaken. Force majeure is purely contractual, so the wording of the clause controls its scope, notice requirements and effect.
Reasonable Endeavours After RTI v MUR Shipping
Many force majeure clauses say that an event counts only if it cannot be overcome by reasonable endeavours. In RTI Ltd v MUR Shipping BV [2024] UKSC 18, decided on 15 May 2024, the UK Supreme Court considered such a proviso after US sanctions were imposed on the charterer's parent company. The charterer offered to pay in euros rather than the US dollars required by the contract, and to cover any conversion loss. The shipowner refused and suspended performance.
The arbitrators held that the shipowner had failed to use reasonable endeavours because accepting euros would have overcome the problem. The Supreme Court unanimously disagreed: a reasonable endeavours proviso is concerned with securing contractual performance, and does not require a party to accept non-contractual performance, absent clear words. The decision, which arose on an appeal from an arbitral award, underlines that tribunals applying English law will read force majeure clauses closely and will not readily rewrite the parties' bargain.
Running Force Majeure and Hardship Claims in ICC Arbitration
Force majeure and hardship claims raise a predictable set of procedural issues. The first is the tribunal's power. A tribunal can apply a contractual adaptation mechanism or a governing law that permits adaptation, but under Article 22(3) of the 2026 ICC Rules it may act as amiable compositeur or decide ex aequo et bono only if the parties have agreed. A party seeking adaptation should therefore identify the legal source of that power in its Request for Arbitration.
The second is evidence. The claimant must usually prove the event, its causal effect on performance, the absence of reasonable alternatives, compliance with notice requirements and, for hardship, the scale of the disequilibrium. That requires contemporaneous correspondence, operational records and, often, quantum or industry experts. Document production requests under the IBA Rules commonly target internal assessments of the event and mitigation options.
The third is timing. Long-term supply, construction and energy contracts often continue while the dispute is pending. Tribunals may be asked for interim measures under Article 29 to preserve performance or the status quo, and parties may seek early determination under Article 30 of defences that are manifestly without merit, for example a force majeure defence plainly barred by a missed notice deadline. Where the contract also contains a multi-tier clause, the negotiation step should be documented carefully.
Most force majeure and hardship claims fail or succeed on notices. Diarise every contractual deadline, send notices that identify the event, the obligations affected and the expected duration, update them as the situation evolves, and record each mitigation option considered. A strong event with a defective notice is often weaker than a modest event properly notified.
Events That Commonly Trigger Force Majeure and Hardship Claims
Recent years have tested these clauses repeatedly. The pandemic produced a wave of disputes over closed sites, restricted labour movement and collapsed demand, and showed that many clauses did not list epidemics or government lockdowns expressly, leaving parties to argue about general wording such as acts of authority. Tribunals asked whether the event, rather than its economic consequences, actually prevented performance, and whether reduced profitability was enough. Usually it was not.
Sanctions are now the most frequently argued event in cross-border trade and finance. The questions are whether the sanctions apply to the party or its performance, whether performance is prohibited or merely more difficult or expensive, and whether licences or alternative routes were reasonably available. Foreign exchange controls raise similar issues where a party cannot remit payment in the contractual currency.
Energy and commodity price shocks generate hardship arguments, particularly in long-term supply and power purchase agreements. Many such contracts contain price review or reopener clauses, and tribunals generally expect parties to use the specific mechanism rather than a general hardship argument. Changes in law, tariffs and export bans sit between the two categories and are often addressed by dedicated change in law clauses that allocate cost rather than excuse performance.
Climate-related events, such as floods, extreme heat and drought, are increasingly relevant. As such events become more frequent, it becomes harder to argue that they could not reasonably have been foreseen when a contract was concluded, which may shift the analysis from force majeure towards risk allocation and insurance.
Drafting Checklist for Long-Term Contracts
Parties can reduce the risk of contested force majeure and hardship claims by addressing the following points when negotiating:
- whether to incorporate the ICC 2020 clauses and, if so, which hardship option to select;
- which events are listed, including sanctions, epidemics, cyberattacks and changes in law, and whether payment obligations are excluded from relief;
- the notice regime, including content, timing and consequences of late notice;
- the interaction with price review, change in law and stabilisation clauses;
- whether a tribunal may adapt the contract, and on what criteria;
- termination rights after prolonged force majeure, and how pre-termination benefits are accounted for.
These points matter most in sectors with long performance periods, such as energy, infrastructure and commodities, where price shocks and regulatory events are common.
How TRW & Co Helps
We advise claimants and respondents on force majeure and hardship claims across energy, construction, commodities, shipping and supply contracts. Our teams in London, Dubai, Singapore, Delhi, Dhaka and New York review clauses and governing law, prepare and respond to notices, assess whether adaptation or termination is available, and conduct ICC arbitrations in which causation, mitigation and quantum are contested. We also draft and renegotiate clauses for new contracts. For related guidance, see our pages on multi-tier clauses, early determination, drafting a notice of dispute and price review arbitration. To discuss a matter, contact us.
Frequently asked questions
What is the difference between force majeure and hardship?
Force majeure concerns events that prevent or impede performance, and typically suspends or excuses obligations and liability while the impediment lasts. Hardship concerns events that leave performance possible but excessively onerous, and typically leads to renegotiation and, failing agreement, adaptation or termination. Contracts often contain both, and the same event can be argued under either.
Can an ICC tribunal rewrite the price in a contract for hardship?
Only if it has a legal basis to do so. That may come from a hardship clause allowing adaptation, such as option B of the ICC 2020 hardship clause, or from a governing law or rules of law that permit adaptation. Without such a basis, and absent agreement to decide ex aequo et bono, a tribunal will generally apply the contract as written.
Are sanctions a force majeure event?
They can be. The ICC 2020 clause lists sanctions among presumed events, so the affected party need only prove the effects could not reasonably be avoided or overcome. Under other clauses, the wording and governing law control. RTI v MUR Shipping shows that English courts will not require a party to accept non-contractual performance to avoid the effects of sanctions.
What happens if force majeure notice is late?
It depends on the clause. Some clauses make timely notice a condition precedent, so late notice defeats the claim entirely. Under the ICC 2020 long form, late notice means relief runs only from the date the notice reaches the other party. Tribunals look closely at notice compliance, so contemporaneous records matter.
Sources
General information only, not legal advice. References to the ICC, the ICC Court and the ICC Rules describe their published rules and practice; TRW & Co is independent of the ICC.