Preparing for the ICC Case Management Conference
ICC case management conference preparation matters more under the 2026 Rules. The initial CMC must be held within 30 days of the tribunal receiving the file, new claims are barred afterwards without leave, and the timetable it produces drives the award deadline. This guide covers the agenda, Procedural Order No. 1 and budget discussions.

Key takeaways
- The initial CMC must be held within 30 days of the tribunal receiving the file (Article 24(1)).
- Expedited cases: CMC within 15 days; Highly Expedited cases: within seven days.
- After the initial CMC, new claims need the tribunal's authorisation (Article 25).
- The procedural timetable is the basis for the Court President's award time limit (Article 34).
- Terms of Reference are optional under the 2026 Rules and are not sent to the Court.
- Bring a draft PO1, a realistic timetable and a costed comparison of procedural options.
ICC Case Management Conference Preparation: What the Rules Require
Good ICC case management conference preparation starts from one fixed point: under Article 24(1) of the 2026 ICC Rules, the tribunal must hold the initial case management conference (CMC) within 30 days of receiving the file from the Secretariat. The Secretary General may extend that time limit on a reasoned request from the tribunal or on its own initiative. At the CMC, the tribunal consults the parties on the procedural measures it may adopt under Article 23(2), and during the CMC or as soon as possible afterwards it must establish the procedural timetable (Article 24(2)).

The shorter tracks compress this further. Under the Expedited Procedure Provisions, the CMC must be held within 15 days of the tribunal receiving the file (Appendix V); under the Highly Expedited Arbitration Provisions, within seven days (Appendix VI). Under the 2021 Rules the CMC was linked to drawing up the Terms of Reference; under the 2026 Rules the CMC is the anchor, and Terms of Reference are optional.
Three consequences make the initial CMC more important than ever. First, after the initial CMC no party may make new claims without the tribunal's authorisation (Article 25). Second, the procedural timetable set at or after the CMC is the basis on which the Court President fixes the time limit for the final award (Article 34). Third, the CMC is where cost and time are won or lost. Our core page on the case management conference explains the framework; this guide focuses on preparation.
Internal preparation before the agenda arrives
The most useful ICC case management conference preparation happens inside the client team, before any agenda is circulated. Three questions should be answered early. What does the client want from the arbitration, and by when: a quick award, leverage for settlement, or a full vindication of its position? Which witnesses and experts will be needed, and when are they genuinely available? And what is the approved budget, and how is it phased? A procedural timetable that ignores a key witness's availability or the client's financial year end will be hard to keep and costly to change.
Counsel should also review the file as the tribunal will see it: the Request, the Answer, any reply to counterclaims, the Court's decisions on constitution and any prima facie jurisdiction decision. Gaps in the pleadings should be filled before the CMC, because Article 25 restricts new claims afterwards. If an early determination application or a request for bifurcation is planned, say so at the CMC so the timetable can accommodate it rather than be disrupted by it later.
Building the Agenda
Tribunals usually circulate a draft agenda, and Article 24(5) allows them to ask the parties for case management proposals before the CMC. Do not wait to be asked. A party that arrives with a reasoned position on each item tends to shape the outcome. The 2026 Note to Parties lists case management techniques that tribunals are expected to consider, and they make a useful agenda skeleton:
- Issues. Identify the issues to be decided at the outset, and revisit them at later stages.
- Bifurcation or partial awards. Consider them only where they are genuinely expected to make the case more efficient.
- Submissions. Decide between a memorial and a pleadings approach, frontloading of evidence, and limits on length.
- Documents. Decide whether document production is needed at all, and if so its scope, timing and format; see our page on document production.
- Witnesses and experts. Number, sequencing, and whether expert meetings or joint reports would narrow issues.
- Hearings. Format (in person, hybrid or virtual), length, location and dates.
- Settlement. Whether to build in a mediation window, for example under the ICC Mediation Rules.
- Further CMCs. Whether to schedule further CMCs after key stages (Article 24(4)).
Add the case-specific items: any early determination application under Article 30, confidentiality orders under Article 23(3), the appointment of a tribunal secretary under Article 44, data protection, sanctions issues and the language of documents.
Procedural Order No. 1
The CMC usually produces Procedural Order No. 1 (PO1) and a procedural timetable. The Rules do not prescribe the content of PO1, but in practice it records the procedural framework the parties and tribunal have agreed or the tribunal has decided. A typical PO1 deals with:
- the parties, counsel, tribunal and any tribunal secretary;
- communications, electronic filing and the use of ICC Case Connect;
- the sequence, format and length of written submissions;
- evidence, including whether the IBA Rules on the Taking of Evidence serve as guidance;
- document production procedure, often with a Redfern schedule;
- witness statements, expert reports and hearing arrangements;
- confidentiality, data protection and cybersecurity; and
- costs submissions and interim costs decisions.
Prepare a marked-up draft PO1 in advance and agree as much as possible with opposing counsel before the CMC, leaving only genuine disputes for the tribunal. The ICC publishes a Model Data Protection Clause for Procedural Order One, which tribunals may use where the GDPR or similar laws apply. Our insights on Procedural Order No. 1 and procedural timetable templates go further.
Budget and Cost Discussions
Cost belongs on the CMC agenda, not just in the final award. Article 23(1) requires the tribunal and the parties to make every effort to conduct the arbitration expeditiously and cost-effectively, having regard to complexity and value. Effective ICC case management conference preparation therefore includes an internal budget that maps costs to the proposed timetable, so you can argue for or against each procedural step on cost grounds.
Points to raise or prepare for include:
- whether hearing costs will be met from the advance on costs or paid directly to the venue, which the Note to Parties asks tribunals to clarify;
- whether the tribunal will make interim costs decisions under Article 41(3), for example after document production or a failed application;
- any request for security for costs, particularly where a claimant is funded or impecunious; and
- an instalment calendar for the advance, which the Note expects to align with the procedural timetable.
Remember also how arbitrators' fees are fixed. The Court fixes them at the end of the case within the scale, taking into account the tribunal's diligence and efficiency, the time spent, the complexity of the dispute and the timeliness of the draft award (Appendix III, Article 6(2)). Parties cannot agree separate fees with the arbitrators. A timetable that is efficient from the start therefore serves everyone, including the tribunal, and arguments framed in those terms tend to be well received.
For the client's own costs, use the CMC to clarify how costs submissions will be made at the end of the case and what level of detail the tribunal expects. Parties that record their costs against the same procedural phases used in the timetable find it much easier to prepare a persuasive costs submission later.
Bring a costs-and-time comparison of at least two procedural options, for example document production versus no production, or one hearing versus bifurcated hearings. Tribunals respond to concrete proposals far better than to general appeals to efficiency.
Terms of Reference: Optional Under the 2026 Rules
Under the 2021 Rules, Terms of Reference were mandatory and new claims were barred once they were signed or approved. The 2026 Rules make them optional: the Note to Parties treats Terms of Reference as a case management technique to be used if the parties and the tribunal decide it is appropriate, and states that in 2026 Rules cases they will not be transmitted to the Court. When used, they normally summarise the claims and relief sought, the applicable procedural rules and a list of issues. Part of your ICC case management conference preparation is to decide whether a list of issues or a short Terms of Reference would help your case. See our page on Terms of Reference.
ICC Case Management Conference Preparation Checklist
| Task | Rule or source | When |
|---|---|---|
| Confirm the CMC deadline and track (standard, expedited, highly expedited) | Art. 24(1); Apps V and VI | On transmission of the file |
| Plead all known claims before the CMC | Art. 25 | Before the CMC |
| Prepare case management proposals and a draft PO1 | Arts 23(2), 24(5) | Ahead of the tribunal's deadline |
| Build a timetable with realistic witness and expert availability | Art. 24(2) | Before the CMC |
| Map costs to procedural options; plan advance instalments | Arts 23(1), 40(4) | Before the CMC |
| Decide on early determination, bifurcation, Terms of Reference | Art. 30; Note to Parties | Before the CMC |
| Agree format and attendees with opposing counsel | Art. 24(5) | One week before |
Use this ICC case management conference preparation table as a minimum. Complex cases may also need an agreed chronology, a dramatis personae, or a joint list of issues, all of which the Note to Parties recognises as useful jointly produced documents.
On the Day: Format, Attendance and Follow-Up
Absent party agreement, the tribunal decides how the CMC is conducted; it may be in person, hybrid, or by video or telephone (Article 24(5)). The tribunal may also ask for the parties themselves, not just counsel, to attend. Consider bringing a business decision-maker: it signals seriousness about settlement windows and lets you respond on budget questions immediately. Agree in advance who will speak to each agenda item, and keep a running note of every point the tribunal decides or reserves.
Follow-up matters as much as attendance. Review the draft PO1 and timetable against your notes, flag errors promptly, and diarise every deadline. Remember that the tribunal may adopt further procedural measures, modify the timetable or hold further CMCs (Articles 24(3) and 24(4)), so record the reasons for each agreed step; they will matter if the timetable is revisited. Our insight on new claims after the initial CMC explains why the CMC date itself matters.
Illustration (hypothetical): two parties to a construction dispute arrive at the initial CMC with an agreed draft PO1 and only three disputed items. The tribunal resolves them in an hour, sets a timetable that leads to a hearing in about a year, and schedules a further CMC after document production. That is what thorough ICC case management conference preparation looks like in practice.
How TRW & Co Helps
We prepare clients for initial and further CMCs in ICC arbitrations as claimant or respondent. Our teams in Dhaka, London, Dubai, New York, Singapore and Delhi draft case management proposals and Procedural Order No. 1, build timetables around witness and expert availability, prepare budgets that compare procedural options, and advise on bifurcation, early determination, document production, Terms of Reference and confidentiality orders. We coordinate with clients' finance teams on advance instalments and interim costs. We are independent of ICC and do not speak for the Court or the Secretariat. To prepare for a forthcoming CMC, contact our team.
Frequently asked questions
When is the initial case management conference held in ICC arbitration?
Under Article 24(1) of the 2026 ICC Rules, within 30 days from the tribunal receiving the file from the Secretariat, which happens once the tribunal is constituted and the provisional advance is paid. The Secretary General may extend the time limit. Under the Expedited Procedure Provisions the period is 15 days, and in Highly Expedited Arbitrations it is seven days.
What is Procedural Order No. 1?
It is the first procedural order, usually issued after the initial CMC, recording the procedural framework for the arbitration: communications, submissions, evidence, document production, hearings, confidentiality and costs. The ICC Rules do not prescribe its contents, so parties should prepare a draft and agree as much as possible with the other side before the CMC.
Are Terms of Reference still required under the 2026 ICC Rules?
No. The 2026 Rules make the CMC the key early step, and the Note to Parties treats Terms of Reference as an optional case management technique, used if the parties and tribunal consider it appropriate. In arbitrations under the 2026 Rules, any Terms of Reference are not transmitted to the Court. Under the 2021 Rules they remain mandatory.
Can I add claims after the initial CMC?
Only with the tribunal's authorisation. Article 25 of the 2026 Rules provides that after the initial CMC no party may make new claims unless authorised, and the tribunal considers the nature of the new claims, the stage of the arbitration, cost implications and other relevant circumstances. Plead all known claims before the CMC wherever possible.
Should the client attend the CMC?
It is often worthwhile. Article 24(5) allows the tribunal to request the attendance of the parties at any CMC. A business representative can take decisions on budget, timetable and settlement windows on the spot, and their presence can help the tribunal understand the commercial context of the dispute.
Sources
General information only, not legal advice. References to the ICC, the ICC Court and the ICC Rules describe their published rules and practice; TRW & Co is independent of the ICC.