Which ICC Rules Apply? Transitional Provisions Under the 2026 Rules
The ICC Rules 2026 transitional provisions look simple: the new Rules govern arbitrations commenced on or after 1 June 2026. In practice, clause wording, the date of the arbitration agreement and the fee scales each follow their own logic, and multi-party cases can straddle the line. This guide explains how to tell which rules apply.

Key takeaways
- Article 1(2) applies the 2026 Rules to arbitrations commenced on or after 1 June 2026.
- Commencement is the date the Secretariat receives the Request for Arbitration (Article 5(2)).
- Clauses freezing the Rules “in force at the date of the contract” can keep disputes under 2021 Rules.
- Expedited thresholds and emergency arbitrator availability depend on the date of the arbitration agreement.
- The 2026 fee scales apply to arbitrations commencing from 1 June 2026, whatever version governs.
- Joinder and consolidation across the 1 June 2026 line need early discussion with the Secretariat.
ICC Rules 2026 transitional provisions: the short answer
The ICC Rules 2026 transitional provisions are short. Article 1(2) states that the 2026 Rules apply to any arbitration commenced on or after 1 June 2026, unless the parties have agreed to submit to the Rules in effect on an earlier date. Under Article 5(2), an arbitration is commenced on the date the Secretariat receives the Request for Arbitration. So the test is when the Request reaches the Secretariat, not when the contract was signed or the dispute arose.

That simple rule hides several moving parts. Some features of the 2026 Rules depend not on the commencement date but on the date of the arbitration agreement, notably the expedited procedure threshold and the availability of the emergency arbitrator. The fee scales follow a third logic: they apply to arbitrations commencing from 1 June 2026 whatever version of the Rules governs. And clauses that refer to the rules “in force at the date of the contract” can keep a 2026 dispute under the 2021 Rules.
This note works through each of those layers. It uses the official English text of the 2026 Rules, the ICC comparison of the 2021 and 2026 texts and the 1 June 2026 Note to Parties and Arbitral Tribunals. For the substance of the revision, see the key changes explained.
How Article 1(2) differs from the 2021 formula
The 2021 Rules addressed the same question in Article 6(1). Parties who agreed to ICC arbitration were deemed to have submitted ipso facto to the Rules in effect on the date of commencement, unless they had agreed to submit to the Rules in effect on the date of their arbitration agreement. The default, therefore, was already dynamic: the version in force when the case starts.
The 2026 formula keeps that dynamic default but changes the exception. The parties may now have agreed to submit to the Rules in effect on “an earlier date”, without tying that date to the arbitration agreement. That is broader. It covers a clause fixing the Rules in force at contract signature, but also, for example, a later agreement made when a dispute crystallises, or a reference to a named edition. Article 1(1) separately confirms that ICC arbitration is administered exclusively by the ICC International Court of Arbitration, which picks up the content of Article 6(2) of the 2021 Rules.
In practice, the ICC Rules 2026 transitional provisions mean that most arbitrations filed after 1 June 2026 will proceed under the 2026 Rules, because the standard ICC clause does not freeze the version. Arbitrations commenced before that date generally remain under the 2021 Rules throughout, including for later procedural events such as the award time limit or corrections.
Timing a filing around the ICC Rules 2026 transitional provisions is rarely worthwhile on its own, but it can matter at the margins. A claimant that filed in late May 2026 secured the 2021 Rules, with mandatory Terms of Reference and the six-month default award deadline; one that waited until June obtained Article 30 early determination and the new award time-limit regime. Where a limitation period or an urgent need for relief is in play, those considerations will normally dominate.
Respondents, for their part, cannot change the applicable version by delaying their Answer, because the reference point is the claimant’s Request. Under the ICC Rules 2026 transitional provisions, a Request sent by email is treated as received when the Secretariat receives it, so claimants approaching any deadline should keep proof of transmission and confirm the date of receipt that the Secretariat records in its acknowledgement.
Clauses referring to rules “in force at the date of the contract”
Some bespoke clauses specify that the arbitration will be conducted under the ICC Rules “in force at the date of this agreement”, or name a particular edition, such as “the ICC Rules of Arbitration (2021)”. The first form is a clear agreement to an earlier version within Article 1(2). The second is less certain: a year in brackets may be a label identifying the institution’s rules, or a deliberate decision to freeze them. Which reading prevails depends on the interpretation of the arbitration agreement under its governing law, and the question is ultimately one for the tribunal and, if challenged, the courts.
The consequences are real. A case under the 2021 Rules requires Terms of Reference under Article 23, has a six-month default time limit for the award running from their signature, lacks an express early determination power, and has no Highly Expedited track. A case under the 2026 Rules has the opposite on each point. Parties who froze the 2021 version for certainty may therefore have locked in features that the ICC itself has since removed.
Illustration: a 2024 joint venture agreement provides for arbitration under “the ICC Rules in force at the date of this Agreement”. A Request filed in September 2026 would, on the face of the clause, proceed under the 2021 Rules, with mandatory Terms of Reference, even though the 2026 Rules were then in force. The parties could still agree, once the dispute arises, to apply the 2026 Rules instead.
ICC Rules 2026 transitional provisions that turn on other dates
Several provisions use their own reference date. Confusing them is a common source of error, so the table sets them out together.
| Feature | Reference date | Rule |
|---|---|---|
| Which version of the Rules governs | Commencement (receipt of the Request) | 2026 Rules if commenced on or after 1 June 2026, unless an earlier version was agreed (Art. 1(2)) |
| Expedited procedure threshold | Conclusion of the arbitration agreement | US$2m (1 March 2017 to 31 Dec 2020); US$3m (1 Jan 2021 to 31 May 2026); US$4m (from 1 June 2026) (App. V, Art. 1(3)) |
| Expedited procedure excluded | Conclusion of the arbitration agreement | Not applicable to agreements concluded before 1 March 2017, unless parties opt in (App. V, Art. 1(4)) |
| Emergency arbitrator excluded | Conclusion of the arbitration agreement | Not available for agreements concluded before 1 January 2012 (App. IV, Art. 1(3)) |
| Fee scales | Commencement | 2026 scales apply to arbitrations commencing on or after 1 June 2026, irrespective of the version of the Rules |
| Costs fixed in the award | Commencement | Schedule of Fees in force at commencement (Art. 41(1)) |
| Note to Parties guidance | None | Applies to all ICC arbitrations whatever the version, save provisions specific to an earlier version |
The expedited procedure is the clearest example. Because the threshold depends on the agreement date, a claim of US$3.5 million filed in 2027 will fall within the automatic expedited procedure only if the arbitration agreement was concluded on or after 1 June 2026. Our note on the US$4 million threshold discusses amended and restated contracts, where the date of conclusion can itself be contested. The general operation of the track is covered in our expedited procedure guide.
The fee scales are the clearest counter-example. Part II, Article 1 of the 2026 Schedule of Fees makes the new scales effective for all arbitrations commencing on or after 1 June 2026 “irrespective of the version of the Rules applying to such arbitrations”. A case that proceeds under the 2021 Rules because the clause froze that version will nonetheless be costed under the 2026 scales if it commenced after 1 June 2026.
Joinder, consolidation and multi-contract cases across the line
Multi-party and multi-contract disputes raise the hardest transitional questions. Under Article 8(1), the date on which the Secretariat receives a Request for Joinder is deemed to be the date of commencement as regards the additional party. If a Request for Joinder is filed after 1 June 2026 in an arbitration that began earlier, the Rules do not say in terms whether that deemed date changes the applicable version for the new party.
The more coherent view is that an additional party joins the existing proceedings under the version already governing them, since a single arbitration cannot sensibly run under two sets of rules, but the point should be raised with the Secretariat at the outset.
Consolidation raises a similar issue. Article 11(3) provides that consolidated arbitrations are merged into the arbitration that commenced first, unless all parties agree otherwise. Where that first arbitration was commenced before 1 June 2026, the consolidated proceedings may continue under the 2021 Rules even though the later arbitrations were filed under the 2026 version. Parties weighing consolidation should factor this into their position, as it affects Terms of Reference, the award time limit and the availability of early determination.
Pending 2021 Rules cases: what can still change
A case that remains under the 2021 Rules is not frozen in every respect. The 1 June 2026 Note states that its guidance applies to all ICC arbitrations, irrespective of the version of the Rules, except where a provision relates specifically to an earlier version. Its updated case management techniques, guidance on tribunal secretaries and practice on scrutiny therefore inform pending cases too. For arbitrations under earlier versions, the Note encourages tribunals to seek the parties’ agreement to electronic notification of the award.
If both sides would benefit from a 2026 feature in a pending 2021 Rules case, such as electronic notification of the award or a structured early determination step, the cleanest route is a written agreement recorded in a procedural order. Within the 2021 framework, tribunals already have wide case management powers to give effect to such agreements.
The ICC Rules 2026 transitional provisions also leave room for parties to move a new dispute onto the 2026 Rules where their clause would otherwise freeze an older version. Because Article 1(2) is framed around party agreement, an agreement made after the dispute arises to apply the 2026 Rules should be respected. It should be explicit, signed by all parties, and should address features such as the Highly Expedited track, which under Article 33 applies only when all parties agree.
Drafting checklist for new ICC clauses
- Use a dynamic reference to the ICC Rules unless there is a specific reason to freeze a version, and if you freeze one, say so expressly.
- Record the date on which the arbitration agreement is concluded, since it drives the expedited procedure threshold.
- Decide whether to opt into Highly Expedited Arbitration or out of the expedited procedure, using clear words rather than an implied preference for three arbitrators.
- Check that the seat, language and governing law provisions work with the 2026 Rules; our ICC model clauses guide sets out the options.
The ICC Rules 2026 transitional provisions reward attention to dates. Before filing, confirm the commencement date you will achieve, the date of each arbitration agreement relied on and any clause wording that refers to a version of the Rules. Our 2026 Rules overview and emergency arbitrator guide explain the features that depend on them.
How TRW & Co helps
We advise parties on which version of the ICC Rules governs a dispute before they file and when an opponent contests it. Our teams in Dhaka, London, Dubai, New York, Singapore and Delhi analyse clause wording that refers to specific editions, map the reference dates that control the expedited procedure, emergency relief and fees, and assess how joinder or consolidation would affect the applicable version. Where both sides would benefit, we prepare agreements to apply the 2026 Rules or selected features in pending cases. To discuss a specific clause or filing, contact our arbitration team.
Frequently asked questions
Which ICC Rules apply to an arbitration filed in July 2026 under a 2022 contract?
In most cases the 2026 Rules. Article 1(2) applies them to any arbitration commenced on or after 1 June 2026, and commencement is the date the Secretariat receives the Request. The 2022 contract date matters only if the clause agreed to the Rules in force at an earlier date. It does, however, fix the expedited procedure threshold at US$3 million, because that threshold follows the date of the arbitration agreement.
What if my clause says the ICC Rules in force at the date of the contract?
That is an agreement to submit to the Rules in effect on an earlier date, which Article 1(2) respects. A dispute under such a clause would proceed under the version in force when the contract was signed, for example the 2021 Rules, with mandatory Terms of Reference. The parties can agree later to apply the 2026 Rules instead, ideally in a written agreement signed by all of them.
Do the 2026 fee scales apply to arbitrations under the 2021 Rules?
They can. The 2026 Schedule of Fees states that its scales apply to all arbitrations commencing on or after 1 June 2026, irrespective of the version of the Rules governing them. So a case that runs under the 2021 Rules because the clause froze that version, but which commenced after 1 June 2026, will be costed under the new scales. Cases commenced earlier keep the scales in force at their commencement.
Is the emergency arbitrator available for old arbitration agreements?
Only if the arbitration agreement was concluded on or after 1 January 2012 and the parties have not opted out. Appendix IV, Article 1(3) excludes agreements concluded before that date, agreements that opt out and agreements arising from a treaty or an investment protection law. For excluded agreements, parties should consider applications to national courts for interim relief, which the Rules expressly preserve.
Can a pending 2021 Rules arbitration switch to the 2026 Rules?
Only by agreement, and even then with care. Article 1(2) applies the 2026 Rules to arbitrations commenced on or after 1 June 2026. For a pending case, parties can agree to adopt particular procedures, such as electronic notification or a structured early determination step, and the tribunal can give effect to that through its case management powers. A full switch would need clear agreement of all parties and consultation with the Secretariat.
Sources
- ICC 2026 Arbitration Rules (official page)
- ICC 2026 Arbitration Rules and 2014 Mediation Rules, English text (PDF)
- ICC Arbitration Rules 2021 and 2026 compared version (PDF)
- ICC Note to Parties and Arbitral Tribunals on the Conduct of ICC Arbitration, 1 June 2026 (PDF)
- ICC: Unveiling the 2026 ICC Arbitration Rules, part 3 – Expedited Procedure Provisions and Emergency Arbitration