Arbitrating Against Indian Public Sector Undertakings
India public sector arbitration has been reshaped by the Supreme Court and by government policy. Unilateral appointment of arbitrators by PSUs is no longer permitted, but challenges and appeals still delay payment. This insight explains the case law, the 2024 procurement guidelines and practical steps for contractors.

Key takeaways
- A party interested in the outcome cannot unilaterally appoint a sole arbitrator (Perkins Eastman, 2019).
- The 2024 Constitution Bench in CORE barred forcing parties to choose from PSU-curated panels.
- Waiver of section 12(5) ineligibility requires express written agreement after disputes arise.
- Since 2015, a section 34 challenge does not automatically stay enforcement of an award.
- 2024 Finance Ministry guidelines discourage routine arbitration clauses for disputes above Rs 10 crore.
- Institutional appointment, such as by the ICC Court, avoids most appointment disputes.
India public sector arbitration: the short answer
India public sector arbitration, meaning arbitration against central and state public sector undertakings (PSUs), statutory authorities and government departments, has changed significantly since 2017. The Supreme Court has dismantled the once-standard clause under which the PSU appointed the arbitrator: a party with an interest in the outcome cannot unilaterally appoint a sole arbitrator, and a 2024 Constitution Bench held that forcing the other side to choose from a PSU-curated panel breaches equal treatment and, in public-private contracts, Article 14 of the Constitution. Delay remains the larger practical risk, because awards against PSUs are frequently challenged through several tiers of courts.

Government policy has also shifted. Guidelines issued by the Ministry of Finance in June 2024 discourage routine arbitration clauses in domestic public procurement, especially for high-value disputes, and encourage mediation. Foreign contractors, suppliers and investors dealing with Indian PSUs need to understand all three developments: appointment, delay and policy.
This insight explains each, with a focus on ICC arbitration and practical steps for contractors. For general principles on state counterparties, see our guide to sovereigns and state-owned entities.
Unilateral appointment: from TRF to the 2024 Constitution Bench
For decades, PSU contracts commonly provided that disputes would go to a sole arbitrator appointed by the PSU's chairman or managing director, or to a tribunal drawn from a panel of retired officers maintained by the PSU. The 2015 amendments to the Arbitration and Conciliation Act 1996 introduced section 12(5) and the Seventh Schedule, which make a person ineligible to act as arbitrator if their relationship with a party, counsel or the subject matter falls within listed categories, notwithstanding any prior agreement. Employees, consultants and advisers of a party fall within the Schedule.
Who counts as the public sector
The term covers a wide range of counterparties: central public sector enterprises owned by the Government of India, state government undertakings, statutory authorities such as highway and port authorities, government departments contracting directly, and public sector banks. Most are "State" for the purposes of Article 12 of the Constitution, which is why constitutional equality principles apply to their contracts. For India public sector arbitration purposes, the label matters less than the clause: the same appointment and delay issues arise whether the counterparty is a railway body, a power utility or a central PSU running a hospital project.
The Supreme Court then built a line of authority on that foundation:
| Decision | Holding |
|---|---|
| TRF Ltd v Energo Engineering Projects (2017) | A managing director who is ineligible to act as arbitrator cannot nominate one either. |
| Perkins Eastman Architects v HSCC (India) (2019) | A party with an interest in the outcome cannot unilaterally appoint a sole arbitrator. |
| CORE v ECI SPIC SMO MCML (JV) (Constitution Bench, 8 November 2024) | Equal treatment applies at the appointment stage; a party cannot be forced to choose from a curated panel; unilateral appointment clauses in public-private contracts violate Article 14. |
In Perkins Eastman, a New York architecture firm's consortium challenged an appointment made by the chairman and managing director of a central PSU under a design contract for a public hospital. The Court set the appointment aside and appointed a sole arbitrator itself. Our note on Perkins Eastman and unilateral appointments covers the facts and reasoning.
What the Constitution Bench decided
In Central Organisation for Railway Electrification v ECI SPIC SMO MCML (JV), the Constitution Bench concluded that PSUs may maintain panels of potential arbitrators, but cannot require the other party to select its arbitrator from a panel the PSU has curated. A clause allowing one party to appoint a sole arbitrator unilaterally gives rise to justifiable doubts about independence and impartiality. Parties may waive the objection under the proviso to section 12(5), but only by express agreement in writing after disputes have arisen. The Court directed that its ruling applies prospectively to appointments made after the date of the judgment, and that this direction applies to three-member tribunals.
What the appointment rules mean for India public sector arbitration
For contractors, the effect is that an India public sector arbitration clause giving the PSU control of the tribunal is no longer a trap without an exit. If a PSU appoints a sole arbitrator unilaterally, the contractor can object and apply to the court under section 11 for an appointment, provided it has not waived the objection in writing after the dispute arose. For three-member tribunals constituted after 8 November 2024, a requirement to pick from the PSU's panel is open to challenge.
Care is still needed. Participating in the arbitration without objecting is not, on its own, an express written waiver under section 12(5), but conduct can create other difficulties. Raise objections promptly and in writing, and avoid signing procedural documents that could be read as an agreement to the appointment. For tribunals constituted before the 2024 judgment, the transitional position needs specific advice.
The same principles reach beyond public sector contracts. Private lenders and large companies have also used unilateral appointment clauses, and Perkins Eastman applies to them, although the Article 14 reasoning in CORE is specific to public-private contracts.
When negotiating with a PSU, propose institutional appointment. The ICC Court's appointment process, or a neutral appointing authority, meets the equal-treatment standard and avoids later litigation over the tribunal's composition.
How ICC arbitration fits
Where a PSU agrees to ICC arbitration, as some do in international contracts with foreign contractors and suppliers, the appointment issues largely fall away, because neither side controls the choice of the presiding arbitrator. Under Article 14(4)(a) of the 2026 ICC Rules, the ICC Court may appoint arbitrators directly where a party is a state or may be considered a state entity. Article 13(10) allows the Court, in exceptional circumstances and notwithstanding the parties' agreement, to appoint every member of the tribunal to avoid a significant risk of unequal treatment or unfairness. Our guide to constitution of the tribunal explains the process.
Delay: where India public sector arbitration time is lost
The main frustration for contractors is not the arbitration itself but what happens after it. PSUs and government bodies often treat a challenge to an adverse award as an institutional necessity, so many awards pass through a section 34 challenge, an appeal under section 37 and a petition to the Supreme Court. Each stage can take substantial time, and the cumulative period from award to payment is often measured in years rather than months.
| Stage | Statutory position | Practical effect |
|---|---|---|
| Making the award (India seat) | Section 29A: award within 12 months of completion of pleadings, extendable by six months by consent, then by the court; for international commercial arbitration the period is a target | Time limits have reduced extreme delays in domestic cases |
| Challenge (India seat) | Section 34: three months from receipt of the award, plus up to 30 days for sufficient cause | A challenge is common in PSU cases |
| Stay of enforcement | Section 36: no automatic stay since 2015; the court may impose conditions such as a deposit | Contractors may obtain part payment while the challenge runs |
| Appeals | Section 37 appeal, then a petition to the Supreme Court | The longest phase in many matters |
Since the 2015 amendments, filing a section 34 challenge no longer suspends enforcement automatically. Courts have frequently required government bodies to deposit all or part of the awarded sum as a condition of a stay, and contractors have often been permitted to withdraw deposited sums against security. A 2021 amendment allows an unconditional stay where the court is prima facie satisfied that the agreement or award was induced by fraud or corruption.
The scope of review is narrow. The Supreme Court's decision in Ssangyong Engineering v NHAI (2019) limited the patent illegality ground to errors on the face of the award in domestic cases, and excluded it entirely for international commercial arbitrations. Our note on Ssangyong v NHAI explains the grounds.
Interest and the cost of delay
Delay has a price for both sides. Section 31(7) allows the tribunal to award interest up to the date of the award and provides for post-award interest until payment, at the rate the award directs or, failing that, at a statutory default rate. Where the contract restricts interest, tribunals and courts have generally given effect to the restriction, so contractors should read interest clauses carefully before signing. For a long India public sector arbitration, the post-award interest rate can be worth more than some heads of claim, and it shapes the PSU's incentive to settle rather than appeal.
Government policy: the 2024 guidelines and settlement schemes
On 3 June 2024, the Department of Expenditure in the Ministry of Finance issued Guidelines for Arbitration and Mediation in Contracts of Domestic Public Procurement. They state that arbitration should not be routinely or automatically included in procurement contracts. As a norm, arbitration may be limited to disputes with a value below Rs 10 crore, measured by the value of the dispute rather than the contract. Including arbitration for larger disputes requires recorded reasons and approval at a senior level, such as the Secretary of the ministry or the managing director of a central PSU.
The guidelines encourage mediation under the Mediation Act 2023 and negotiated settlement, including through high-level committees that may include a retired judge or senior technical expert. Where arbitration is used, institutional arbitration may be preferred after considering cost. The guidelines are policy, not legislation: they do not affect existing arbitration agreements, but they influence what PSUs will accept in new contracts.
For foreign contractors, the practical consequence is that India public sector arbitration may not be on offer at all for large domestic procurement contracts. Bidders should read tender dispute clauses early, raise concerns through pre-bid queries where the process allows, and price the risk of a court-only or mediation-first regime. Where the contract is international, such as a supply contract financed by a multilateral lender, the lender's procurement rules may require international arbitration regardless of the domestic guidelines.
The government has also used one-time settlement schemes. The Vivad se Vishwas II (Contractual Disputes) scheme, launched in 2023, offered contractors settlement of up to 65% of the net amount of arbitral awards passed on or before 31 January 2023, and up to 85% of court-awarded amounts, with claims due by 31 October 2023. Such schemes show that the government recognises the cost of prolonged litigation, but their terms require careful evaluation against the prospects of the challenge.
Practical steps for contractors and investors
India public sector arbitration rewards preparation at three points: contract negotiation, the dispute itself and enforcement.
- At negotiation. Seek institutional arbitration with neutral appointment, a clear seat, and a mechanism for interim payments or bank guarantees. Recognise that, under the 2024 guidelines, the PSU may resist arbitration for large disputes; consider what alternative, such as a dispute board or structured mediation, would protect you.
- When the dispute arises. Follow the contract's notice and escalation provisions strictly, since PSUs frequently rely on them as preconditions. Object to any non-compliant appointment immediately and in writing.
- During the arbitration. Build a record that will survive a section 34 or section 48 challenge: reasons on each issue, clear treatment of contractual time bars, and documented procedural fairness.
- Protect security instruments. PSUs frequently hold performance and retention guarantees. Where an encashment is threatened in connection with the dispute, consider urgent court relief, recognising that Indian courts restrain calls on unconditional bank guarantees only in narrow cases such as egregious fraud or irretrievable injustice.
- After the award. Oppose any unconditional stay, seek a deposit, and consider whether a settlement scheme or negotiated payment is commercially better than years of appeals.
Keep the commercial relationship in view. Many contractors continue to work with the same PSU on other projects while a dispute runs, and internal approval processes mean that PSU officers may be unable to settle without a defensible record. Structured proposals supported by independent expert analysis, or a formal mediation, can give decision-makers the cover they need to agree a payment that a contested appeal would otherwise postpone for years.
Foreign contractors should also consider whether a bilateral investment treaty or a foreign seat is available. India terminated many of its older bilateral investment treaties from 2017, so treaty protection should be checked case by case. A foreign seat removes the section 34 stage, though enforcement in India against a PSU still proceeds through the High Courts under Part II. Our guide to India as a seat compares the routes.
How TRW & Co helps
We advise contractors, suppliers, investors and lenders in disputes with Indian public sector undertakings and government bodies, and we also advise state-linked entities on procedure and settlement. Our work covers clause negotiation, objections to non-compliant appointments, conduct of ICC and other institutional arbitrations, and strategy for challenge, stay and enforcement proceedings, coordinated with Indian litigation counsel. Our teams in Delhi, Dhaka, London, Dubai, Singapore and New York bring together Indian law knowledge and international arbitration practice, and we help clients evaluate settlement offers and government schemes against the realistic timetable of a challenge. To discuss a contract or a dispute, please contact us.
Frequently asked questions
Can an Indian PSU still appoint the arbitrator under its contract?
Not unilaterally as sole arbitrator. Since Perkins Eastman (2019), a party with an interest in the outcome cannot appoint a sole arbitrator alone. In CORE (2024), a Constitution Bench held that a party cannot be required to choose its arbitrator from a PSU-curated panel, and that unilateral appointment clauses in public-private contracts violate Article 14. The CORE ruling applies to appointments made after 8 November 2024.
Can a contractor waive the objection to a PSU-appointed arbitrator?
Yes, but only expressly. The proviso to section 12(5) allows parties to waive ineligibility by an express agreement in writing after disputes have arisen, and CORE confirmed that the same principle applies to objections of bias against a unilaterally appointed arbitrator. Silence or participation alone is not an express written waiver, but objections should be raised promptly.
Does a challenge to an award against a PSU stop enforcement?
Not automatically. Since the 2015 amendments, filing a section 34 application does not stay the award by itself. The PSU must apply for a stay, and the court may impose conditions such as depositing all or part of the award. An unconditional stay is available only where fraud or corruption is shown prima facie.
What did the 2024 Finance Ministry guidelines change?
The Department of Expenditure guidelines of 3 June 2024 say that arbitration should not be routinely included in domestic public procurement contracts and, as a norm, may be limited to disputes below Rs 10 crore. Larger disputes require recorded reasons and senior approval for arbitration. The guidelines encourage mediation. They are policy and do not override existing arbitration agreements.
Will a PSU agree to ICC arbitration?
Some PSUs accept ICC or other institutional arbitration, particularly in international contracts with foreign contractors or suppliers, and the 2024 guidelines express a preference for institutional arbitration where arbitration is used. Whether a particular PSU will agree depends on its internal approvals and bargaining position, so the clause should be negotiated early.
Sources
- Central Organisation for Railway Electrification v ECI SPIC SMO MCML (JV), Supreme Court of India, 8 November 2024
- Perkins Eastman Architects DPC v HSCC (India) Ltd, Supreme Court of India, 26 November 2019
- Department of Expenditure, Guidelines for Arbitration and Mediation in Contracts of Domestic Public Procurement, 3 June 2024
- Press Information Bureau: Vivad se Vishwas II (Contractual Disputes) scheme
- ICC 2026 Arbitration Rules (Articles 13 and 14)
- Arbitration and Conciliation Act 1996 (India Code)
General information only, not legal advice. References to the ICC, the ICC Court and the ICC Rules describe their published rules and practice; TRW & Co is independent of the ICC.