Middle East Energy Transition Disputes
Middle East energy transition disputes are growing with the region's hydrogen, solar, storage and grid programmes. We explain where claims arise, from EPC delays and technology guarantees to offtake and curtailment, and how the 2026 ICC Rules on multi-contract claims, experts and urgent relief help parties manage them.

Key takeaways
- The UAE aims to triple renewables' contribution by 2030 and exceed 28 GW of clean capacity by 2031.
- Single hydrogen projects can involve dozens of interlocking contracts and billions of dollars.
- Interface gaps between EPC, technology supply and power packages drive many performance claims.
- Energy accounted for 15% of new ICC cases in 2025, second only to construction.
- Articles 8, 10 and 11 of the 2026 ICC Rules help keep multi-contract disputes together.
- State-owned counterparties raise authority, approval and immunity issues to address before signing.
Middle East Energy Transition Disputes: The Short Answer
Middle East energy transition disputes are the claims that arise from the region's build-out of solar, wind, green and blue hydrogen, battery storage, transmission and carbon capture projects. They are mostly contractual: delay and performance claims under EPC contracts, warranty claims against technology suppliers, tariff and offtake disputes, grid connection and curtailment claims, and shareholder disputes inside project joint ventures. Because the projects combine state-linked offtakers, international sponsors, export credit and commercial lenders, and supply chains spread across Asia and Europe, the contracts usually refer disputes to international arbitration, and ICC arbitration is one of the standard choices.

This note explains where the disputes come from, the contract terms that most often decide them, and how the 2026 ICC Rules, in force since 1 June 2026, deal with multi-contract projects, technical evidence and urgent relief. It sits alongside our sector page on energy, oil and gas and renewables and our Middle East desk.
The Projects Behind the Disputes
The scale of investment explains the volume of potential claims. The updated UAE Energy Strategy 2050 aims to triple the contribution of renewable energy by 2030 and to raise installed clean energy capacity from 14.2 GW to more than 28 GW by 2031, with national investment estimated at AED 150 to 200 billion. Saudi Arabia's National Renewable Energy Program, run under the Ministry of Energy, procures successive rounds of utility-scale solar and wind capacity, and other Gulf states and Egypt have announced comparable programmes. Oman and Egypt are also positioning themselves as hydrogen exporters.
Hydrogen illustrates the size of single projects. According to ACWA Power, the NEOM Green Hydrogen Project is an equal joint venture between NEOM, Air Products and ACWA Power, designed to produce 600 tonnes per day of hydrogen by electrolysis and up to 1.2 million tonnes per year of green ammonia, powered by around four gigawatts of solar and wind capacity, at a project cost of about US$8.5 billion, with first product expected in 2027. These are the sponsor's figures.
A project of that kind rests on dozens of interlocking contracts, each a potential source of Middle East energy transition disputes, and the sponsor's published figures may change as the project moves into operation.
| Project type | Typical contracts | Recurring dispute themes |
|---|---|---|
| Utility-scale solar and wind | PPA with state utility; EPC; module and turbine supply; O&M | Delay liquidated damages, performance ratio and degradation guarantees, change in law, curtailment |
| Green and blue hydrogen and ammonia | Electrolyser supply; licence agreements; EPC; offtake; shareholders' agreement | Technology performance, integration risk between packages, offtake volume and price, cost overruns |
| Battery storage | Supply and integration; capacity or tolling agreement | Availability guarantees, warranties, fire and safety incidents |
| Transmission and interconnectors | Grid connection agreement; EPC; cross-border agreements | Connection delays, allocation of grid risk, state-to-state arrangements |
| Carbon capture and storage | Capture plant EPC; transport and storage agreements | Capture rate guarantees, liability for leakage, regulatory change |
Where the Claims Arise
Construction and integration. Most claims start on site. Fixed-price EPC contracts for solar and hydrogen plants allocate delay and performance risk to the contractor, but the interfaces between packages, for example between the electrolyser supplier, the balance-of-plant contractor and the renewable power plant, leave gaps. When the plant does not reach guaranteed output, each party points to another package. Where contracts are based on FIDIC forms, time-bar notices and engineer's determinations decide much of the outcome; claims procedures under those forms deserve as much attention as the technical case.
Technology performance. Electrolysers, high-capacity modules and long-duration storage are newer technologies with limited operating history at gigawatt scale. Disputes turn on how performance guarantees were defined, the test conditions, degradation allowances, and whether the owner operated the plant within the supplier's specifications. Warranty caps and exclusions of consequential loss often matter as much as the technical findings.
Offtake, tariff and change in law. Long-term PPAs and hydrogen offtake agreements fix price and volume for decades. Claims arise from curtailment, grid unavailability, deemed energy payments, indexation, and new taxes or regulations. Our note on renewable energy PPA disputes examines these terms in detail.
Joint ventures and financing. Sponsor groups commonly combine a state-linked entity, a regional developer and an international technology partner. Disagreements over cost overruns, cash calls, deadlock and exit can lead to shareholder arbitrations that run alongside the construction claims.
Lenders and direct agreements. Project finance adds direct agreements that give lenders step-in rights and notice of defaults. Lenders are rarely parties to the construction or offtake arbitration, but their consent may be needed before a settlement, a termination or a change to the contract price, and a default notice served in the wrong form can trigger cross-defaults under the financing. Claims strategy therefore has to be checked against the finance documents as well as the project contract.
Quantum. Damages in these cases often depend on lost revenue over a long contract life, discounted to present value, or on the cost of remedial works and replacement equipment. Assumptions about future power and hydrogen prices, degradation and availability move the numbers significantly, so quantum experts should be engaged early and given the operating data they need.
Pre-Arbitral Steps and Forum Choice
Notices, experts and dispute boards
Most project contracts set out a staged process before arbitration: notice of claim, negotiation between senior executives, expert determination of technical questions, and in construction contracts a dispute avoidance or adjudication board. These steps are useful, because many technical disagreements resolve once an independent expert has examined the data. They are also a frequent source of jurisdictional objections if a party starts arbitration without completing them. Tribunals and courts differ on whether non-compliance goes to jurisdiction or admissibility, so the safer course is to complete each step, or document why it could not be completed, before filing a Request for Arbitration.
Three drafting points help. First, state time limits for each step and say what happens if a step is not completed in time, so that a party can move on to arbitration with certainty. Second, define the scope of expert determination narrowly, confined to technical or valuation questions, and say whether the expert's decision is final or can be reopened in arbitration. Third, preserve the right to seek urgent relief from an emergency arbitrator or a court at any stage. Contracts that follow these points tend to channel Middle East energy transition disputes into a predictable sequence rather than a contest over procedure.
Seat, language and governing law
Seat choice for these projects usually lies between a regional seat, such as onshore Dubai or Abu Dhabi, the DIFC, the ADGM or Riyadh, and an established international seat such as London, Paris or Singapore. State-linked counterparties often prefer a local seat and local governing law, while international sponsors and lenders often prefer English law and a neutral seat. Either way, the seat decides which courts supervise the arbitration and hear any challenge to the award, so it should be chosen with enforcement in mind. Our guide to choosing seat, governing law and language sets out the factors.
Language and governing law deserve equal care. Where local law governs, mandatory rules on matters such as limitation of liability, liquidated damages and termination may override the contract's allocation of risk, and some local courts reduce agreed damages that they consider excessive. An English-language arbitration seated in a Model Law jurisdiction, with a clear choice of governing law, reduces uncertainty for all parties. It also helps to agree at the outset how documents in Arabic, Chinese or other languages of the supply chain will be translated, because technical records from manufacturers are often not in the language of the arbitration and translation costs can be substantial in document-heavy performance cases.
Hydrogen, Solar and Grid: Contract Risks to Address Early
Hydrogen
Hydrogen projects add a further layer: product specification and certification. Export offtakers increasingly require proof that hydrogen or ammonia meets a defined carbon intensity, and certification schemes are still developing. If a certification standard changes during the life of the offtake agreement, who bears the cost of compliance, and can the buyer reject product? Contracts that leave this open invite Middle East energy transition disputes years after commissioning.
Solar and wind
In solar and wind projects the most common points of contention are the performance ratio test, module degradation, soiling and cleaning obligations in desert conditions, and the allocation of grid curtailment risk. Many disputes are settled once both sides' technical experts agree on the data, which makes early, joint data-sharing protocols valuable. Owners should keep SCADA data, inverter logs, meteorological records and cleaning schedules in a form that can be produced and analysed, because performance claims are won or lost on the quality of the operating record.
Grid and interconnection
Transmission projects and interconnectors depend on state utilities and, for cross-border links, on intergovernmental arrangements. Delays in connection works can strand completed generation assets. Contracts should state who bears that risk, how deemed completion works, and whether payments continue while the grid is unavailable.
Middle East Energy Transition Disputes Under the 2026 ICC Rules
ICC arbitration is well established in the sector. In its dispute resolution statistics for 2025, the ICC reported 881 new cases under its Arbitration Rules, with energy accounting for 15% of filings, second only to construction and engineering. Several features of the 2026 Rules are particularly useful for Middle East energy transition disputes:
- Multi-contract claims and joinder. Article 10 allows claims under more than one contract to be brought in a single arbitration, Article 8 governs joinder of additional parties, and Article 11 governs consolidation. Each depends on compatible arbitration agreements, which is why clause alignment across the project documents matters.
- Technical evidence. Under Article 26 the tribunal hears party-appointed experts and may, after consulting the parties, appoint its own expert under Article 26(3). Expert conferencing and joint expert reports are common in performance disputes.
- Early determination. Article 30 allows a party to apply for early determination of claims or defences that are manifestly without merit or manifestly outside the tribunal's jurisdiction.
- Urgent relief. Before the tribunal is constituted, Article 31 and Appendix IV provide for an emergency arbitrator, who may now issue preliminary orders. Appendix IV does not apply where the arbitration agreement arises from a treaty or an investment protection law.
- Smaller claims. For agreements concluded on or after 1 June 2026, the expedited procedure applies automatically to disputes up to US$4 million unless the parties opt out, which suits many supply and O&M disputes.
The ICC Commission's report on resolving climate change related disputes, published in 2019, also discusses features that can help these cases, such as access to scientific expertise and efficient procedures.
State Parties, Treaties and Enforcement
Many offtakers, grid operators and co-investors are state-owned. That raises questions of authority to agree to arbitration, approvals required under local law, and immunity from execution at the enforcement stage. Sponsors should obtain clear evidence of authority and, where possible, an express waiver of immunity from execution. Every GCC state and Egypt is a party to the New York Convention, according to the UNCITRAL status table, but local enforcement practice varies, and assets of state entities may be protected by local law.
Foreign investors may also have treaty protection. Where a government changes a tariff regime or a subsidy, a contractual claim against the offtaker can sit alongside a potential investment treaty claim against the state. Our note on UAE and Saudi investment treaty networks explains the treaty landscape, and our insight on the investment carve-out from ICC emergency arbitration explains why urgent relief works differently in treaty-based cases.
Align the dispute resolution clauses across the EPC, supply, O&M, offtake and shareholder agreements before financial close: the same institution, seat, language and compatible tribunal provisions, with express consent to consolidation and joinder. Mismatched clauses are the single most common reason that Middle East energy transition disputes fragment into parallel proceedings with inconsistent outcomes.
Illustration: a green ammonia plant fails its performance test. The owner blames the electrolyser supplier; the supplier blames the balance-of-plant contractor's water treatment system; the contractor blames power supply fluctuations from the solar plant. If all three contracts provide for ICC arbitration with the same seat and compatible clauses, the owner can seek to bring the claims together under Articles 8 and 10 of the 2026 Rules. If one contract instead provides for local court litigation, the owner may face separate proceedings and the risk of inconsistent findings. This example is hypothetical.
How TRW & Co Helps
From Dubai, working with our teams in London, Singapore, New York, Delhi and Dhaka, we advise sponsors, contractors, suppliers, lenders and state-linked entities on energy transition projects across the Middle East. We review and align dispute resolution clauses across project documents before financial close, advise on notices and claims during construction and operation, act for claimants and respondents in ICC arbitrations, and coordinate technical experts on performance, delay and quantum. We also plan urgent relief and enforcement strategy where state entities or assets in several jurisdictions are involved. To discuss a project or a dispute, please contact our team.
Frequently asked questions
What are the most common Middle East energy transition disputes?
Most are contractual: delay and performance claims under EPC contracts for solar, wind and hydrogen plants; warranty claims against technology suppliers such as electrolyser and module manufacturers; tariff, curtailment and change-in-law claims under PPAs and offtake agreements; and joint venture disputes over cost overruns and funding. Treaty claims can arise where a state changes the regulatory regime.
Why is ICC arbitration common for these projects?
The projects involve international sponsors, lenders and suppliers alongside state-linked offtakers, so parties want a neutral forum and awards enforceable under the New York Convention. The 2026 ICC Rules also offer tools suited to complex projects, including multi-contract claims, joinder, consolidation, tribunal-appointed experts, early determination and emergency arbitrator relief.
Can claims under several project contracts be heard together?
Often, if the contracts are drafted for it. Article 10 of the 2026 ICC Rules allows claims under more than one contract in a single arbitration, and Articles 8 and 11 deal with joinder and consolidation. Each depends on compatible arbitration agreements, so the clauses in the EPC, supply, O&M and offtake contracts should be aligned before signing.
Is emergency arbitrator relief available against a state entity?
Under the 2026 ICC Rules, a party to a commercial contract with a state-owned entity can usually apply to an emergency arbitrator under Article 31 and Appendix IV. The emergency arbitrator provisions do not apply where the arbitration agreement arises from a treaty or an investment protection law, so treaty-based claims require a different approach to urgent relief.
How should hydrogen offtake agreements deal with certification risk?
They should define the product specification and any carbon intensity standard precisely, state which certification scheme applies, and allocate the cost and consequences if that scheme changes during the contract term. Clear rejection rights, price adjustment mechanisms and an expert determination step for technical disagreements reduce the risk of later disputes.