Shipbuilding Contract Disputes
Shipbuilding arbitration decides who bears the cost when a newbuilding is late, underperforms or is cancelled. This note explains delay and cancellation clauses, refund guarantees after Rainy Sky v Kookmin Bank, technical disputes, and when ICC arbitration is a better fit than the LMAA Terms.

Key takeaways
- Most newbuilding contracts are governed by English law with London arbitration, usually under the LMAA Terms.
- Permissible delay notices and cancellation thresholds decide most delay disputes.
- Rainy Sky v Kookmin Bank requires refund guarantees to be read with business common sense.
- Refund guarantees often defer payment until an award if the yard starts arbitration.
- ICC suits offshore units, state-owned yards and multi-contract projects needing joinder and consolidation.
Shipbuilding arbitration: the essentials
Shipbuilding arbitration is the default forum for disputes between shipyards and buyers. Most newbuilding contracts, whether based on the Shipbuilders' Association of Japan (SAJ) form, the Norwegian standard form, a Chinese yard form or BIMCO's NEWBUILDCON, are governed by English law and refer disputes to arbitration in London, most often under the Terms of the London Maritime Arbitrators Association (LMAA). ICC arbitration is a strong alternative for offshore units, specialised vessels, state-owned yards and multi-contract projects, where institutional administration, scrutiny of awards and multi-party tools add value.

The disputes themselves follow a familiar pattern. Delay and the yard's entitlement to extra time, technical shortfalls in speed, fuel consumption or deadweight, buyers' rights to cancel, and calls under refund guarantees account for most cases. Market cycles shape when they arise: in a falling market buyers look for reasons to cancel, and in a rising market yards resist delivery at contract prices. This note explains the main issues and when ICC rather than LMAA arbitration is the better fit.
Delay, permissible delay and cancellation
Newbuilding contracts set a delivery date and allow the yard extensions for "permissible delays": force majeure events, buyer-caused delays, modifications and, often, delays in the supply of buyer's equipment. Beyond a short grace period, the yard pays liquidated damages for each day of non-permissible delay, usually capped at a fixed number of days. Once total delay passes a long-stop date, the buyer may cancel and recover its pre-delivery instalments with interest.
Most shipbuilding arbitration about delay turns on three questions:
- Was the delay permissible? Yards must usually give notice of a force majeure event within a set period and then notify its end and the resulting extension. Missing those notices can forfeit the extension.
- How is permissible delay counted towards cancellation? Contracts differ on whether force majeure delays count towards the buyer's cancellation threshold, and the drafting decides whether cancellation is valid.
- Was the cancellation itself valid? A buyer who cancels prematurely risks being in repudiatory breach, exposing it to the yard's claim for the contract price less resale value.
Liquidated damages are generally treated as the exclusive remedy for delay within the cap. Arguments that the clause is a penalty rarely succeed in commercial shipbuilding contracts governed by English law. Our note on liquidated damages in arbitration covers the wider principles.
Illustration: a yard delivers a vessel 200 days late. It claims that 120 days were permissible, citing a typhoon, late approval of drawings by the buyer and a supplier's insolvency. The buyer accepts the typhoon but says the yard gave notice of the drawing delay late, and that a supplier's insolvency is a risk the yard bears. If the contract allows cancellation after 180 days of non-permissible delay, the classification of each period decides not only the liquidated damages but whether the buyer could have walked away. Contemporaneous notices, production schedules and correspondence about drawing approvals will be the key evidence.
Technical disputes and performance shortfalls
Newbuilding contracts specify guaranteed speed, fuel consumption, deadweight and other performance criteria. Shortfalls within a band attract price reductions on a sliding scale; beyond it, the buyer may reject the vessel. Sea trial results, measurement methods and the condition of trials are therefore frequent sources of argument.
Many contracts send technical disagreements about construction or conformity with specifications to the classification society, whose decision is final on technical questions, while legal disputes go to arbitration. The line between "technical" and "legal" is not always clear, and a party may argue that the classification society exceeded its remit. Where an independent expert opinion is needed, the ICC International Centre for ADR's expertise services can appoint or propose an expert, and an ICC tribunal may itself appoint an expert under Article 26(3) of the 2026 Rules.
Evidence and procedure
Delay and technical claims are document-heavy. Production schedules, class surveyor reports, sea trial records, modification requests and notices exchanged during construction usually decide the case, supported by expert evidence from naval architects, marine engineers and delay analysts. Parties should preserve yard and site records from the moment a dispute appears likely and agree early in the arbitration how expert evidence will be organised, including whether experts meet to narrow issues before the hearing. In ICC proceedings, the first case management conference is the natural place to settle these questions and set a realistic timetable.
Lower-value disputes, such as a single shortfall in performance criteria or a contested modification price, can be resolved quickly. Under the 2026 ICC Rules, the expedited procedure applies automatically where the amount in dispute does not exceed US$4 million and the arbitration agreement was concluded on or after 1 June 2026, and parties may agree to the Highly Expedited Arbitration track for very fast decisions.
Refund guarantees in shipbuilding arbitration
Buyers pay instalments before delivery, often amounting to a large share of the price. Their protection is a refund guarantee, issued by a bank on behalf of the yard, promising to repay instalments if the contract is cancelled or the yard fails. Refund guarantees are central to shipbuilding arbitration because their terms decide whether a buyer gets its money back immediately or only after the underlying dispute is resolved.
The leading English authority on construction is Rainy Sky SA v Kookmin Bank [2011] UKSC 50, decided by the UK Supreme Court on 2 November 2011. Six buyers had ordered vessels from a Korean yard, which entered a debt workout procedure. The bank argued that the advance payment bonds did not cover refunds triggered by the yard's insolvency. The Supreme Court unanimously disagreed: where a clause is capable of two meanings, the court should prefer the one more consistent with business common sense, and excluding the yard's insolvency, the very risk the bonds were meant to cover, made no commercial sense.
Refund guarantees commonly provide that if the yard disputes the buyer's cancellation and refers the matter to arbitration, the bank's obligation to pay is deferred until a final award or settlement. That turns the guarantee from an on-demand instrument into one that tracks the arbitration. Buyers should check carefully whether the guarantee is truly payable on demand and whether the yard's notice of arbitration suspends payment. Our note on letter of credit and demand guarantee disputes explains the independence principle that applies where the guarantee is payable on demand.
ICC versus LMAA for shipbuilding arbitration
The LMAA is an association of maritime arbitrators, not an administering institution. Arbitrations under the LMAA Terms, currently the LMAA Terms 2021, are run by the tribunal itself, seated in London, with small and intermediate claims procedures for lower-value disputes. The ICC International Court of Arbitration administers cases worldwide under the 2026 ICC Rules, with Secretariat supervision and scrutiny of draft awards.
| Feature | LMAA Terms 2021 | ICC Rules 2026 |
|---|---|---|
| Administration | Tribunal-run; no administering institution | ICC Court and Secretariat administer the case |
| Seat | London | Any seat chosen by the parties or fixed by the Court |
| Arbitrator pool | Specialist maritime arbitrators, often with commercial shipping backgrounds | Broad international pool, including construction and technical specialists |
| Fees | Arbitrators' fees agreed or fixed by the tribunal, often time-based | Ad valorem scale based on amount in dispute, plus administrative expenses |
| Fast-track options | Small Claims and Intermediate Claims Procedures | Expedited procedure (automatic up to US$4 million for new agreements); opt-in Highly Expedited Arbitration |
| Emergency relief | No institutional emergency arbitrator; court support available | Emergency arbitrator under Article 31 and Appendix IV |
| Multi-party and multi-contract | More limited; usually depends on consent or tribunal case management | Joinder, multi-contract claims and consolidation under Articles 8, 10 and 11 |
| Award review | No institutional scrutiny | Court scrutiny of draft awards under Article 37 |
LMAA arbitration is efficient, specialist and well understood in the shipping market, and for a standard bulk carrier or tanker contract between experienced parties it remains the natural choice.
ICC shipbuilding arbitration makes more sense where the project looks more like a construction or engineering contract than a ship purchase: drilling units, floating production units, naval and patrol vessels, and complex specialised tonnage. It also suits disputes involving state-owned yards or buyers from jurisdictions less familiar with London maritime practice, and series contracts where several hulls, subcontracts and guarantees need to be resolved together under Articles 10 and 11. Our page on ICC joinder and consolidation explains how those tools work.
Governing law, seat and enforcement
English law dominates shipbuilding contracts, and London is the usual seat. Under the Arbitration Act 2025, which came into force on 1 August 2025, the law of the arbitration agreement is the law of the seat unless the parties expressly choose otherwise; a choice of law for the main contract is not enough. Our note on the Arbitration Act 2025 changes explains the consequences. Domestic Chinese yards sometimes insist on arbitration in China, and parties should assess the implications for interim relief and enforcement before agreeing.
Enforcement is usually less of a concern than in other sectors, because the major shipbuilding nations, including China, South Korea and Japan, are parties to the New York Convention. The practical difficulty is more often the refund guarantor's position, the yard's financial health, and whether assets such as the vessel itself can be held while the dispute is resolved. Our shipping and commodities page covers arrest and security in more detail.
Two further risks deserve attention. Sanctions can affect payment routes, equipment supply and the identity of permitted end users, and may need to be addressed both in the contract and in the conduct of any arbitration. Yard insolvency, as in Rainy Sky, can trigger local restructuring regimes that try to stay claims; buyers should take advice early on whether those regimes affect an arbitration seated abroad and on the position of the refund guarantor.
Read the refund guarantee before you cancel. If payment is deferred once the yard starts arbitration, your cash will be tied up until the award, so the strength of your cancellation case, the speed of the chosen procedure and the guarantor's credit all matter. In shipbuilding arbitration, the guarantee wording often decides the commercial outcome more than the merits.
Drafting checklist for newbuilding contracts
- Choose LMAA or ICC deliberately, considering vessel type, counterparties, linked contracts and the need for emergency relief.
- Align the dispute clauses of the shipbuilding contract, refund guarantee, parent guarantee and equipment supply contracts.
- Define permissible delay notices and how force majeure counts towards cancellation thresholds.
- State clearly whether the refund guarantee is payable on demand or deferred pending arbitration, and cover the yard's insolvency expressly.
- Separate technical questions for the classification society or an expert from legal questions for the tribunal.
- Name the seat and, if a different law should govern the arbitration agreement, say so expressly.
How TRW & Co helps
We advise buyers, owners, financiers and yards on shipbuilding arbitration and related guarantee disputes. Our teams in London, Singapore, Dubai, Dhaka, Delhi and New York review newbuilding contracts and refund guarantees, advise on cancellation strategy and notices, and act for claimants and respondents in ICC arbitrations and coordinated court proceedings. We work with naval architects, marine engineers and quantum experts on technical and delay claims, and plan enforcement against yards, guarantors and assets across Asia and the Middle East. To discuss a contract or a dispute, please contact us.
Frequently asked questions
Why are most shipbuilding contracts arbitrated in London?
Most standard newbuilding forms, including the SAJ form and many yard forms, are governed by English law, and the London maritime arbitration community offers specialist arbitrators and well-understood procedures under the LMAA Terms. English courts are also supportive of arbitration. Parties remain free to choose ICC arbitration, another seat or another institution where the project calls for it.
What did Rainy Sky v Kookmin Bank decide?
In 2011 the UK Supreme Court held that advance payment bonds issued by Kookmin Bank covered the buyers' right to a refund when the Korean shipyard became insolvent. Where a clause has two possible meanings, the court should prefer the one more consistent with business common sense. Excluding the yard's insolvency would have defeated the commercial purpose of the bonds.
Is a refund guarantee always payable on demand?
No. Many refund guarantees provide that if the yard disputes the buyer's cancellation and commences arbitration, the bank need pay only after a final award or settlement. Others are payable on first demand. The wording must be checked before cancellation, because it determines whether the buyer recovers its instalments immediately or only at the end of the arbitration.
When should a buyer choose ICC rather than LMAA arbitration?
ICC arbitration is often preferable for offshore units, naval and specialised vessels, projects with many linked contracts, disputes with state-owned yards, and cases where emergency relief or institutional scrutiny of the award is valuable. LMAA arbitration remains efficient and appropriate for standard commercial vessels between experienced shipping parties.
Can technical disputes be decided by the classification society?
Many newbuilding contracts provide that disputes about construction or conformity with the specifications are referred to the classification society, whose decision is final on technical matters, while legal disputes go to arbitration. The scope of such a clause is often contested, so contracts should define clearly which questions belong to the classification society and which to the tribunal.
Sources
General information only, not legal advice. References to the ICC, the ICC Court and the ICC Rules describe their published rules and practice; TRW & Co is independent of the ICC.