Virtual Site Visits in Construction Arbitration

Virtual site visits construction tribunals use, from live walk-throughs to drone surveys, 3D scans and BIM models, can replace or supplement costly physical inspections. We explain the basis in the ICC and IBA Rules, what ICC construction guidance recommends, the evidential risks of each technology and a protocol that keeps remote inspections fair.

Drone survey and 3D model of a project prepared for virtual site visits construction arbitration

Key takeaways

  • Articles 23(2), 26(1) and 27(1) of the 2026 ICC Rules support remote inspections and recorded site evidence.
  • IBA Article 7 lets tribunals inspect sites and gives both parties the right to attend.
  • ICC construction guidance warns site visits are often dominated by the owner that controls the site.
  • BIM models show design intent; they prove as-built conditions only if updated against reality.
  • Preserve unedited footage, metadata and raw scan data, and share them in usable formats.
  • Agree operators, viewpoints, communications and recording in a procedural order before the visit.

Virtual site visits construction tribunals can rely on

Virtual site visits construction tribunals now use range from a live-streamed walk-through of a plant to drone surveys, 3D laser scans and navigable Building Information Modelling (BIM) models. They can show an arbitral tribunal what it would have seen on site without the cost and logistics of flying three arbitrators and two legal teams to a remote project. They can also show things a physical visit cannot, such as work that has since been covered up or demolished. But they are only as reliable as the protocol behind them: who controls the camera, what is captured, and how the material is authenticated.

Drone survey and 3D model of a project prepared for virtual site visits construction arbitration
Drone surveys, 3D scans and BIM models can bring a project into the hearing room, provided both parties can test how the images were produced.

For ICC users the answer is straightforward. The 2026 ICC Rules give the tribunal ample power to receive this kind of evidence, and ICC guidance on construction arbitration already anticipates it. The work lies in designing a fair process, ideally agreed early, that addresses access, equality of arms, authenticity and data security.

Article 26(1) of the 2026 ICC Rules requires the tribunal to establish the facts of the case "by all appropriate means". Article 27(1) allows the tribunal, after consulting the parties, to decide that any hearing will be conducted in person, in hybrid form or by videoconference or other electronic communication. Article 23(2) empowers it to adopt appropriate procedural measures, again after consultation. Together these provisions comfortably cover a remote inspection or the receipt of recorded site evidence.

Article 7 of the IBA Rules on the Taking of Evidence is more specific. It allows the tribunal, at a party's request or of its own motion, to inspect, or require inspection by a tribunal-appointed or party-appointed expert of, "any site, property, machinery or any other goods, samples, systems, processes or Documents". The tribunal must determine the timing and arrangements in consultation with the parties, and the parties and their representatives have the right to attend. That right to attend is the key design constraint for any remote format: both sides must be able to see what the tribunal sees, when it sees it.

The 2026 Note to Parties adds that where a tribunal decides on a hearing format without a party's agreement or over its objection, it is expected to give reasons, and that virtual hearings require consultation on data privacy, confidentiality and security. The same expectations apply sensibly to remote inspections.

What ICC construction guidance says about site visits

The ICC Commission report Construction Industry Arbitrations: Recommended Tools and Techniques for Effective Management (2019 update) remains the leading institutional guidance. It refers to the 2017 version of the Rules, but its practical recommendations carry over directly to virtual site visits construction cases now involve.

  • Access depends on the owner. The report notes that a site visit is generally only feasible with the permission and cooperation of the owner, and that what happens on a visit should be agreed rather than imposed.
  • Alternatives should be discussed early. Whether or not there is a visit, the tribunal should discuss what means are available to see or learn what would have been seen during the works, for example videos or presentations by the parties. Where material was produced for a party's own purposes, the parties must agree how it is used.
  • Videos and photographs help. Even footage created for promotional or historical purposes can be useful, particularly where it shows what can no longer be seen.
  • Timing. A visit is most efficient after the written evidence and well before the hearing.
  • No uncontrolled advocacy. A detailed protocol should cover who attends, who points out features, what communications are allowed, timing and route, and ensuring the tribunal sees everything relevant to both parties. The report warns that visits are often dominated by the owner because it controls the site, and that the tribunal must also see what the contractor wishes it to see.
  • Technology competence. The report recognises that BIM and scheduling systems make disputes more technical, that tribunals may need to operate the project's software, and that consents may be needed to let arbitrators use those applications.

Each of these points becomes sharper in a virtual format, where the person holding the camera or building the model effectively decides what the tribunal sees.

Technologies for virtual site visits construction disputes use

The main technologies for virtual site visits construction parties deploy have different strengths and different evidential risks.

TechniqueBest forEvidential cautions
Live-streamed walk-throughReal-time inspection of current conditions with questions from the tribunalCamera operator controls framing; connectivity on site; need a joint operator or dual cameras
Recorded video and 360-degree imageryShowing defects, access constraints and work sequencesEditing and selection; preserve unedited originals and metadata
Drone (UAV) surveys and photogrammetryLarge sites, roofs, pipelines, earthworks and progress over timeAviation permits and site safety; ground control and accuracy statements
3D laser scanning (point clouds)As-built geometry, tolerances, deformation and clashesSurvey method, registration error and who processed the data
BIM and federated modelsDesign intent, changes, clashes and sequencingModel version control; whether the model reflects as-built reality
Contemporaneous progress photographs and site recordsConditions during the works that can no longer be seenDating, completeness and gaps in the record

BIM evidence deserves particular care. A model shows design intent and recorded changes, but it is not proof of what was built unless it was updated against site reality. Where the project followed an information management framework such as the ISO 19650 series, the common data environment and its audit trail can help establish which version of the model existed when. Tribunals will want to know who controlled the model, when it was last updated and whether the version shown is the one the parties used during the project.

Drone and scanning evidence is often best presented through experts. Under IBA Article 7, inspection can be carried out by party-appointed or tribunal-appointed experts, and the ICC construction report recommends that once an arbitration has begun, tests by party experts should be carried out jointly and under the tribunal's direction, with similar constraints for site inspections. A joint scan or survey, with agreed methodology and shared raw data, avoids duelling datasets.

A protocol for virtual site visits construction cases need

A written protocol, adopted by procedural order after consulting the parties, is the single most important safeguard. It should address at least the following.

  1. Purpose and scope. The issues the visit is meant to inform, and the areas, elements or systems to be shown.
  2. Operators and route. Who operates cameras or drones, whether each side may nominate an operator, and an agreed route or list of viewpoints, including those requested by the party that does not control the site.
  3. Communications. Who may speak, whether representatives may point out features, and a prohibition on argument during the visit.
  4. Technology and recording. The platform, test runs, back-up arrangements, whether the visit is recorded and how the recording becomes part of the record.
  5. Authenticity. Preservation of unedited originals with metadata, statements from operators or surveyors, and the chain of custody of data files and models.
  6. Access to underlying data. Provision of point clouds, survey data and model files to the other side in usable formats, with any software licences or consents needed for the tribunal to view them.
  7. Safety, permits and confidentiality. Drone permissions, site safety rules, and measures for commercially sensitive or security-sensitive installations.

Data security deserves its own paragraph in the protocol. Scans, models and footage of energy, infrastructure or defence-related facilities can be commercially and security sensitive, and large files are often exchanged through cloud links. The 2026 Note to Parties expects the tribunal, the parties and those acting for them to apply appropriate technical and organisational security measures, which in virtual site visits construction cases should extend to surveyors, drone operators and model hosting providers. Agree where data will be stored, who may access it, and how it will be returned or destroyed at the end of the case.

Finally, plan how the material will be used at the hearing. Experts can walk the tribunal through a scan or model during their evidence, but the viewing software, file versions and screen-sharing arrangements must be tested in advance, and the tribunal should have its own access to the same files after the hearing for deliberation.

Practical point

Give the non-controlling party a right to request specific viewpoints in advance and to have its own representative or expert on site during any live visit. That one measure answers the ICC report's warning that site visits tend to be dominated by the owner, and makes the resulting record much harder to attack later.

The general mechanics of remote hearings, including platform choice, test runs and integrity measures, are set out in our guide to virtual and hybrid hearings and our virtual hearing protocol checklist. The ICC Commission's technology report also contains detailed guidance on organising virtual proceedings.

When a physical visit is still better

Virtual site visits construction parties propose are not always the right answer. A physical inspection may still be preferable where scale, sound, vibration, smell or the spatial relationship between elements matters, where the tribunal needs to witness tests being run, or where connectivity on site makes a live stream unreliable. The ICC construction report suggests that combining joint tests at a plant with a tribunal visit can be very helpful, provided operating conditions are representative.

Cost and proportionality also cut both ways. A remote visit avoids travel, but high-quality scanning, modelling and production can be expensive. In an expedited case under Appendix V, recorded footage and an agreed description of the site may be enough. In a major delay and defects claim, a combination of a short physical visit by one arbitrator, which the ICC report notes the parties may agree, with recorded scans for the full tribunal may give the best value. Our notes on delay and disruption claims and on construction and FIDIC disputes explain how site evidence fits into the wider case.

Illustration: in a hypothetical ICC arbitration over cracking in a desalination plant in the Gulf, the parties agree a joint 3D scan of the affected structures by an independent surveyor, a live-streamed walk-through with one operator nominated by each side, and full access to the raw point cloud for both experts. The tribunal receives the recording and scan data as part of the record and decides that no physical visit is required.

How TRW & Co helps

We act for employers, contractors, subcontractors and project companies in ICC construction and energy arbitrations. Our teams in Dhaka, London, Dubai, Singapore, New York and Delhi help clients decide whether a physical or virtual inspection best serves their case, negotiate site visit and data protocols, coordinate surveyors, drone operators and BIM specialists with the expert team, and prepare site evidence so that it withstands challenge on authenticity and completeness. Where the other side controls the site, we press for access and viewpoints that give the tribunal a balanced picture. To discuss site evidence in a construction dispute, contact us.

Frequently asked questions

Can an ICC tribunal order a virtual site visit?

Yes. Article 26(1) of the 2026 ICC Rules requires the tribunal to establish the facts by all appropriate means, Article 27(1) allows remote or hybrid hearings after consultation, and IBA Article 7 permits inspections. Practical access, however, usually depends on the party or owner controlling the site, so tribunals generally proceed by agreement and procedural order.

Are drone footage and 3D scans admissible evidence?

Generally yes. The tribunal decides admissibility and weight, for example under IBA Article 9.1. Weight depends on authenticity and method: who captured the data, with what equipment, how it was processed and whether unedited originals and metadata are available. Joint surveys with shared raw data are the most persuasive.

Does a BIM model prove what was actually built?

Not by itself. A BIM model records design intent and logged changes, but it reflects as-built reality only if it was updated against site conditions. Tribunals will ask who controlled the model, which version is being shown and how it compares with surveys, photographs and site records from the relevant period.

How can a contractor ensure fairness when the employer controls the site?

Seek a protocol giving each side the right to nominate viewpoints in advance, to have a representative or expert present during any live visit, and to receive unedited recordings and raw data. The ICC construction report expressly warns that site visits tend to be dominated by the owner and that the tribunal must also see what the contractor wishes it to see.

When is a physical site visit still preferable?

Where scale, noise, vibration or spatial relationships matter, where the tribunal needs to observe live tests, or where on-site connectivity is unreliable. A hybrid approach, for example a short visit by one arbitrator by agreement combined with recorded scans for the full tribunal, can balance cost and evidential value.

Sources

  1. ICC Commission Report: Construction Industry Arbitrations, Recommended Tools and Techniques for Effective Management (2019 update)
  2. ICC 2026 Arbitration Rules
  3. IBA Rules on the Taking of Evidence in International Arbitration (2020)
  4. ICC Note to Parties and Arbitral Tribunals on the Conduct of ICC Arbitration (1 June 2026)
  5. ICC Commission Report: Leveraging Technology for Fair, Effective and Efficient International Arbitration Proceedings

General information only, not legal advice. References to the ICC, the ICC Court and the ICC Rules describe their published rules and practice; TRW & Co is independent of the ICC.