FIDIC 2017 Clause 21: From DAAB to ICC Arbitration
The 2017 FIDIC books turn every construction dispute into a timed sequence of notices and referrals. This guide to the FIDIC Clause 21 DAAB to ICC pathway explains the deadlines that matter, how Notices of Dissatisfaction work, when the DAAB step can be skipped, and how to start an ICC arbitration under the 2026 Rules.

Key takeaways
- A Notice of Dissatisfaction within 28 days is the gateway to arbitration of a DAAB decision.
- After an NOD on a determination, the Dispute must reach the DAAB within 42 days or the NOD lapses.
- Arbitration may start from day 28 after the NOD, even without settlement talks.
- Failures to comply with DAAB decisions, and cases with no DAAB in place, can go straight to arbitration.
- FIDIC names ICC and three arbitrators but not the seat, so fix the seat in the contract.
FIDIC Clause 21 DAAB to ICC: The Short Answer
Under the 2017 FIDIC Red, Yellow and Silver Books, a construction dispute does not go straight to arbitration. It travels through a sequence: a claim and the Engineer's (or Employer's) determination, a Notice of Dissatisfaction, a referral to the Dispute Avoidance/Adjudication Board (DAAB), a DAAB decision, a second Notice of Dissatisfaction, a short amicable settlement window and, finally, international arbitration under the ICC Rules. Understanding the FIDIC Clause 21 DAAB to ICC sequence matters because each step carries a deadline, and missing one can make a determination or decision final and binding, closing the door to arbitration on that issue.

This guide follows the Red Book (Conditions of Contract for Construction, second edition 2017, as reprinted with amendments in 2022), with the Yellow and Silver Books working in a broadly similar way. It explains the Sub-Clause 21.4 to 21.6 mechanics, the exceptions that let a party go directly to arbitration, how courts and tribunals have treated skipped steps, and what changes once the ICC Secretariat registers the Request under the 2026 ICC Rules. Particular Conditions frequently amend Clause 21, so always read the contract actually signed, together with any side letters and agreed procedural amendments.
The FIDIC Clause 21 DAAB to ICC Sequence Step by Step
The 2017 suite moved the old Clause 20 dispute provisions into a new Clause 21 and separated claims (Clause 20) from disputes (Clause 21). A "Dispute" in the 2017 sense normally crystallises only after a claim has been made, the Engineer has determined it under Sub-Clause 3.7, and a party has given a Notice of Dissatisfaction (NOD) with that determination. The 2022 amendments, published by FIDIC as Issue No. 3 and effective from 1 January 2023, also deem certain matters to be Disputes, such as non-payment that triggers termination rights, unpaid financing charges and contested termination notices, which may be referred to the DAAB without an NOD.
| Step | Red Book provision | Typical time limit | Consequence of missing it |
|---|---|---|---|
| Notice of Claim | Sub-Clause 20.2.1 | 28 days after the claiming party became aware, or should have become aware, of the event | Claim may be time-barred, subject to Sub-Clause 20.2.5 |
| Fully detailed Claim | Sub-Clause 20.2.4 | 84 days, unless a longer period is agreed | Notice of Claim may lapse if the legal basis is not stated in time |
| Engineer's determination | Sub-Clause 3.7 | 42 days for the determination after the fully detailed Claim | Deemed rejection, which then becomes a Dispute |
| NOD on the determination | Sub-Clause 3.7.5 | 28 days after receiving the determination | Determination becomes final and binding |
| Referral to the DAAB | Sub-Clause 21.4.1 | 42 days after giving or receiving the NOD | NOD treated as lapsed |
| DAAB decision | Sub-Clause 21.4.3 | 84 days after referral, or as agreed | Either party may give an NOD as if a decision had been given |
| NOD on the DAAB decision | Sub-Clause 21.4.4 | 28 days after receiving the decision | Decision becomes final and binding |
| Amicable settlement | Sub-Clause 21.5 | Arbitration may start on or after day 28 after the NOD | None, but the window must be respected |
| ICC arbitration | Sub-Clause 21.6 | Check the contract for any outer limit on commencing arbitration | Final resolution of the Dispute |
These periods reflect the published General Conditions as summarised in training material from the Asian Development Bank and FIDIC's own 2022 amendments list. Employers, lenders and funders often vary them, and some Particular Conditions add further outer limits for commencing arbitration. Treat the table as a starting point, not a substitute for the signed contract. Where the Employer is a state entity, local procurement rules or financing conditions may also add approval steps before a settlement can be agreed, which in practice lengthens the amicable settlement stage and should be built into the timetable from the outset.
Notices of Dissatisfaction: The Gatekeeper
The NOD is the single most important document in the FIDIC Clause 21 DAAB to ICC journey. Sub-Clause 21.4.4 provides, in substance, that neither party may commence arbitration of a Dispute unless an NOD has been given in respect of the DAAB's decision, subject to the exceptions discussed below. If no NOD is given within 28 days, the decision becomes final and binding on both parties. A tribunal later asked to revisit that issue will usually have no jurisdiction to do so.
Because so much turns on it, an NOD should be drafted with care. It should be expressly labelled as a Notice of Dissatisfaction, refer to the relevant Sub-Clause, identify the determination or decision, and set out which parts the party is dissatisfied with and why. A partial NOD is permitted: Sub-Clause 21.4.4 allows a party to object to only part of a decision, in which case the remainder becomes final and binding. That is useful tactically, but it requires precision. Vague wording that challenges "the decision" generally may be read as covering everything, or may be attacked as ambiguous.
Notices must also comply with the general notice provisions in Sub-Clause 1.3: in writing, delivered by the agreed means and to the agreed address, and identified as a Notice. Electronic transmission systems agreed in the Particular Conditions should be used exactly as specified. A well-reasoned NOD sent to the wrong email address, or one that reads like ordinary correspondence, invites a jurisdictional fight months later.
Diarise both the 28-day NOD deadline and the 42-day DAAB referral deadline the moment a determination arrives. Under Sub-Clause 21.4.1, a party that gives an NOD on the Engineer's determination but fails to refer the Dispute to the DAAB within 42 days risks the NOD lapsing and the determination becoming final. Many disputes are lost on that second clock, not the first.
Amicable Settlement and the Referral to ICC Arbitration
Once an NOD has been given on the DAAB's decision, Sub-Clause 21.5 requires the parties to attempt to settle the Dispute amicably before arbitration begins. Unless otherwise agreed, arbitration may be commenced on or after the 28th day after the NOD was given, even if no attempt at amicable settlement has been made. The 2017 edition shortened the equivalent 56-day period in the 1999 books. In practice, the window is often used for a without-prejudice meeting at senior management level, or for an agreed mediation under the ICC Mediation Rules.
Sub-Clause 21.6 then provides that, unless settled amicably, the Dispute is finally settled by international arbitration under the ICC Rules of Arbitration, by three arbitrators, in the contract's ruling language, unless the parties agree otherwise. The arbitrators have full power to open up, review and revise any certificate, determination, instruction, opinion or valuation of the Engineer and any decision of the DAAB, except one that has become final and binding. Neither party is limited in the arbitration to the evidence or arguments it put to the DAAB, and the DAAB's decision is admissible in evidence.
The clause names the institution but not the seat. Parties who leave the seat blank leave it to be fixed by the ICC Court under Article 19 of the 2026 Rules, which gives up an important element of control over the supervisory courts and set-aside grounds. Our guide to choosing seat, governing law and language explains why the seat should be written into the Contract Data.
When the FIDIC Clause 21 DAAB to ICC Steps Can Be Bypassed
Three routes allow a party to go to arbitration without completing every step of the FIDIC Clause 21 DAAB to ICC ladder. First, Sub-Clause 21.7 allows a failure to comply with a DAAB decision, whether binding or final and binding, to be referred directly to arbitration, with Sub-Clauses 21.4 and 21.5 not applying to that failure. The tribunal has power, by summary or other expedited procedure, to order enforcement of the decision by an interim or provisional measure or an award. Our companion insight on enforcing DAAB decisions through arbitration covers that route in detail.
Second, Sub-Clause 21.8 applies where there is no DAAB in place, whether because the appointment has expired or a party has frustrated the appointment process. The Dispute may then be referred directly to arbitration. The 2017 edition also tightened the default appointment mechanism in Sub-Clause 21.2, and the 2022 amendments make the President of FIDIC, or a person appointed by the President, the appointing official who can also fix the members' fees if they cannot be agreed.
Third, the DAAB step itself may be excused by the general law. The Swiss Federal Supreme Court, in decision 4A_124/2014 of 7 July 2014 concerning an ICC arbitration seated in Geneva under the 1999 FIDIC conditions, accepted that the dispute board procedure is in principle a mandatory precondition. It nonetheless upheld the tribunal's jurisdiction where the claimant had tried for well over a year to get an ad hoc board constituted.
In England, the Technology and Construction Court in Peterborough City Council v Enterprise Managed Services [2014] EWHC 3193 (TCC) stayed court proceedings so that the parties would follow the dispute adjudication machinery in a 1999 FIDIC EPC/Turnkey contract. Courts and tribunals, in short, expect the FIDIC Clause 21 DAAB to ICC sequence to be followed unless there is a genuine reason why it cannot be.
Running the ICC Arbitration Under the 2026 Rules
For arbitrations commenced on or after 1 June 2026, the 2026 ICC Rules apply unless the parties agreed otherwise. Several features suit construction disputes that arrive via Clause 21. Terms of Reference are now optional, but the initial case management conference within 30 days of the tribunal receiving the file remains mandatory under Article 24. Article 30 allows early determination of claims or defences that are manifestly without merit or manifestly outside jurisdiction, a useful tool where one party argues that an issue was never the subject of a valid NOD. Article 29 permits interim measures in the form of an order or an award.
The Request for Arbitration should map the contractual history: each claim, determination, NOD, DAAB referral and decision, with dates and documents. That allows the Secretariat, the Court and later the tribunal to see at a glance that the conditions precedent were satisfied. Respondents should consider whether any part of the claim was never referred to the DAAB, or became final and binding, and raise the objection in the Answer rather than later, since a party that participates without objecting risks being treated as having waived the point.
Amounts matter too. Under the 2026 Rules, the expedited procedure applies automatically to disputes up to US$4 million where the arbitration agreement was concluded on or after 1 June 2026, with lower thresholds for older agreements. Because FIDIC Sub-Clause 21.6 calls for three arbitrators, parties should consider whether that choice is compatible with the expedited procedure; the ICC Court may appoint a sole arbitrator notwithstanding a contrary provision in the arbitration agreement. The ICC Commission's Report on Construction Industry Arbitrations remains a practical guide to managing schedules, experts and site visits in these cases.
Checklist for Moving From FIDIC Clause 21 DAAB to ICC Arbitration
- Map every claim. For each head of claim, record the Notice of Claim, fully detailed Claim, determination, NOD and DAAB decision, with dates.
- Check finality. Identify any determination or decision that became final and binding because no timely NOD was given.
- Read the Particular Conditions. Confirm amended periods, the seat, the language, any outer limit for commencing arbitration and whether the 2022 amendments were incorporated.
- Confirm the DAAB position. If no DAAB is in place, gather evidence of the appointment attempts in case Sub-Clause 21.8 is disputed.
- Separate non-compliance claims. A failure to pay a DAAB decision can go directly to arbitration under Sub-Clause 21.7 and may justify an early interim award.
- Plan the expert evidence. Delay and quantum experts should be instructed well before the Request is filed.
A disciplined record of this kind also helps if the case later reaches court. Tribunals faced with conditions-precedent objections typically ask whether the specific dispute now pleaded was the dispute referred to the DAAB; a clear map answers that question before it is asked. For a wider view of pre-arbitral steps, see our multi-tier clause compliance guide and the construction and FIDIC disputes overview.
How TRW & Co Helps
We advise employers, contractors and subcontractors on the full FIDIC Clause 21 DAAB to ICC pathway, from the first Notice of Claim to the final award. Our teams in Dhaka, London, Dubai, New York, Singapore and Delhi review Particular Conditions, prepare and audit Notices of Dissatisfaction, present and respond to DAAB referrals, and assess whether each dispute is ready for arbitration. When a case moves to the ICC, we prepare Requests and Answers that map the contractual history, coordinate delay and quantum experts, and run applications for interim relief or early determination where they fit the strategy.
We act for claimants and respondents and give candid views on risk, cost and timing. To discuss a live project or a contract under negotiation, contact our team.
Frequently asked questions
Can a party start ICC arbitration without going to the DAAB under FIDIC 2017?
Normally no. Sub-Clause 21.4.4 makes an NOD on a DAAB decision a precondition to arbitration. The main exceptions are Sub-Clause 21.7, which lets a party refer a failure to comply with a DAAB decision directly to arbitration, and Sub-Clause 21.8, which applies when no DAAB is in place. Courts have also excused the step where one party frustrated the appointment of the board.
What happens if no Notice of Dissatisfaction is given?
If neither party gives an NOD within 28 days of receiving the DAAB decision, the decision becomes final and binding on both parties. The arbitral tribunal cannot later open it up, review or revise it, although a party can still bring an arbitration to enforce it if the other side fails to comply.
Does FIDIC Clause 21 specify the seat of arbitration?
No. Sub-Clause 21.6 provides for ICC arbitration with three arbitrators in the ruling language of the contract, but leaves the seat to be agreed. If the parties do not agree one, the ICC Court will fix the place of arbitration under Article 19 of the 2026 Rules. Parties should state the seat in the Contract Data or Particular Conditions.
Are DAAB decisions binding while the arbitration is pending?
Yes. Under Sub-Clause 21.4.3, a DAAB decision is binding on both parties, who must promptly comply with it whether or not an NOD is given. It remains binding unless and until it is revised in an amicable settlement or an arbitral award. Non-compliance can itself be referred to arbitration under Sub-Clause 21.7.
Do the 2026 ICC Rules apply to FIDIC contracts signed earlier?
Generally yes, if the arbitration is commenced on or after 1 June 2026, because Article 1(2) applies the Rules in force when the arbitration starts unless the parties agreed otherwise. However, the expedited procedure threshold depends on when the arbitration agreement was concluded, so older contracts may carry a lower threshold.
Sources
- FIDIC, Conditions of Contract for Construction (Second Edition 2017): amendments list, Issue No. 3
- ICC 2026 Arbitration Rules (official page and text)
- ICC Arbitration and ADR Commission Report on Construction Industry Arbitrations (2019)
- Peterborough City Council v Enterprise Managed Services Ltd [2014] EWHC 3193 (TCC)
- Asian Development Bank, Key changes in the 2017 FIDIC Red Book (2023 training material)
General information only, not legal advice. References to the ICC, the ICC Court and the ICC Rules describe their published rules and practice; TRW & Co is independent of the ICC.