Disputes on JICA-Funded Projects in Bangladesh
Japanese funded projects Bangladesh disputes follow JICA's standard bidding documents: FIDIC MDB conditions, a standing Dispute Board and a two-track arbitration clause for foreign and domestic contractors. This insight explains the procurement framework, Dispute Board timetable, ICC default and the role of Bangladeshi courts in guarantee and enforcement disputes.

Key takeaways
- JICA's Works SBD uses the FIDIC MDB Harmonised Edition (2010) with JICA Particular Conditions.
- JICA basically requires a standing Dispute Board for all contracts, whatever their size.
- A notice of dissatisfaction is due within 28 days of the board's decision, or the decision becomes final.
- Foreign contractors arbitrate before the named institution, JCAA if chosen, or the ICC by default.
- Domestic contractors arbitrate under Bangladeshi law, which means the Arbitration Act 2001.
Japanese funded projects Bangladesh disputes: the short answer
Japanese funded projects Bangladesh disputes are governed first by the contract conditions that JICA's standard bidding documents require: FIDIC-based conditions with a standing Dispute Board, a 28-day notice of dissatisfaction and, for foreign contractors, international arbitration administered by the institution named in the Contract Data, with ICC arbitration as the default. Domestic contractors arbitrate under Bangladeshi law. Knowing which category a contractor falls into, and keeping to the Dispute Board timetable, decides most of what follows.

Japan is one of Bangladesh's largest development partners. In August 2020 alone, JICA signed ODA loan agreements with Bangladesh for projects including the Jamuna Railway Bridge, the expansion of Hazrat Shahjalal International Airport and several phases of the Dhaka Mass Rapid Transit system. Projects of this scale involve Japanese, Bangladeshi and third-country contractors, consultants and suppliers, and disputes over delay, variations and payment are a normal part of their life.
This insight explains the procurement framework, the contract conditions, the Dispute Board process and the arbitration options. It is general information, not legal advice.
The JICA procurement framework
Under a Japanese ODA loan, the borrower, typically a Bangladeshi ministry or implementing agency, runs the procurement and signs the contract. JICA finances the project and reviews key procurement steps, but it is not a party to the works contract. JICA's standard documents make the point directly: no party other than the borrower derives any rights from the loan agreement or has any claim to the loan proceeds.
The rules are set out in documents published on JICA's guidelines page, including the Handbook for Procurement under Japanese ODA Loans (October 2023), the Guide for Procurement and Evaluation Procedures (November 2021) and the Standard Bidding Documents. The Standard Bidding Document for Procurement of Works (Version 2.4, with revisions in 2023) uses the FIDIC Conditions of Contract for Construction, MDB Harmonised Edition (June 2010), with JICA's Particular Conditions. The Notes for Users require the standard General Conditions to be used without modification, and Particular Conditions may not materially alter them without JICA's agreement.
The framework also carries integrity rules. JICA may reject an award or declare a firm ineligible for corrupt or fraudulent practices, and it recognises debarment decisions of the multilateral development banks under specified conditions. Allegations of this kind can surface in a commercial dispute and should be handled with care.
Bid stage: Contract Data and one-sided terms
Many Japanese funded projects Bangladesh disputes can be traced back to choices made, or not made, at bid stage. The Contract Data fixes the arbitration institution, the number of board members, the appointing entity if the parties cannot agree and the price adjustment data. Bidders who do not read these entries carefully inherit defaults they did not intend.
JICA has also published a Check List for One-sided Contracts (March 2011), which it uses to review whether employers have altered the standard conditions in ways that shift risk unfairly to contractors. Typical concerns include deleting the contractor's entitlement to time or money for employer risks, removing the Dispute Board or narrowing the arbitration clause. A contractor that finds such changes in a tender can raise them through the clarification process, and the record of having done so can matter if a dispute later turns on what the parties intended.
Joint venture structure deserves attention at the same time. Because JICA's arbitration clause follows the nationality of the lead partner, a change in leadership or in the corporate identity of the lead partner can change the forum. That consequence should be understood before the joint venture agreement is signed.
How the Dispute Board works
JICA favours standing Dispute Boards. Its Dispute Board Manual (November 2019) states that JICA basically requires the employer to establish a standing board for all contracts regardless of size, and strongly recommends against ad hoc boards formed only after a dispute arises. Board costs are eligible for financing under the loan. Under the JICA Particular Conditions, the employer pays the regular costs of the board and half of any non-regular costs arising from referrals, while the contractor pays the other half of the non-regular costs.
| Step | JICA SBD (Works), Clause 20 | Practical note |
|---|---|---|
| Board decision | Within 84 days of the referral, or another period proposed by the board and approved by both parties | Decision is binding and must be given effect promptly |
| Notice of dissatisfaction | Within 28 days of receiving the decision, or of the 84-day period expiring without one | Without a valid notice, arbitration is generally unavailable |
| Decision becomes final | If no notice of dissatisfaction is given within 28 days | Calendar control is part of the merits |
| Amicable settlement | Parties attempt settlement; arbitration may begin after the 56th day from the notice | Settlement talks do not suspend other time limits |
| Arbitration | Sub-Clause 20.6, as amended by JICA's Particular Conditions | Foreign or domestic contractor route |
In Japanese funded projects Bangladesh disputes, the board is often most valuable before any formal referral. Regular site visits and informal opinions can defuse disagreements about ground conditions, design approvals or programme revisions before they harden. Our page on ICC Dispute Boards explains how the ICC can support board appointments and procedure.
The arbitration clause in Japanese funded projects Bangladesh disputes
JICA's Particular Conditions replace the MDB arbitration sub-clause with a two-track rule. If the contractor is foreign, or the lead partner of a joint venture is foreign, disputes go to international arbitration administered by the institution designated in the Contract Data under its rules; or, if so specified, to the Japan Commercial Arbitration Association under its rules; and if neither is specified, to arbitration administered by the ICC under the ICC Rules of Arbitration. The place of arbitration is a neutral location determined under the applicable rules, and the language is the contract's language for communications.
If the contractor is domestic, or the lead partner of a joint venture is domestic, arbitration is conducted in accordance with the laws of the country, which in Bangladesh means the Arbitration Act 2001. Classification can be contested, for example where a Bangladeshi-incorporated subsidiary of a foreign group leads a joint venture, and JICA's own manual acknowledges that the terms are not defined. Contractors should resolve the question at bid stage, not after a dispute arises.
Where ICC arbitration applies, the 2026 ICC Rules govern arbitrations commenced on or after 1 June 2026, unless the parties agreed otherwise. The tools most relevant to Japanese funded projects Bangladesh disputes include early determination of manifestly unmeritorious claims under Article 30, the emergency arbitrator under Article 31 and Appendix IV, and joinder and multi-contract claims under Articles 8 to 10.
Check the Contract Data before you sign. Whether it names an institution, whether it chooses JCAA or leaves the ICC default in place, and how the neutral place of arbitration will be fixed all affect cost, timing and enforcement. A blank entry is not neutral: it activates the default.
Common issues on Japanese-financed projects
Large transport, power and urban projects generate familiar claims. Land acquisition and utility relocation delay access to site; design reviews take longer than programmed; variations are instructed without the formal steps the contract requires; and price adjustment formulas fail to keep pace with currency movements and commodity prices. Subcontractors and suppliers then claim against the main contractor, often under subcontracts with different dispute clauses.
Japanese funded projects Bangladesh disputes also raise questions about approvals within the employer's organisation. Extensions of time and variations may require sign-off at several levels of government, and payment of an award or settlement by a state agency requires budgetary authority. Recording each approval step, and the dates on which requests were made, protects both sides when the history is reconstructed years later. For the national public works conditions that run alongside FIDIC, see our insight on construction disputes in Bangladesh under FIDIC.
Claims, notices and records
Under the MDB conditions used by JICA, the contractor must give notice of a claim within 28 days after it became aware, or should have become aware, of the event or circumstance, and failure to do so can extinguish the entitlement to additional time or payment. A fully detailed claim must then follow, by default within 42 days of that awareness, or within another period proposed by the contractor and approved by the Engineer.
Where the event has a continuing effect, interim claims are submitted at monthly intervals and a final claim follows once the effects end. These requirements are applied strictly by many tribunals, so notice discipline matters as much as the underlying merits.
Records do the rest. Site diaries, programme updates, correspondence with the Engineer and minutes of progress meetings are the evidence that decides delay and disruption claims. On projects with Japanese, Bangladeshi and third-country staff, records should be kept in the contract language, with translations of key documents prepared as they are created rather than years later for the arbitration.
Illustration: a joint venture led by a foreign contractor builds a viaduct on a JICA-financed rail project. Late handover of land delays the works, and the Engineer rejects most of the extension of time claimed. The joint venture refers the dispute to the standing board, receives a favourable decision and, when the employer serves a notice of dissatisfaction, the dispute proceeds to ICC arbitration under the default in the Contract Data. The scenario is hypothetical.
Bangladeshi courts, guarantees and enforcement
The seat determines what Bangladeshi courts can do during the arbitration. With a Dhaka seat, section 7A of the 2001 Act allows interim measures, including applications to restrain a call on a performance security. With a foreign seat, a larger bench of the High Court Division held in 2021 that section 7A relief is available only once enforcement of the foreign award is sought, so urgent relief must come from an emergency arbitrator, the tribunal or the courts of the seat.
A foreign award is enforced in Bangladesh through the Court of the District Judge in Dhaka under sections 45 and 46, on New York Convention grounds. Japan and Bangladesh are both Convention states, and Bangladesh's bilateral investment treaty with Japan may offer additional protection for qualifying investments. Our page on Dhaka as an arbitral seat explains the court regime, and our insight on World Bank and ADB funded projects compares the other development-partner frameworks.
How TRW & Co helps
We advise Japanese, Bangladeshi and international contractors, employers, consultants and subcontractors on Japanese funded projects Bangladesh disputes. Our teams in Dhaka, Singapore, London and Dubai review bid-stage Contract Data and dispute clauses, prepare claims and notices, support Dispute Board referrals and conduct ICC, JCAA-administered and Dhaka-seated arbitrations, coordinating with technical experts on delay and quantum. We act for claimants and respondents and focus on preserving rights early, because most of these disputes are decided by what happens in the first months. To discuss a project, contact our team.
Frequently asked questions
Is JICA a party to the construction contract?
No. The Bangladeshi borrower or implementing agency signs the contract with the contractor. JICA finances the project and reviews procurement, and its standard documents state that no party other than the borrower derives rights from the loan agreement or has a claim to the loan proceeds. Claims are therefore made against the employer, not against JICA.
Which arbitration rules apply if the Contract Data is blank?
For a foreign contractor, or a joint venture led by a foreign partner, JICA's Particular Conditions provide that where neither an institution nor rules are specified, the arbitration is administered by the ICC under the ICC Rules of Arbitration. For a domestic contractor, arbitration proceeds under Bangladeshi law, namely the Arbitration Act 2001.
Who pays for the Dispute Board?
Under JICA's Particular Conditions, the employer pays the regular costs, such as retainers and scheduled site visits, and half of the non-regular costs arising from dispute referrals; the contractor pays the other half of the non-regular costs. JICA treats board costs as eligible for financing under the loan, which removes a common excuse for not appointing a board.
What if no Dispute Board was appointed?
The MDB conditions used in JICA's Works SBD contain provisions for appointment by an appointing entity and for referral to arbitration where no board is in place. A contractor should press for appointment in writing and keep records of the request, so that a later tribunal can see the procedure was not frustrated by the contractor.
Can Bangladeshi courts stop a performance security call?
With a Dhaka seat, section 7A of the Arbitration Act 2001 allows the court to grant interim measures, and courts have sometimes restrained calls. With a foreign seat, section 7A relief is generally unavailable before enforcement, so the emergency arbitrator, the tribunal or the courts of the seat are the practical options.
Sources
- JICA: Guidelines, Standard Bidding Documents and Evaluation Guides and Manuals
- JICA Standard Bidding Document for Procurement of Works (Version 2.4, revised 2023)
- JICA Dispute Board Manual (November 2019)
- JICA press release: ODA loan agreements with Bangladesh (13 August 2020)
- Arbitration Act 2001 (Act No. 1 of 2001), Laws of Bangladesh
- ICC 2026 Arbitration Rules
General information only, not legal advice. References to the ICC, the ICC Court and the ICC Rules describe their published rules and practice; TRW & Co is independent of the ICC.