GCC Construction Disputes
GCC construction disputes are shaped as much by mandatory local law as by the FIDIC forms parties sign. We explain the usual Gulf amendments to FIDIC, decennial liability and judicial control of agreed damages, approvals needed to arbitrate with public employers, and how to run an ICC claim that survives enforcement.

Key takeaways
- Most Gulf projects use heavily amended FIDIC forms; dispute boards and financing charges are often deleted.
- Civil codes impose mandatory decennial liability and allow agreed damages to be adjusted.
- The UAE's new Civil Transactions Law entered into force on 1 June 2026.
- Saudi and Qatari public bodies need high-level approval before agreeing to arbitrate.
- Separate quantification of principal, financing costs and interest protects awards at enforcement.
GCC Construction Disputes in Brief
GCC construction disputes are usually fought under FIDIC-based contracts that have been heavily amended by employers, and decided under civil codes that override parts of the bargain. The standard form supplies the machinery for notices, variations, extensions of time and dispute boards; local law supplies mandatory rules on decennial liability, judicial control of agreed damages, good faith and, in Saudi Arabia, the Sharia prohibition of interest. Where the employer is a government body, statutory approval for arbitration may also be needed. ICC arbitration remains a common final tier, alongside regional institutions.

This note explains the typical FIDIC amendments seen in the Gulf, the local law rules that most often change outcomes, the approvals and seat choices that affect arbitration, and how to prepare a claim that survives scrutiny and enforcement. It focuses on the UAE, Saudi Arabia and Qatar, with general comments on Kuwait, Bahrain and Oman. It is general information, not legal advice, and project documents and governing law always need individual review.
How FIDIC Is Amended in the Gulf
The FIDIC Red, Yellow and Silver Books are the reference point for most major projects in the region, in both the 1999 and 2017 editions. Some public employers still use forms derived from older FIDIC editions or their own standard conditions. In practice, few projects use the general conditions unamended. Particular conditions commonly change the risk allocation in the following ways.
- Dispute boards removed or diluted. The Dispute Avoidance/Adjudication Board in Clause 21 of the 2017 forms (Clause 20 in 1999) is often deleted, replaced by engineer's or employer's determinations, or made non-binding, sending disputes straight to negotiation and arbitration. See our guide to ICC dispute boards.
- Tighter notices and time bars. The 28-day notice for claims in Sub-Clause 20.2 of the 2017 forms is sometimes shortened, or supplemented by additional conditions precedent.
- Ground and design risk shifted. Unforeseeable physical conditions, errors in employer's requirements and site data warranties are frequently transferred to the contractor.
- Financing charges removed. Delayed-payment financing charges under Sub-Clause 14.8 are often deleted or capped, and in Saudi Arabia they may conflict with the prohibition of interest.
- Different arbitration tier. ICC arbitration in Sub-Clause 21.6 may be replaced by a local institution, a local seat or, for some public employers, the local courts.
FIDIC's own Golden Principles caution against particular conditions that change the balance of risk or the fundamental dispute mechanism. They are not binding, but tribunals and experts are familiar with them, and they can help a contractor argue that an onerous amendment should be read narrowly. Our construction and FIDIC disputes page discusses the standard machinery in more detail.
Local Law Rules That Change GCC Construction Disputes
Most GCC civil codes belong to the civil law tradition and contain construction rules within the contract of muqawala (the contract for work). Several of those rules are mandatory, so the parties cannot contract out of them whatever the FIDIC conditions say. The table summarises the points that most often matter in GCC construction disputes.
| Issue | UAE | Saudi Arabia | Qatar |
|---|---|---|---|
| Civil code | Civil Transactions Law issued by Federal Decree-Law No. 25 of 2025, in force 1 June 2026, replacing Federal Law No. 5 of 1985 | Civil Transactions Law (Royal Decree M/191), in force December 2023 | Civil Code (Law No. 22 of 2004) |
| Decennial liability | Contractor and architect jointly liable for ten years for collapse and defects threatening stability (Article 880 of the 1985 Code) | Check the Civil Transactions Law rules on the contract for work and any project-specific regulation | Mandatory decennial regime in the Civil Code |
| Agreed damages | Courts and tribunals may adjust agreed compensation to equal the loss (Article 390 of the 1985 Code); reports indicate the 2025 law keeps review of excessive penalties | Now governed by the codified rules on compensation; check the text against the contract | Judicial control of agreed compensation in some form; check the Civil Code |
| Interest and financing charges | Commercial interest permitted under the Commercial Transactions Law, with limits | Contractual and statutory interest generally unenforceable as riba | Interest in commercial matters generally less problematic than in Saudi Arabia |
| Arbitration with public bodies | Depends on the emirate and entity; check authority to sign | Approval of the President of the Council of Ministers unless a special law permits (Arbitration Law, Article 10(2)) | Prime Minister's approval for administrative contracts (Law No. 2 of 2017, Article 2(2)) |
UAE: a new civil code from June 2026
The UAE's 1985 Civil Code governed construction contracts for four decades. Its decennial liability regime in Article 880 makes the contractor and architect jointly liable for ten years for total or partial collapse of buildings or installations and for defects threatening their stability, and Article 390 allows a judge or tribunal to vary agreed compensation so that it equals the loss suffered. The new Civil Transactions Law issued by Federal Decree-Law No. 25 of 2025 entered into force on 1 June 2026. Published reports on the new law indicate that courts retain power to review agreed penalties that are excessive or do not reflect the actual loss. For contracts concluded before that date, parties should check the transitional provisions and assume that disputes may involve both codes.
Saudi Arabia: codified civil law and Sharia
Saudi Arabia's Civil Transactions Law, which came into force in December 2023, codified rules that were previously applied by the courts from Sharia principles. It brings greater predictability to questions of contract formation, performance, compensation and the contract for work. Sharia continues to frame public policy, so claims for interest, financing charges or compensation that is in substance interest remain at risk. Claims for proven actual loss caused by delay are on firmer ground.
Qatar, Kuwait, Bahrain and Oman
The civil codes of Qatar, Kuwait, Bahrain and Oman share much of the same civil law structure, with decennial liability for structural defects and judicial control of penalty clauses in some form. Details differ, including limitation periods and the extent to which agreed damages can be adjusted, so each project's governing law must be checked rather than assumed.
Notices, Time Bars and Good Faith
Time bars are among the most contested issues in GCC construction disputes. FIDIC's 2017 forms make the 28-day notice in Sub-Clause 20.2 a condition of entitlement, subject to the engineer's power to excuse late notice in some circumstances. Under common law, a clearly drafted time bar is usually enforced. Under Gulf civil codes the position is less settled. Tribunals generally start from the contract, but parties invoke doctrines of good faith in performance and abuse of right, and argue that strict forfeiture is disproportionate where the employer had actual knowledge of the event and suffered no prejudice.
The safe course is to comply. Contractors should treat every notice period as strict, give a short notice early and follow it with detailed particulars, and keep contemporaneous records. Employers relying on a time bar should be ready to show that they did not waive it by continuing to engage with the claim. Our note on time-bar notices in construction arbitration sets out the drafting and evidence points.
On Gulf projects, notices are often sent by email, letter and project management platforms in English and Arabic. Agree in the contract which channel is the formal one and which language governs, and keep a log. Many GCC construction disputes turn less on law than on whether the contractor can prove that a notice reached the right person on time.
Arbitrating GCC Construction Disputes Under ICC Rules
ICC arbitration is attractive for GCC construction disputes because of the ICC Court's scrutiny of awards, its experience with large multi-party construction cases and the neutrality of the institution. The ICC has a case management office in Abu Dhabi. Regional institutions such as the Dubai International Arbitration Centre, the Saudi Center for Commercial Arbitration and arbitrateAD in Abu Dhabi are also widely used, and some employers insist on them.
Capacity and approvals
Arbitration with public employers needs particular care. Article 10(2) of the Saudi Arbitration Law provides that government bodies may not agree to arbitrate without the approval of the President of the Council of Ministers unless a special law allows it. Article 2(2) of Qatar's Law No. 2 of 2017 requires the Prime Minister's approval, or that of his delegate, for arbitration of administrative contract disputes. A clause signed without the required approval is vulnerable to a jurisdictional objection years later, so contractors should ask for evidence of approval at tender stage.
Seat, arbitrators and language
The seat determines the supervising court and the annulment regime. Options include onshore Dubai or Abu Dhabi, the DIFC or ADGM, Riyadh, Doha or a neutral seat such as London, Paris or Singapore. In a Saudi-seated arbitration, Article 14 of the Saudi Arbitration Law requires a sole arbitrator, or the chair of a three-member tribunal, to hold at least a university degree in Sharia or law. Arabic is often the language of the contract and the local court, so translation costs and bilingual tribunals deserve early thought. See our page on Riyadh as a seat.
Dispute boards and the ICC route
Where the DAAB survives, a contractor holding a binding but unpaid board decision can refer the failure to comply directly to arbitration under the 2017 forms. Our note on enforcing DAAB decisions through ICC arbitration explains the procedure. Expedited procedures under the 2026 ICC Rules apply automatically to lower-value disputes depending on when the arbitration agreement was concluded, which can suit discrete claims such as unpaid interim certificates.
Quantum, Delay and Evidence
Large GCC construction disputes are typically won on records. Delay claims require an as-planned programme accepted under the contract, regular updates and a method of analysis that the tribunal can test. Disruption and acceleration claims need resource and productivity data. Because many projects involve mega-scale public developments with multiple contractors, concurrent delay and interface issues are common, and tribunals expect experts to address them directly.
- Experts. Appoint delay and quantum experts early enough to shape document requests. Tribunals in the region generally follow the IBA Rules as guidance.
- Interest. Where the governing law or the place of enforcement restricts interest, frame late-payment losses as proven financing costs or damages and quantify them separately.
- Decennial claims. Defect claims may arise long after completion; preserve as-built records and design approvals for at least the decennial period.
- Security. Performance bonds and advance payment guarantees are often called during disputes. Injunctions against calls are difficult to obtain, so contract drafting matters.
Illustration: a hypothetical contractor on a Riyadh infrastructure project claims an extension of time and US$40 million for employer-caused delay, plus financing charges under Sub-Clause 14.8. Its counsel pleads the financing claim in the alternative as actual borrowing costs, supported by bank statements, and asks the tribunal to set out each head separately in the dispositive part. If an enforcing court later refuses a component as interest, the rest of the award remains intact. Our note on Vision 2030 giga-project disputes discusses the Saudi context further.
Subcontract chains and multi-party claims
Gulf projects often involve long chains of subcontracts, some under FIDIC-derived forms and others under bespoke terms with different dispute clauses. A main contractor that passes an employer's claim down the chain, or a subcontractor's claim up it, needs compatible clauses if it wants a single forum. The ICC Rules allow joinder, claims between multiple parties, claims under multiple contracts and consolidation where the conditions are met, but only if the arbitration agreements are compatible. Mismatched seats, institutions or languages can leave a contractor fighting the same delay event in two places with inconsistent results. Our guide to joinder and consolidation explains the conditions.
Where the employer is a public body with its own approvals regime, back-to-back drafting is harder still, and paid-when-paid clauses need checking against the governing civil code. Early mapping of every dispute clause in the chain, before a claim crystallises, is the cheapest protection available to a contractor in the middle.
Practical Checklist for GCC Construction Disputes
- Read the particular conditions first; identify every change to Clauses 1, 4, 8, 13, 14, 20 and 21.
- Identify the governing law and which civil code version applies to the contract date.
- Confirm the employer's capacity and any approval required to arbitrate.
- Map notice requirements and diarise every deadline.
- Assess mandatory rules: decennial liability, adjustment of agreed damages and interest.
- Choose a seat and institution with enforcement against the counterparty's assets in mind.
- Plan translation, experts and document management from the outset.
How TRW & Co Helps
We act for contractors, employers, consultants and funders in GCC construction disputes from our Dubai office, with support from colleagues in London, Singapore and our other network offices and with locally licensed counsel where court work is needed. We review and negotiate FIDIC particular conditions, advise on notices and claims during the project, prepare and defend DAAB referrals, and run ICC and regional arbitrations from request to award. We work closely with delay, quantum and technical experts, and we plan enforcement in the Gulf and beyond from the start. To discuss a project or dispute, please contact our team.
Frequently asked questions
Are FIDIC time bars enforceable in the Gulf?
Often, but not with the certainty of common law systems. Tribunals start from the contract, but parties invoke good faith, abuse of right and proportionality arguments under Gulf civil codes, especially where the employer knew of the event and suffered no prejudice. Contractors should comply strictly; employers should avoid conduct that suggests waiver.
Can a contractor exclude decennial liability by contract?
Generally no. Decennial liability in Gulf civil codes is mandatory protection for the owner and the public. Under the UAE regime, the contractor and architect are jointly liable for ten years for collapse and for defects threatening stability. Contracts can allocate responsibility between contractor and designer but cannot remove the statutory liability.
Will a tribunal enforce liquidated damages in full?
Not necessarily. Under UAE law, agreed compensation may be adjusted to equal the actual loss, and reports on the new 2025 Civil Transactions Law indicate that review of excessive penalties continues. Other Gulf codes contain comparable controls. Parties should be ready to prove or rebut the actual loss rather than relying solely on the agreed rate.
Do Saudi government employers need approval to arbitrate?
Yes. Article 10(2) of the Saudi Arbitration Law provides that government bodies may not agree to arbitration without approval of the President of the Council of Ministers, unless a special law allows it. Contractors should obtain evidence of approval, or of the special legal basis, before relying on an arbitration clause.
Is ICC arbitration suitable for GCC construction disputes?
It is widely used, particularly for international contractors and large projects. The ICC Court scrutinises awards and has extensive construction experience, and the ICC has a case management office in Abu Dhabi. Regional institutions are also common, and the right choice depends on the employer, seat and enforcement plan.
Sources
- Saudi Ministry of Justice: Law of Arbitration (Royal Decree M/34, 2012)
- QICDRC: Qatar Law No. 2 of 2017 Promulgating the Civil and Commercial Arbitration Law
- FIDIC: International Federation of Consulting Engineers
- ICC: 2026 Arbitration Rules (with 2014 Mediation Rules)
- WIPO Lex: Saudi Civil Transactions Law (Royal Decree M/191)
- UAE Legislation portal: Federal Decree-Law No. 25 of 2025 Promulgating the Civil Transactions Law
General information only, not legal advice. References to the ICC, the ICC Court and the ICC Rules describe their published rules and practice; TRW & Co is independent of the ICC.